May 9, 2024

The Montana Department of Transportation (MDT) and LHC Inc. have delayed construction on the northern segment of the MT 83 Swan Lake Pavement Preservation project due to poor weather. Work on Montana Highway 83 (MT 83) is expected to resume on Saturday, May 11.

From Saturday, May 11 through Friday, May 17, travelers can expect:

  • Milling and paving between mile markers 70 and 78.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.
  • Typical working hours: 7 a.m. to 9 p.m.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

May 3, 2024

The Montana Department of Transportation (MDT) and LHC Inc. continue improving the northern segment of the Swan Lake Pavement Preservation project on Montana Highway 83 (MT 83).

The week of May 6, travelers can expect:

  • Milling and paving between mile markers 70 and 78.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

April 26, 2024

The Montana Department of Transportation (MDT) and LHC Inc. are resuming construction on the northern segment of the Swan Lake Pavement Preservation project on Montana Highway 83 (MT 83) next week.

The week of April 29, travelers can expect:

  • Milling and paving between mile markers 70 and 78.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

April 19, 2024

The Montana Department of Transportation (MDT) and LHC Inc. are experiencing weather delays and expect to resume construction on the northern segment of the Swan Lake Pavement Preservation project on Montana Highway 83 (MT 83) late next week.

The week of April 22, travelers can expect:

  • Milling, paving, and signage installation to occur between mile markers 70 and 78.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

April 4, 2024

The Montana Department of Transportation (MDT) and LHC Inc. will resume construction on the northern segment of the project on Montana Highway 83 (MT 83).

The week of April 15, travelers can expect:

  • Milling, paving, and signage installation between mile markers 70 and 78.
  • Traffic control in place. Anticipate single-lane closures, short delays, temporary traffic lights, and pilot cars.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

October 6, 2023

The Montana Department of Transportation (MDT) and Knife River continue working on the southern segment of the project on Montana Highway 83 (MT 83).

The week of October 9, travelers can expect:

  • Signage installation between mile markers 47 and 53, and 65 and 71.
  • Traffic control in place. Single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars guiding traffic through mile markers 65 and 71. Expect reduced speeds throughout the project area.
  • An 11-foot width restriction in place on MT 83. Wide loads will be accommodated as needed through the Swan Lake project area.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

September 28, 2023

The Montana Department of Transportation (MDT), and Knife River continue working on the southern segment of the project on Montana Highway 83 (MT 83).

The week of October 2, travelers can expect:

  • Crews placing temporary pavement markings between mile markers 47 and 71. Final pavement markings are expected next year.
  • Bridge deck repairs occurring between mile markers 47 and 54. Repairs are expected to be complete by the end of the week.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, reduced speeds, temporary traffic lights, and pilot cars guiding traffic through the project area.
  • An 11-foot width restriction in place on MT 83. Wide loads will be accommodated as needed through the Swan Lake project area.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

September 25, 2023

The Montana Department of Transportation (MDT), and Knife River continue working on the southern segment of the project on Montana Highway 83 (MT 83).

The week of September 25, travelers can expect:

  • Signage installation between mile markers 65 and 71.
  • Bridge deck repairs between mile markers 47 and 54.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, reduced speeds, temporary traffic lights, and pilot cars guiding traffic through the project area.
  • An 11-foot width restriction in place on MT 83. Wide loads will be accommodated as needed through the Swan Lake project area.
  • Other construction projects on MT 83 have traffic control and width restrictions in place. Be prepared for delays before you leave, download MDT’s mobile app “MDT 511” or visit 511mt.net and check your route. If you're driving and want to check in, pull safely off the road and dial 511. Tune in to local radio stations and watch for variable message signs along the route.

September 14, 2023

The Montana Department of Transportation (MDT), and Knife River continue working on the southern segment of the project on Montana Highway 83 (MT 83).

The week of September 18, travelers can expect:

  • Paving between mile markers 65 and 71.
  • Signage installation between mile markers 47 and 54.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars guiding traffic through the project area.
  • An 11-foot width restriction in place on MT 83.

September 8, 2023

The Montana Department of Transportation (MDT), and Knife River continue working on the southern segment on Montana Highway 83 (MT 83).

The week of September 11, travelers can expect:

  • Paving between mile markers 65 and 70.
  • Milling and paving between mile markers 47 and 53, scheduled to occur late in the week, weather and other factors permitting.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars guiding traffic through the project area.
  • An 11 foot width restriction in place on MT 83.

August 31, 2023

The Montana Department of Transportation (MDT), LHC Inc., and Knife River continue working on both project segments on Montana Highway 83 (MT 83). Crews will pause for the Labor Day holiday weekend beginning Saturday, September 2, and resume work on Tuesday, September 5.

The week of September 4, travelers can expect:

  • Paving to begin on the southern segment between mile markers 65 and 70.
  • Milling and paving to begin on the northern segment between mile markers 70 and 78.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, temporary traffic lights, and to be guided through the project area by pilot cars.

August 24, 2023

The Montana Department of Transportation (MDT) and Knife River continue working on the southern segment of the Montana Highway 83 (MT 83) Pavement Preservation project. The week of August 28, crews will be working between mile markers 70 and 65, and 53 and 47, weather permitting.

Travelers can expect:

  • Pavement sealing beginning.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, temporary traffic lights, and to be guided through the project area by pilot cars.

The milling and paving work for the northern segment is planned for early next month.

August 18, 2023

The Montana Department of Transportation (MDT) and Knife River plan to start work on the southern segment of the project the week of August 21, weather permitting. Crews will be working between mile markers 70 and 65, and 53 and 47 on Montana Highway 83 (MT 83).

Travelers can expect:

  • Pavement removal beginning.
  • Traffic control in place, including single-lane closures, 10 to 15-minute delays, temporary traffic lights, and to be guided through the project area by pilot cars.

The milling and paving work for the northern segment is planned for early next month.

August 11, 2023

The Montana Department of Transportation (MDT) and LHC Inc. plan to work on the northern segment of the project near the lake, weather permitting. Crews are working between mile markers 70 and 78 on Montana Highway 83 (MT 83).

The week of August 14:

  • Guardrail work is nearing completion along the west side of the highway, closest to the lake.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.

The next phase of the project includes milling and paving work, which is planned for later this month.

August 3, 2023

The week of August 7, the Montana Department of Transportation (MDT) and LHC Inc. anticipate working on the northern segment of the project near the lake, weather permitting. Crews are working between mile markers 70 and 78 on Montana Highway 83 (MT 83).

Drivers should expect:

  • Guardrail removal and installation along the west side of the highway, closest to the lake.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.

July 28, 2023

The week of July 31, the Montana Department of Transportation (MDT) and LHC Inc. anticipate working on the northern segment of the project near the lake, weather permitting. Crews are working between mile markers 70 and 78 on Montana Highway 83 (MT 83).

Drivers should expect:

  • Guardrail removal and installation along the west side of the highway, closest to the lake.
  • Traffic control in place. Anticipate single-lane closures, 10 to 15-minute delays, temporary traffic lights, and pilot cars.

July 21, 2023

The week of July 24, The Montana Department of Transportation (MDT) and LHC Inc. anticipate working on the following, weather permitting:

Between mileposts 70 and 78 on Montana Highway 83 (MT 83):

  • Guardrail work continues.
  • Expect single-lane closures. Temporary traffic lights and pilot cars will assist drivers through the project area. Be prepared for delays of 10-15 minutes.

July 14, 2023

The week of July 17, The Montana Department of Transportation (MDT) and LHC Inc. anticipate working on the following, weather permitting:

North segment: On MT 83 beginning just north of Bond Creek and extending approximately 5 miles, ending just north of Soup Creek Road.

  • Guardrail work begins.
  • Expect single-lane closures. Temporary traffic lights and pilot cars will assist drivers through the project area. Be prepared for delays.

July 7, 2023

The Montana Department of Transportation (MDT), LHC Inc., and Knife River are improving roughly 19 miles of Montana Highway 83 (MT 83) near Swan Lake. Crews anticipate working on the following, weather permitting:

1. North segment: beginning just north of Bond Creek and extending for approximately 5 miles, ending just north of Soup Creek Road.

Week of July 17:

  • Traffic control placement.
  • Preparations underway for pavement removal, requiring single-lane closures. Temporary traffic lights and pilot cars will assist drivers through the project area. Be prepared for delays.

2. South segment: beginning north of Lion Creek bridge, extending to the Lake/Missoula County line.

  • Work is anticipated to begin mid-August.