Contractor's System Project Question and Answer Forum

BULLETIN BOARD                                                                                                                                                                                              

______________________________________________________________________________________________________________________________________________________________________________
MDT will be hosting Pre-Bid Networking Conferences in each district. MDT staff, airport consultants, and transit providers will be available to talk about upcoming projects in the district. Prime contractors, subcontractors, and suppliers interested in transportation related work are encouraged to attend and network with one another. Attendance at this conference may entitle you to ten extra contract days on eligible large projects throughout the year in the corresponding district.

  • District 4: October 17th at 3:00 pm at the Sleep Inn (1006 S Haynes Ave, Miles City)
  • District 1: November 18th at 2:00 pm at the Hampton Inn (1140 2nd St W, Kalispell)
  • District 3: January 24th at 8:00 am at Best Western Premier Helena Great Northern Hotel (835 Great Northern Blvd, Helena)
  • District 2: February 13th at 3:00 pm at the LaQuinta Inn (1 Holiday Park, Butte)
  • District 5: March 2025 – Billings: more details coming soon

_____________________________________________________________________________________________________________________________________________________________________________________________
2025 Letting Schedule: LINK

__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Watch - Public Bid Opening - Live Stream: ZOOM MEETING INFORMATION

__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Advertised Projects: If you would like to receive the Invitation for Bids PDF document when projects are advertised, please send an email request to mdtcps@mt.gov. Follow the link for more information: EMAIL DISTRIBUTION
___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

101 - D1 GUARDRAIL & FENCING (I-90) - November 14, 2024

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 13-NOV-2024 09:29 AM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express Secure Internet Bidding


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Thursday 24-OCT-2024 07:43 AM
Company: Montana Fence Company
Contact: Jim Ritter
Regarding bid items 607100149, 607100202, 607100259, 607100360 and 607100380. The state has asked for wood line posts and brace panels to 'match existing'. It's our professional opinion that there is greater benefits to switch from wood posts to steel line posts and steel panels [MDT Drawings 607-05] as compared to 'matching existing' and we ask the state to consider a change. Here are our reasons:
1. the project sites are in mountainous fire corridors putting the fencing at risk to burning - we have been replacing fire-burned wood fences around the state of Montana with steel fences and panels and believe it would be wise to do so on this project.
2. Steel posts will not rot or decay.
3. Steel posts tend to pound in, through and around the rocks and roots in this mountainous terrain while wood posts tend to explode while pounding.
4. Steel fence is easier to maintain. Will the state consider a change to these bid items?
Answer
Submitted: Tuesday 29-OCT-2024 02:35 PM
After consideration, the Department will accept the requested changes.
Plan sheets have been updated and can be viewed here: PLANS
Bid Item 607 100 152  FARM FENCE-TYPE F3M-32 IN WW is hereby increased to 202,224.0 LNFT.
Bid Item 607 100 281  FARM FENCE-TYPE F5M is hereby increased to 86,015.0 LNFT.
Bid Item 607 100 219  FARM FENCE-TYPE F3M is hereby added to the contract at a quantity of 6,837.0 LNFT.
Bid Item 607 100 362  FARM FENCE-PANEL/SINGLE FM is hereby added to the contract at a quantity of 463.0 EACH.
Bid Item 607 100 385  FARM FENCE-PANEL/DOUBLE FM is hereby added to the contract at a quantity of 227.0 EACH.

The following items are hereby deleted from the contract:
Bid Item 607 100 149  FARM FENCE-TYPE F3W-32 IN WW
Bid Item 607 100 202  FARM FENCE-TYPE F3W
Bid Item 607 100 259  FARM FENCE-TYPE F5W
Bid Item 607 100 360  FARM FENCE-PANEL/SINGLE FW
Bid Item 607 100 380  FARM FENCE-PANEL/DOUBLE FW

An amendment will be issued, updated bid files will be posted.

-2-
Submitted: Tuesday 29-OCT-2024 11:08 AM
Company: Montana Fence Company
Contact: Jim Ritter
After having visited the site and analyzed fencing plans we believe that 150 working days is not sufficient to properly complete the scope of this project. The mountain corridor location presents challenges that will slow progress and reduce overall speed. We believe an amendment to increase the work days to 220 would be more realistic to handle the scope of the project. Would the state please consider this change?
Answer
Submitted: Thursday 31-OCT-2024 11:28 AM

An additional 70 working days is hereby added to the contract for a total of 220 days.  Special Provision 2. Contract – Flex Time Proceed Date is hereby replaced with the following updated special provision: CONTRACT TIME - FLEX TIME PROCEED

-3-
Submitted: Friday 01-NOV-2024 04:06 PM
Company: Montana Fence Company
Contact: Jim Ritter
Due to the dense overgrowth and tree falls along this corridor, there is a tremendous amount of clear clearing on the fence line required for this project. Would the state prefer trees and brush to be left in place after clearing or would the state prefer materials to be mulched and broadcast?
Answer
Submitted: 08-NOV-2024 11:20 AM
The following special provision is hereby added to the contract:
TIMBER CLEARING AND DECKING
In addition, Special Provision 18. Eagle Protection and Conservation is hereby replaced with the following special provision: EAGLE PROTECTION AND CONSERVATION
Bid Item #201 130 000 CLEARING AND GRUBBING is hereby added to the contract at a quantity of 1.0 LS.

An amendment will be issued, updated bid files will be posted.

-4-
Submitted: Thursday 07-NOV-2024 03:26 PM
Company: Coral Construction Company
Contact: Kris Karpstein
Can lane closures be left in place when workers are not present or will it be required to remove and replace daily the traffic control based on area of work?
Answer
Submitted: Friday 08-NOV-2024 08:55 AM
Remove traffic control when workers and/or hazards are not present.  Remove and store unused traffic control devices in approved staging areas outside of the clear zone. If hazards exist over night that cannot be mitigated, provide traffic control and set the work zone speed limits according to Table 618-5 in the standard specifications.

-5-
Submitted: Thursday 07-NOV-2024 03:24 PM
Company: Coral Construction Company
Contact: Kris Karpstein
What other contracts will be going on in the same areas that we may need to coordinate lane closures with?
Answer
Submitted: Friday 08-NOV-2024 11:05 AM
Coordinate the D1 Guardrail and Fencing (I-90) with other contractors working on projects along I-90, including, but not limited to, UPN 9839000 SF 199 Msla HT Median Cable Rail (RP 55.4 – 58.4) and UPN 10303000 SF 209 Missoula South Signs (RP 17.0 – 58.2, various locations).  Priority will be given to these projects if there is a scheduling conflict.  Contract time will be suspended at the discretion of the Project Manager if the coordination of the work with these projects results in a delay to the project.

102 - GREENOUGH HILL - NORTH - November 14, 2024

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 13-NOV-2024 09:32 AM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express Secure Internet Bidding


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Wednesday 30-OCT-2024 08:12 AM
Company: HighMark Traffic Services, Inc.
Contact: Bradley Meyer
Can you verify the quantity for PMS Joint Seal is correct? Special Provision 26 Joint Seal calls for for 3 joints full length 2' wide which does not calculate to the quantities in the plans.
Answer
Submitted: Thursday 31-OCT-2024 03:26 PM
Bid Item # 403010235 – PMS JOINT SEALING is hereby increased to 11,938 SQYD.

Sheet 4 of the road plans has been revised and can be found here: SHEET 4
An amendment will be issued, updated bid files will be posted.
Update
Submitted: Friday 01-NOV-2024 11:50 AM

This quantity reflects three joint seals for typical 1, and two joint seals for typical 2.

-2-
Submitted: Tuesday 05-NOV-2024 03:16 PM
Company: Knife River
Contact: Estimator
Can you clarify SP #29 in regard to the stockpile/windrow of millings. Where exactly are these millings to be put and are they to be stockpiled or put in a windrow. If windrowed how far down the road (assuming Sunset Hill Rd) are we needing to windrow this material?
Answer
Submitted: Thursday 07-NOV-2024 07:53 AM
Windrow the millings on Sunset Hill Road between the end of pavement near Paws Up to the intersection with Elk Flats Road.  The county will grad the millings on the road during placement.

103 - BARRETTS - DILLON - November 14, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Thursday 07-NOV-2024 01:27 PM
Company: Riverside Contracting, Inc.
Contact: Cale Fisher
SP #25 specifies the construction of shoofly detours at the Jackson Interchange and SP #19 notes the same locations have been identified as apparent aquatic resources. As MDT has not provided a detail for the detour nor a layout to show the location in relation to the apparent aquatic resources has MDT verified the detours can be constructed at these locations without impacting the aquatic resources?
Answer
Submitted: Wednesday 13-NOV-2024 09:13 AM
SP#25 requires the construction of shoofly detours.  These are temporary in nature with the design being the responsibility of contractor.  As indicated in SP#19 wetlands are anticipated to exist in the vicinity of the Jackson Interchange.  If the contractor’s shoofly design requires temporary impacts to aquatic resources, the contractor would be required to obtain any necessary permits.  Generally temporary wetland impacts are permitted under section 404 of the clean water act under a nationwide permit 33, which does not require preconstruction notification unless the temporary fill is being placed in a navigable water of the US.  All general and regional conditions found here:  
https://www.mdt.mt.gov/business/contracting/docs/env/2021/2021-NWP-33-FS-all-BMP-RC-SRMZ.pdf must be followed when using Nationwide permit 33.  Montana Regional condition B.3. requires that temporary fills in wetlands must be placed on a horizontal marker layer, such as fabric or certified weed-free straw, to delineate the pre-project ground elevation and facilitate complete fill removal and site restoration. 

In accordance with SP#19 the contractor should submit an Aquatic Resource Protection Plan to the Project Manager and DEES detailing the BMPs or alternate methods proposed for each location (Including call out a horizontal marker layer as explained above).

104 - LIBBY AIRPORT - N & S (S-482) - November 14, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

105 - US 93 & TREELINE ROAD (KAL) - November 14, 2024

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 13-NOV-2024 09:34 AM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express Secure Internet Bidding


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Friday 08-NOV-2024 01:27 PM
Company: Montana Lines, Inc.
Contact: Pat Bomgardner
The existing traffic signal indications at this intersection may already have retro-reflective borders. Please clarify the intent of bid item 617533000, SIG-TRAF-BACKPLATE-REFLECTIVE.
Answer
Submitted: Tuesday 12-NOV-2024 10:48 AM
Bid item # 617533000 SIG-TRAF-BACKPLATE-REFLECTIVE qty 5 EA is hereby removed.

Sheet E1 of the electrical plans has been revised and can be found here: SHEET E1

An amendment will be issued, updated bid files will be posted.

-2-
Submitted: Friday 08-NOV-2024 01:46 PM
Company: Montana Lines, Inc.
Contact: Pat Bomgardner
Item 617000000, FOUNDATION-CONCRETE, has a bid quantity of 5.6 CUYD. This captures only the quantity needed for pole 7. Please clarify.
Answer
Submitted: Tuesday 12-NOV-2024 10:50 AM
Bid item # 617000000 FOUNDATION-CONCRETE is hereby increased to 8.03 CUYD.

Sheet E1 of the electrical plans has been posted and can be found in response to Question #1 above.

An amendment will be issued, updated bid files will be posted.

106 - SOUTH OF PLEVNA - SOUTH - November 14, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Monday 4-NOV-2024 09:27 AM
The following Mastic Crack Seal & Pavement Repair special provision is hereby added to this contract: MASTIC CRACK SEAL & PAVEMENT REPAIR


Questions

No Questions available for this project.

107 - NYHAGEN RD PATH - CUT BANK - November 14, 2024

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 13-NOV-2024 09:35 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express Secure Internet Bidding


Clarifications

-1-
Submitted: Tuesday 22-OCT-2024 09:11 AM
The following special provision hereby replaces special provision #15 CONTRACTORS SURVEYING AND LAYOUT – DEPARTMENT STAKING: CONTRACTORS SURVEYING AND LAYOUT – DEPARTMENT STAKING


Questions

-1-
Submitted: Wednesday 06-NOV-2024 04:34 PM
Company: Alpine Sign Inc
Contact: John
On Sheet S2 of the Sign Location and Specification shows Station 111+23.60 LT as Sheet Aluminum XI on two 5" wood posts. Shouldn't this be an Increment Type XI ?
Answer
Submitted: Tuesday 12-NOV-2024 03:30 PM
Bid item #619 010 090 SIGNS-ALUM REFL SHEET XI is hereby decreased to 90 SQFT.

Bid item #619 010 062 SIGNS-ALUM SHEET INCR XI – qty 21 SQFT, is hereby added.

Sheet S1 and S2 of the signing plans have been revised and can be found here: SHEET S1 & S2

An amendment will be issued, updated bid files will be posted.

108 - SF 209 GREAT FALLS DISTRICT SIGNS - November 14, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

101 - WEST OF JORDAN - WEST - December 05, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Thursday 14-NOV-2024 01:18 PM
Company: montana fence
Contact: larry iverson
Referencing fencing drawing 607-10, it is written that we can install single panels up to 660' and double panels up to 990'. This project has only 4411' of barbed wire fence. It is also asking for 51 single panels and 5 double panels. Is there chance to get drawings with the fencing on them to analyze the needs?

-2-
Submitted: Monday 18-NOV-2024 08:15 AM
Company: Riverside Contracting Inc.
Contact: Dennis Devous
Can you tell me the existing section of the project? Are there cores taken in the existing roadway?

-3-
Submitted: Tuesday 19-NOV-2024 03:45 PM
Company: Riverside Contracting Inc.
Contact: Dennis Devous
With the combinations of Bridge work with all the Dig outs set up on the project there is not enough time set up to get it all done in the stated the Contract Time. We feel you need to add 60 days to the Contract. Please add the 60 days to the Contract Time.

102 - WHITE SULPHUR SPRINGS - SOUTH - December 05, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

103 - SIGNALS - ANACONDA & DEER LODGE & MAIN ST - DEER LODGE & ANACONDA - URBAN - December 05, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Thursday 07-NOV-2024 10:16 AM
This project is being re-advertised. Changes may have been made to the prior bid package. If you submitted a question when this project was previously advertised and believe your question is still applicable, please ask the question on the Q&A forum again. By doing so, your question and MDT’s corresponding answer will become part of the contract.


Questions

No Questions available for this project.

104 - SF 209 MISSOULA NORTH SIGNS - December 05, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

105 - SF 209 BUTTE DISTRICT SIGNS - December 05, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

106 - PENNSYLVANIA WALKS - ANACONDA - December 05, 2024

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Thursday 07-NOV-2024 10:16 AM
This project is being re-advertised. Changes may have been made to the prior bid package. If you submitted a question when this project was previously advertised and believe your question is still applicable, please ask the question on the Q&A forum again. By doing so, your question and MDT’s corresponding answer will become part of the contract.


Questions

No Questions available for this project.

301 - TIMBER BRIDGES - FORSYTH AREA - December 18, 2024

Notifications

-1-
Submitted: Wednesday 03-JUL-2024 11:21 AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on July 31, 2024.

Project Name:   TIMBER BRIDGES-FORSYTH AREA
Project No.:        STPB 14-6(23)235
Control No.:       9886000


This project includes design and construction services required to design and reconstruct fourteen (14) existing timber bridges along US Highway 12 northwest of Forsyth, Montana.  The project involves replacing the aging and deteriorating timber bridges with new structures and will reconstruct the adjacent roadways as necessary.


The project RFQ and attachments can be found at the following link:   RFQ
                                                                                                               ATTACHMENT A
                                                                                                               ATTACHMENT B
                                                                                                               ATTACHMENT C

-2-
Submitted: Friday 16-AUG-2024 07:00 AM
Short-Listed Firms:
Century/KLJ
Frontier West/RPA/Morrison-Maierle
Riverside/DOWL

-3-
Submitted: Thursday 29-AUG-2024 03:42 PM
Meeting minutes from the Pre-proposal meeting held on 8/27/2024 can be found at this link: PRE-PROPOSAL MEETING MINUTES


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Friday 27-SEPT-2024 07:00 AM
Phase 1 documentation allowing steel as a pipe material option is rescinded.  No CSP, CSPA, SSPP, or SSPPA will be allowed with this project, regardless of backfill material non-corrosiveness.

-2-
Submitted: Tuesday 01-OCT-2024 08:13 AM
The Activity 144 Right of Way Plan Revisions are complete and can be found at the following link: Activity 144 Right of Way Plan Revisions
A minor revision from the Activity 142 Right of Way Plans was addressed in the Activity 144 submittal.  The minor revision is located at Site 05505 and was revised to acquire slightly less property.

-3-
Submitted: Tuesday 15-OCT-2024 12:38 PM 
Detours must be designed and constructed to meet 35mph design speed standards.  The Phase 1 Preliminary Plans conceptual detour layouts are designed to 35mph design speeds.

-4-
Submitted: Wednesday 16-OCT-2024 10:06 AM
Structure 05504 (Horse Creek) proposed superstructure must have a low cord elevation of no less than 2716.3’ for purposes of effective wildlife permeability.  Floodplain requirements, hydraulic performance, and other governing criteria must still be considered in the final design and permitting.

-5-
Submitted: 18-OCT-2024 11:28 AM
For structure 05496, outlet velocity must not exceed 9.0 ft/s during the 10-year event.

-6-
Submitted: Thursday 24-OCT-2024 02:56 PM
9886000SUCADZ31.dwg is rescinded from the RFP attachments and replaced with 9886000SUCADZ31.dwg.  The Right of Way boundary within a parcel in Block 1 of the original townsite of Vanada east of Bridge 05505 was revised in the updated SUCADZ31.dwg file.  The revision to the boundary provides more highway Right of Way than the original SUCADZ31.dwg file.

-7-
Submitted: Tuesday 29-OCT-2024 01:25 PM
The Quality Control Manager is required to provide statements within 10 working days upon completion of each item bulleted below, for each structure.  The Quality Control Manager is to state whether the work was constructed in accordance with the design, MDT Standard Specifications, and Contract Documents.  The Firm does not have the authority to accept non-conforming work.  The Firm is responsible for proposing repair, mitigation, or other resolution for non-conforming work.

    • Beam Seats (elevation flat, level?)
    • Bearing Devices (fiber pads, condition, orientation, full bearing contact, conformance to plan/shop drawing details?)
    • Anchor bolts (location, depth/elevation, grouting, anchor nuts conforming?)
    • Steel Bolting (conforming to plan/shop drawing details and bolt tensioning requirements?)
    • Precast Prestressed Deck Sections leveling and jacking. (within required tolerance?)
    • Weld Ties (per details, welding requirements?)
    • Grouted Keyways (grout mixed and cured per product instructions, flush with deck surface?)
    • Deck surface (finish, cross-slope, draining properly?)
    • Finished profile grade of bridge approaches.
    • Cleanup of bridge caps, spilled concrete, excess epoxy/grout, work site.

-8-
Submitted: Thursday 31-OCT-2024 09:08 AM
All Parcels for the project have been field closed by MDT Right of Way.  Right of Way Agreements contain contract requirements for fence type/locations and landowner coordination.  Right of Way Agreements can be found here: 9886000_ROW_Agreements.  Firms must thoroughly review, understand, and provide all requirements stated in the Right of Way Agreements.

-9-
Submitted: Thursday 14-NOV-2024 08:43 AM
Commercial Mix-PG 58V-34 is hereby rescinded from the contract requirements and replaced with Commercial Mix-PG 58H-34.


Questions

-1-
Submitted: Wednesday 28-AUG-2024 09:53 AM
Company: KLJ Engineering
Contact: Dan Richardson
RFP Section IV.M.9 Hydraulics.  Can you discuss what will be required to be stamped for hydraulics if culvert sizes and bridge sizes remain the same as designed in the bridging documents?
Answer
Submitted: Thursday 05-SEPT-2024 06:57 AM
If the Firm changes the hydraulic performance of the site, the Firm must update the hydraulic modeling and stamp the updated hydraulic report associated with the site.  A general list of changes that could affect hydraulic performance, but are not limited to, is provided in Section IV., Part I., Bullet 3.d of the Project RFP.  Changes to the hydraulic performance of a structure will require MDT review and approval through the ATC process. 

At proposed bridge sites, if the Design Build Firm agrees to the Phase 1 recommendation, they will need at a minimum a stamped memo documenting: 1) the new abutment scour requirements, and 2) the bridge deck drain design.

-2-
Submitted: Wednesday 28-AUG-2024 09:53 AM
Company: KLJ Engineering
Contact: Dan Richardson
RFP Section IV. O.1 Utilities states “A new fiber line is being installed adjacent to the project as described in the Phase 1 Bridging Documents. As Built survey for this new fiber line has not been completed.”  Has this been completed so we can account for it on our bid price and ultimately in our final design?
Answer
Submitted: Tuesday 03-SEPT-2024 12:17 PM

Intermountain Infrastructure Group (IIG) is the utility owner for this new fiber line and completing installation under permit ending 40066.  Installation of the new fiber line is not complete and as-built information has not been submitted.   IIG was provided with Phase 1 Engineering construction limits when finalizing their route and are expected to remain clear of the project.  As-built information will be provided as a notification to the Q&A forum when available.

-3-
Submitted: Wednesday 28-AUG-2024 10:02 AM
Company: KLJ Engineering
Contact: Dan Richardson
RFP Section IV.P.2 Environmental and Permitting states “Cultural resource information is included in Attachment Q…. The Cultural Resources Consultation letters, and any cultural do not disturb areas, will be provided to the Firm after award.”  Can you direct us to which section of Attachment Q these are located and secondly, are there other areas that were not identified in the Bridging Document Plans as “do not disturb areas” that will be provided after the award?  This would aid in identifying if there are constraints that may affect the bid price and design.
Answer
Submitted: Tuesday 03-SEPT-2024 12:22 PM

The Cultural Resources Report and Cultural Resources Report Addendum will be provided to the  successful Firm after award. These documents were intentionally not transmitted to all Firms and will not be found within Attachment Q.  All Do Not Disturb (DND) areas resulting from the Cultural Investigations can be found in the Preliminary Plans (Attachment Q-016) and associated DWG files (Attachment Q-036).  No additional DND areas will be provided after award.

-4-
Submitted: Wednesday 28-AUG-2024 10:04 AM
Company: KLJ Engineering
Contact: Dan Richardson
RFP Section VI.A.5. The Q/A Forum closes 7 days prior to the Technical Proposal due date. Would MDT be willing to re-open the Q/A after the Technical Proposals are submitted for any bidding questions?
Answer
Submitted: Friday 30_AUG-2024 01:57 PM
The Q&A Forum will close 7 days prior to the Technical Proposal due date and will not re-open for questions after Technical Proposals are submitted.  MDT may post clarifications and notifications on the Q&A Forum no later than 5:00PM the day before bid price proposals are due.

-5-
Submitted: Thursday 29-AUG-2024 12:22 PM
Company: Morrison-Maierle
Contact: Jim Scoles
Please clarify who is conducting Right-of-Way fencing negotiations.  It has been noted that MDT is acquiring Right-of-Way identified through the Phase 1 Engineering Effort.  However, for sites where there is no acquisition, who is responsible for coordinating fencing agreements?  For example, if we disturb fence but are not changing Right-of-Way acquisition limits, who is handling fencing agreements?
Answer
Submitted: Tuesday 03-SEP-2024 04:15 PM
MDT will be responsible for negotiating and obtaining fencing agreements with Landowners.  For parcels where only fencing will be disturbed (negotiation only parcel), the Firm must notify the Glendive District Right-of-Way Supervisor a minimum of 8 weeks prior to removal of the fence to allow time for negotiations and agreements to be complete prior to placement of new fence.

-6-
Submitted: Thursday 29-AUG-2024 12:23 PM
Company: Morrison-Maierle
Contact: Jim Scoles
Relating the Technical Proposal requirements section, what are the expectations with the limited number of 11”x17” sheets allowed in the schedule and plan sheets sections?  There are some aspects of the RFP that imply additional information is required to be provided in these sections (bridge foundation plan and list of baseline schedule items).  Is it MDT’s expectation to have a fully detailed schedule with all major and minor activities or more of a rollup condensed schedule showing major activities?
Answer
Submitted: Tuesday 3-AUG-2024 01:05 PM
For the two 11”x17” sheets allowed in the schedule section, MDT would like to see a condensed schedule showing major design and construction activities. Page 19 of the RFP provides a list of the minimum activities that must be included in the schedule if applicable to the project.  For the twenty 11”x17” sheets in the preliminary plans section, MDT would like to see fourteen Road Plan and Profile Sheets showing the proposed structure for each site and six Bridge Plan sheets which consist of a general layout, footing plan, and transverse section for each of the two proposed bridges.

-7-
Submitted: Thursday 29-AUG-2024 02:43 PM
Company: Riverside Contracting
Contact: Stacy Hill
Please clarify who is responsible for obtaining the floodplain permit? The floodplain permitting was not covered in the Environmental and Permitting section of the RFP.  Often times with floodplain permitting, the SPA 124 permit and CWA 404 permit must be obtained prior to submitting the floodplain permit application.
Answer
Submitted: Thursday 05-SEPT-2024 07:02 AM

The Firm will be responsible for filling out the joint application, signing the joint application as the Applicant and as the Landowner on behalf of MDT, applying for the permit, application fees, obtaining the floodplain permit, renewing the floodplain permit, if required, during construction, and providing any required post construction documentation to the floodplain administrator.  Please check with the floodplain administrator, often on MDT projects a floodplain permit can be issued, conditionally upon receipt of the SPA 124 and CWA 404. 

-8-
Submitted: Friday 30-AUG-2024 03:26 PM
Company: Riverside/DOWL
Contact: Matthew James Mettler
The Phase I bridging documents 26-Hydraulics Reports and Models are missing the 05496 crossing data. The information included in the folder is duplicate data for the 05498 crossing. Can we get a copy of the report, model and associated supporting files?
Answer
Submitted: Tuesday 03-SEP-2024 01:46 PM

Site 05496 Hydraulics reports, model, and data: 9886000HYCPZ02

-9-
Submitted: Friday 30-AUG-2024 03:27 PM
Company: Riverside/DOWL
Contact: Matthew James Mettler
The SRH-2D model for the 05507 crossing is missing. Can we get a copy of the hydraulic model?
Answer
Submitted: Tuesday 03-SEP-2024 01:15 PM
Site 05507: SMS-SRH2D model:
9886000HY2DMZ11

-10-
Submitted: Thursday 05-SEP-2024 08:23 AM
Company: DOWL, LLC
Contact: Matthew James Mettler
There is conflicting information from the ROW document and TS&L report that crossing 05507 and 05512 on the perpetuation of the stock pass function. For the technical proposal, should we assume these crossings will be sized to meet hydraulic requirements, not for stock pass?
Answer
Submitted: Wednesday 11-SEP-2024 08:21 AM
Structures 05507 and 05512 should be sized to meet hydraulic requirements, not stockpass usage. MDT District ROW is in the process of negotiating stockpass terminations and fencing agreements at both sites.

-11-
Submitted: Monday 30-SEP-2024 09:44 AM
Company: Frontier West LLC
Contact: Kris Anderson
Structure ID 05508: Sheet No. 44 (Hydraulic Data Table) shows 54” RCP or 54” CSP. Sheet No. 45 shows 6’ x 7’ concrete culvert. Sheet No. 58 appears to show a 54” culvert. Sheet No. 72 shows a 6’ x 7’ concrete culvert. Various reports note both round pipes and variously sized RCB culvert structures. Would MDT please confirm the Structure ID 05508 bridging documents size and provide the minimum vertical and horizontal clearance if a stock crossing is required?
Answer
Submitted: Monday 07-OCT-2025 12:43 PM
The 54” diameter pipe was the minimum hydraulic opening.  Per landowner negotiations, site 05508 will need to be a stockpass that can fit an inscribed 6’ wide by 6’ tall square.  Phase 1 recommended a conceptual 6’ span x 7’ rise RCB stockpass with 1’ of infill material.  Provide a stockpass opening with a minimum 6’ vertical rise as measured from the top of infill material to bottom of ceiling, and a minimum 6’ span as measured from inside of wall to inside of wall. Up to 12”x12” top haunches (chamfers) of box culverts are allowed to protrude into the inscribed 6’x6’ square.

-12-
Submitted: Monday 30-SEP-2024 09:45 AM
Company: Frontier West LLC
Contact: Kris Anderson
Would MDT please confirm whether Spread Width is allowed to encroach into the travel lanes on for structures 05504 and 05505? The Design-Build Bridging Documents are inconsistent regarding the approved Spread Width and whether encroaching into the travel lanes to avoid discharge within the ordinary high water mark (OHWM) is an approved design deviation from the Bridge Design Specifications and MDT Hydraulic Manual. Generally, written narratives in the Bridging Documents describe deck drainage configured such that Spread Width does not encroach into the travel lanes at the bridges. However, the Bridge Plans show deck drainage spacing which results in Spread Width which does encroach into the travel lanes and avoids discharge within OHWM. Would MDT please verify that 2.7’ of spread with is approved at structure 5504 and 2.6’ of spread width is approved at 5505?
Answer
Submitted: Monday 07-OCT-2024 08:22 AM
Maximum allowable spread width is defined in Figure 14.3-1 of the Hydraulics Manual, and is stated in the Hydraulic Reports and Bridge TS&L Reports for sites 05504 and 05505, as being equal to the shoulder width. Any proposed deviation from this requirement will need to be presented as an ATC.  Discharge must meet the requirements of DEQs 401 certification which states “all permittees shall, to the maximum extent practicable, incorporate and construct design features that eliminate bridge deck run-off containing sediment, salt, or other pollutants from discharging directly into state water”.

-13-
Submitted: Monday 14-OCT-2024 11:04 AM
Company: Riverside Contracting, Inc.
Contact: Russ Gaub
Special Backfill for box culverts on sheet 45 of the plans states "When Specified". The prelininary estimates for each site do not have quantities specified for special backfill except for the 84" RCP. The crosss sections indicate some locations require special backfill with no quantity specified. Please verify whether or not special backfill is required for all box culverts.
Answer
Submitted: Friday 18-OCT-2024 12:37 PM
All culverts require either special backfill or non-corrosive special backfill based on site specific soil corrosivity.  Per MDT Hydraulics Manual 11.6.2.5.1 and Figure 11.6-4, non-corrosive backfill is required if soil resistivity is less than 300 ohm-cm, or if pH is less than 6.  The awarded Firm must develop a special provision for sites requiring non-corrosive special backfill.  Minimum design life for the concrete pipes must be met.

-14-
Submitted: Wednesday 23-OCT-2024 01:26 PM
Company: DOWL, LLC
Contact: Matt Mettler
The RFP requires a minimum font size of 10 for development of the Technical Proposal. This is certainly achievable for the narrative and other content with exception to publishing a 2-page Gantt Chart with adequate clarity to demonstrate knowledge of the project and the critical path. This has been challenging even using an 11x17 sheet size. Will MDT allow a smaller font size for the schedule?
Answer
Submitted: Thursday 24-OCT-2024 02:53 PM
A minimum font size 5 can be used for the 11" x 17" sheets allowed in the schedule section of the Technical Proposal.

-15-
Submitted: Wednesday 30-OCT-2024 08:10 AM
Company: RPA
Contact: April Gerth
The PKT files used to develop the corridors don't appear to have been included in the bridging documents. Can these be provided or can we be directed to where they are in the documents?
Answer
Submitted: Thursday 31-OCT-2024 02:17 PM

PKT files used for the Phase 1 Analysis are included in the following link: 9886000_PKT_Files

-16-
Submitted: Thursday 14-NOV-2024 01:58 PM
Company: Frontier West
Contact: Kris Anderson
Technical Proposal Page Limit, VI.B: Are the 20 plan sheets in the Preliminary Plans subsection included in the 40 page limit? If yes, can the total proposal limit be changed to 60?
Answer
Submitted: Friday 15-NOV-2024 11:48 AM
The 20 plan sheets in the Preliminary Plans subsection are included in the 40 pages/sheets Technical Proposal limit.  Pursuant to page 6 of the Pre-Proposal Meeting minutes,  additional pages/sheets will not be allowed.

502 - SF 179 EAGLE PASS TRAIL SAFETY / US-93 WILDLIFE OVERPASS / US-93 NORTH NINEPIPE - January 15, 2025

Notifications

-1-
Submitted: Wednesday 02-OCT-2024 12:30 PM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Progressive Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on Wednesday, October 23, 2024

Project Names:   SF 179 EAGLE PASS TRAIL SAFETY
                             US-93 WILDLIFE OVERPASS
                             US-93 NORTH NINEPIPE

Project No:          HSIP STWD(762)
                             SSS 5-2(204)41
                             SSS 5-2(202)41

Control No:         9614001
                            10567000
                            10568000


The proposed tied Project will reconstruct approximately 3.7 miles of US Highway 93 from south of Eagle Pass Trail to Brooke Lane in the Ninepipe area (RP 40.8 to 44.5).  The Project will include construction of three new highway bridges, a wildlife overpass, shared use path facility, wildlife fencing and other accommodation features, intersection improvements, a widened typical section, and drainage upgrades.  The Project is intended to improve connectivity and safety in a culturally and environmentally significant area.

The project RFQ and attachments can be found at the following link: RFQ & ATTACHMENTS

-2-
Submitted: Tuesday 08-OCT-2024 02:42 PM
FHWA formally approved PDB delivery and MDT’s qualifications-focused selection approach described in the RFQ for the subject tied projects (UPNs 9614001, 10567000, 10568000) on October 4, 2024.

-3-
Submitted: Wednesday 06-NOV-2024 10:23 AM
Short-listed Firms (in alphabetical order):
-Kiewit Infrastructure Co. / Michael Baker International / WGM Group / Herrera / Lorenzen Soil Mechanics
-Sletten Construction / Riverside Contracting / HDR / Morrison-Maierle / SK Geotechnical
-Sundt-Schellinger JV / DOWL / Jacobs / DJ&A

-4-
Submitted: Wednesday 06-NOV-2024 10:25 AM
MDT will postpone issuing the RFP by one week.  The revised Procurement Schedule is as follows:

DATE EVENT
10/02/2024 RFQ Advertisement Date
10/23/2024 SOQ Response Due Date
11/06/2024 Short List Date
11/07/2024
11/14/2024
RFP Issue Date
11/14/2024
11/21/2024
Pre-Proposal Meeting
12/11/2024
12/16/2024
Q&A Forum Closes at 5:00 pm local time
12/18/2024
12/23/2024
Technical Proposal Due Date
01/09 & 10/2025 Interviews at Missoula, MT
01/15/2024 Price Proposal Due Date
01/21/2025 Award Date
02/10/2025 Initial Preconstruction Phase Notice to Proceed (anticipated)

-5-
Submitted: Thursday 14-NOV-2024 03:39 PM
MDT will further delay issue of the Request for Proposals for the subject tied projects.  MDT will provide an updated procurement schedule when it becomes available.

-6-
Submitted: Wednesday 20-NOV-2024 01:58 PM
MDT anticipates issuing the RFP on November 27, 2024. This issue date is subject to change. The entire revised procurement schedule with be included in the RFP.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Monday 07-OCT-2024 04:51 PM
Company: Sundt/Schellinger JV
Contact: Ben Becker
We would like to request 3 additional pages for section 3.4 Organization Chart and Staffing Plan. This section is identical to the requirements in the RFQ for the smaller DAR project, which allowed for 2 - 11x17s for org chart and 2-8.5x11s for staffing plan. In addition, the additional pages would allow for proposers to provide a detailed org chart, while also fully answering all 7 questions in the staffing plan for this important MDT project.
Answer
Submitted: Wednesday 09-OCT-2024 01:42 PM
MDT will not allow the request for additional pages in section 3.4 Organization Chart and Staffing Plan.