Contractor's System Project Question and Answer Forum

BULLETIN BOARD                                                                                                                                                                                                                      
REMINDER!
Tuesday, November 11, 2025, is a state holiday and offices will be closed in observance of Veteran's Day. The Question and Answer Forum for contracts in the November 13, 2025 bid letting will close to new questions at 3:00 PM Friday, November 7, 2025.
________________________________________________________________________________________________________________________________________________________

NOVEMBER 13TH BID LETTING - TWO PROJECTS ADDED
Two projects have been added to the November 13th bid letting.

Call 106 – Three Forks Area Bridge Decks
Call 107 – I-15 Bridge Decks-Butte Area

____________________________________________________________________________________________________________________________________________________
UPDATED BIDDER'S LIST

The Bidder's List was updated based on an Interim Final Rule issued by USDOT on 10/3/2025 to remove the requirement to report race and gender:  BIDDER’S LIST

You may need to clear the cache in the web browser, if the new version is not downloading.
________________________________________________________________________________________________________________________________________________________
Qualified Products List (QPL)

Please review the expiration dates on the Department’s QPL regarding metal guardrail and associated materials. Please contact Randy Boysen at rboysen@mt.gov with questions or concerns.
______________________________________________________________________________________________________________________________________________________

Manufactured Products Waiver Notification
Beginning with the November 13, 2025 letting, the manufactured products waiver within 23 CFR 635.410 will be rescinded. Effectively, this means that the final manufacture of all materials defined as manufactured products in Section MT 601 of the MDT Materials Manual must meet domestic origin requirements. The Department is in the process of updating contract documents. Please contact Randy Boysen at rboysen@mt.gov with questions or concerns.
____________________________________________________________________________________________________________________________________________________

2nd Tier Subcontractors
For contractors that intend to use 2nd tier subcontractors in an effort to meet an SBE/DBE goal, please ensure that the specific dollar amount for the work they will be performing is indicated in the Bidders List.  If you have any questions about 2nd tier subcontractors on projects with DBE/SBE goals or how to enter that information in the bid file or on the bidders list, please contact Maggie Metzger at 406.422.9421 or mmetzger@mt.gov.  

______________________________________________________________________________________________________________________________________________________________________________
SBE Goals
Effective with the June 5, 2025 letting, MDT's Civil Rights Bureau will be identifying project specific Small Business Enterprise (SBE) goals. The percentage for the goal will be outlined by special provision. Please see the DBE/SBE Webpage
____________________________________________________________________________________________________________________________________________________________________________________________________________________________
UPDATE TO BIDDING PROCESS EFFECTIVE 6/5/25 LETTING
Effective with the June 5, 2025 letting, the Bidder’s List file must be attached in AASHTOWare Project Bids and include the required information for the prime contractor, subcontractors, and suppliers that provided a quote for the project. There will be a tab in AASHTOWare Project Bids where the Bidder’s List will be uploaded, prior to bid submission.
A video tutorial outlining this new process can be viewed at the following link: BIDDER'S LIST AASHTOWARE PROJECT BIDS TUTORIAL
The DBE-SBE Bidding Requirements special provision will be effective with the June 5, 2025 letting: DBE-SBE BIDDING REQUIREMENTS SPECIAL PROVISION

________________________________________________________________________________________________________________________________________________________________________________________________
2025 Bulletin Board Requirements: Prime contractors are responsible for erecting a bulletin board prior to work commencing on the project. It must include all required notices and posters, plus the contract-specific wage rates and EEO Policy Statements for the Prime and all Subs. Work with the Engineering Project Manager / Maintenance Superintendent or their designee to identify the most appropriate format and location for the board given the unique aspects of the project. Encouraged locations include staging areas or adjacent to project roadways. Subcontractors must supply their EEO Policy Statement to Prime contractors. Full requirements and examples can be found in the BULLETIN BOARD RESOURCE GUIDE
________________________________________________________________________________________________________________________________________________________________________________

Watch - Public Bid Opening - Live Stream: ZOOM MEETING INFORMATION

_______________________________________________________________________________________________________________________________________________________________________________________________________________________________

Advertised Projects: If you would like to receive the Invitation for Bids PDF document when projects are advertised, please send an email request to mdtcps@mt.gov. Follow the link for more information: EMAIL DISTRIBUTION
_______________________________________________________________________________________________________________________________________________________________________________________________________________________________

201 - CLARK FORK/OLD HWY 10 BRIDGES - October 23, 2025

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 22-OCT-2025 12:53 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Wednesday 22-OCT-2025 11:51 AM
The following special provisions are hereby added to the contract:
MODIFIED BRIDGE DECK CONCRETE WATER CURE
CONCRETE-CLASS STRUCTURE LOW SLUMP
BRIDGE DECK REINFORCING STEEL COVER


Questions

-1-
Submitted: Friday 26-SEP-2025 12:34 PM
Company: Sundt Construction
Contact: Joe Padon
Where are the additional geo-tech information located?
Has there been a sieve analysis and shear test completed on the existing material onsite, within the new bridge shadow?
Answer
Submitted: Tuesday 30-SEP-2025 12:28 PM
Attached are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to
MDT Headquarters 2511 Holman Avenue, Billings, MT 59102 to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.). The documents can be found at: GEOTECHNICAL REPORTS
One shear test was performed on Boring ST-7.

UPDATED
Submitted: Thursday 09-OCT-2025 11:32 AM
Please see address change above.

-2-
Submitted: Sunday 28-SEP-2025 12:58 PM
Company: Omega Caisson Drilling Inc.
Contact: NICK A LUDWIG
Is there a spec for the permanent casing embedment into the bedrock?
Who makes the determination of when to advance the bottom of casing beyond the design elevations?
Is casing installation method at the contractors discretion?
Are spin bottom buckets allowed for shaft cleanout if wet or loose soils are present?
Answer
Submitted: Monday 06-OCT-2025 02:35 PM

1. Not specifically.  The estimated tip elevations are shown on the drawings but may be subject to variation based on the conditions encountered.  Install the permanent casing to facilitate stable excavation, cleaning, inspection, and quality concrete placement.
2. 
The Contractor is ultimately responsible for satisfying the requirements set forth in the contract documents.  The decision of where to terminate the permanent casing is anticipated to be a collaborative effort between the Contractor, MDT’s Project Manager, and a Geotechnical engineer.  Address this important item in the required installation plan submitted for approval, as well as discussed in the shaft pre-construction meeting.
3. 
Yes, subject to the requirements of the contract documents and as approved in the required installation plan.
4. 
Yes, spin bottom buckets may be used to help with the cleanout, although per Special Provision #57, an airlift or other approved equal is required for the final cleanout.

-3-
Submitted: Tuesday 30-SEP-2025 03:25 PM
Company: Battle Ridge Builders
Contact: Cody Ham
Requiring traffic back on the bridge October 2026 means that there will be no demolition taking place in 2026 and just some deep foundation and access work. That leaves 150 working days to remove and replace a tall 800 foot bridge with difficult access and environmental concerns. That is not sufficient time. Just cure time alone will use almost 30 percent of these days. Please consider a more permanent detour that allows work through the 26-27 winter so demolition can start in 2026.
Answer
Submitted: Friday 03-OCT-2025 07:00 AM
Bid the project as advertised.

-4-
Submitted: Thursday 02-OCT-2025 12:17 PM
Company: Sundt Construction
Contact: Joe Padon
With such a short time to construct the new bridge, will working hours between 6 am to 10 pm be eliminated to allow double shifting?
Answer
Submitted: Monday 06-OCT-2025 10:38 AM
Special Provision # 34 Noise Impact is hereby removed from the contract. Double shifting will be allowed.

-5-
Submitted: Saturday 04-OCT-2025 11:45 AM
Company: Sundt
Contact: Joe Padon
Clarify the structure for which section 1 Paragraph 21 sentence E is reffering to. There appears to be be now drawings for the work in Section 1 Paragraph 21 subsection 2 sentence D and what is required under this contract.
Answer
Submitted: Wednesday 08-OCT-2025 09:07AM
Special Provision #21 is for structure 01377 and 01379.  Special Provision 21. C. 2). d) does not apply to this project.

-6-
Submitted: Monday 06-OCT-2025 02:02 PM
Company: Alpine Sign Inc
Contact: John
Can MDT please address the sizes shown in the Signing and Delineation Summary for R5-1A at Stations 99+19 LT & 99+49 RT
Answer
Submitted: Wednesday 08-OCT-2025 09:39 AM

The R5-1A sign size has been updated to 42”X30” for both locations. Updated plan sheets S1 and S2 can be viewed here: SHEETS S1 & S2
The affected Bid Item is hereby revised as follows:
619 010 090 SIGNS-ALUM REFL SHEET XI – 89.9 SQFT
An amendment will be issued, updated bid files will be posted.

-7-
Submitted: Monday 06-OCT-2025 04:52 PM
Company: DBM Contractors, Inc.
Contact: Ryan Thody
Who should we contact for setting up a visit to view the rock core samples for this project? Please provide an address of where the samples are located.
Answer
Submitted: Thursday 09-OCT-2025 11:25 AM
Contractors can contact Dustin Hutzenbiler at (406) 652-3930 or via email at
dhutzenbiler@skgeotechnical.com to schedule a date and time to view the core samples. Samples are located at 2511 Holman Avenue, Billings, Montana 59102, and are available for viewing Monday through Friday, between 9:00 AM and 4:00 PM. Please provide a minimum of three business days’ advance notice.

-8-
Submitted: Tuesday 07-OCT-2025 09:39 AM
Company: Hamilton Construction
Contact: Casey Shaw
SP 42 says "Remove the entire existing structure including but not limited to the deck slabs, beams, bridge rails, curbs, end bents, intermediate piers, foundations, and all incidental items." Drawing B4 shows the in-water piers being removed 3' below grade. Does the 3' below grade removal apply to the other piers, as well as the abutments or are they to be removed in their entirety? If the latter, then it appears shoring would be needed on the west side as well as the east, even though B4 only shows it on the east. Please advise.
Answer
Submitted: Friday 10-OCT-2025 09:07 AM
Remove existing Piers Nos. 4 and 5 in accordance with Special Provision 42 – Remove Structure. Remove all other substructures in accordance with Subsection 202.03.1.B. Removal of Substructures.

-9-
Submitted: Tuesday 07-OCT-2025 09:41 AM
Company: Hamilton Construction
Contact: Casey Shaw
The second season on this project requires more work to be accomplished by 10/29/27 than time allows for, especially when considering cure times. Would MDT be open to adding a third season to complete demo, remove access, and finish incidental work, assuming we were able to get the bridge open to traffic by 10/29/27 to make the schedule possible?
Answer
Submitted: Friday 10-OCT-2025 09:24 AM

Per special provision #2, the contract changes to a working day contract after October 29, 2027.  For clarification, no working days would be charged during the winter period and up until the seal coat dates if the demo and removal of access work have no impact on the traveling public.  Special Provision #2 Contract Time – Completion Date is hereby replaced with the following special provision:  CONTRACT TIME - COMPLETION DATE
UPDATE
Submitted: Friday 17-OCT-2025 02:03 PM

Special Provision #2 CONTRACT TIME - COMPLETION DATE has been updated due to a subsequent question.
 

-10-
Submitted: Tuesday 07-OCT-2025 09:46 AM
Company: Hamilton Construction
Contact: Casey Shaw
SP 13 states that the contract time will be increased by 10 calendar days for those who attended the pre-bid networking conference. Do those 10 additional days eliminate incurring disincentives and liquidated damage during that time?
Answer
Submitted: Wednesday 08-OCT-2025 10:19 AM
Road User Costs would apply from October 29, 2027 through November 8, 2027,  and Liquidated Damages would apply after November 8, 2027 for a successful bidder who has attended the pre-bid networking conference on November 18, 2024.  Road User Costs and Liquidated Damages would not be combined or added together after November 8, 2027.

-11-
Submitted: Tuesday 07-OCT-2025 09:44 AM
Company: Hamilton Construction
Contact: Casey Shaw
Do liquidated damages, as shown on Table 108-4 of the Standard Specs, apply in addition to $4300/day disincentive if traffic is not switched out of crossover configurations by 10/29/27?
Answer
Submitted: Wednesday 08-OCT-2025 10:16 AM
Liquidated Damages will apply after October 29, 2027 per special provision 4.C.3).  The assessment of Liquidated Damages and Road User Costs will not be combined or added together after October 29, 2027.

-12-
Submitted: Tuesday 07-OCT-2025 11:12 AM
Company: Battle Ridge Builders
Contact: Cody Ham
Will the state allow Clearcast deck forms for this deck? They are clear so they will allow for state inspection. These forms would shorten construction time and make the work significantly more safe for our crews as this bridge is very tall.
Answer
Submitted Thursday 09-OCT-2025 8:47 AM
Stay in place forms are not permitted.  Bid the project as advertised.

-13-
Submitted: Tuesday 07-OCT-2025 05:34 PM
Company: Garco Construction, Inc.
Contact: Tim Loucks
Per SP 22, Page 16 RAILROAD COORDINATION AND FLAGGING. 1) The referenced site does not contain any standard agreements, just an application process. Please provide standard "C" and "C-1" agreements relative to the project. 2) Please confirm if MDT will provide compensation for providing RR Protective Liability Insurance per 107.07 or if this cost is to be borne by the Contractor.
Answer
Submitted: Thursday 09-OCT-2025 8:50 AM
The “C” and “C-1” agreements are Railroad agreements, not MDT agreements.  Follow the stated electronic permitting process with the railroad to gain permission, ensure proper insurance levels, and coordination of possible flagging. 
MDT will provide compensation to the contractor for providing RR Protective Liability Insurance per 107.07. 

UPDATE
Submitted: Tuesday 14-OCT-2025 9:23 AM
MDT will provide compensation to the contractor for flagging and inspection services, and permit processing fees (excluding rush processing fees). The cost of providing RR Protective Liability Insurance per 107.07 and 107.13.2 are to be borne by the Contractor.

 

-14-
Submitted: Thursday 09-OCT-2025 07:41 PM
Company: Sundt
Contact: Joe Padon
Section 55 Paint Existing Structural Steel Paragraph D sentence 4 states "Repair areas subject to pack rust as identified by the Project manager" How can a contractor quantify the amount of pack rust to be removed if no quantity is given?
Answer
Submitted: Wednesday 15-OCT-2025 09:00 AM
Previous inspection reports of the structure indicate pack rust at the pin and hanger assemblies, generally between the girder pin plate and transverse girder hanger angle.  Heavier pack rust is noted on the exterior girders.  Anticipate pack rust in these areas.  Any pack rust repair areas found beyond what is noted in the previous sentences will be paid under 109.04.

-15-
Submitted: Thursday 09-OCT-2025 07:52 PM
Company: Sundt
Contact: Joe Padon
In Spec Section 55 paragraph D sentence 4 sub section a) Notify the project manager of locations not identified on the Plans were built-up steel sections are deformed over 1/4" due to pack rust. Repair these areas as directed by the Project Manager.
Please clarify the plans being referred to and what the repair will consist of for proper pricing of this bid item.
Answer
Submitted: Wednesday 15-OCT-2025 09:00 AM
There are no painting or painting repair plans.  This section is meant to ensure all pack rust is addressed and repaired.  The repair would follow the same procedure as described in special provision 55.D.4.  Refer to answer on Question #14 for anticipated pack rust repair areas.

-16-
Submitted: Friday 10-OCT-2025 10:25 AM
Company: Sundt
Contact: Joe Padon
There isn't a grading plan sheet for the east side of the river under the bridge, will one be provided?
Answer
Submitted: Tuesday 14-OCT-2025 11:57 AM
Please refer to Plan Sheets 16 and 17 for grading and soil/erosion control improvements on the east side.

-17-
Submitted: Friday 10-OCT-2025 06:13 PM
Company: Sundt
Contact: Joe Padon
Sheet 23 of the plans show EFAC line north of the WB structure . Will the state allow the area north from the EFAC boundary that lies between that line and property boundaries be used for lay down and access?
Answer
Submitted: Tuesday 21-OCT-2025 03:05 PM
The shaded area in the following link can be used for staging and access: STAGING AREA OLD HWY 10
The following Special Provision is hereby added to the contract: STAGING AREA AND ACCESS

 

-18-
Submitted: Monday 13-OCT-2025 03:48 PM
Company: Sletten Construction
Contact: Russ Robertson
Does the Interim Final Rule affect the 3.7% SBE participation requirement per Special Provision 11? Is it still required?
Answer
Submitted: Monday 20-OCT-2025 10:05 AM
The SBE goal defined in Special Provision 11 remains in effect.  Please see guidance regarding changes to MDT DBE/SBE goals and certifications
 at the following LINK.

-19-
Submitted: Tuesday 14-OCT-2025 09:25 AM
Company: Sundt
Contact: Joe Padon
Can the south shaft at Pier 2 extend the perm casing to elevation 2893.28
Answer
Submitted: Friday 17-OCT-2025 08:43 AM
Bid as advertised.  A request to extend the permanent casing may be submitted as an RFI for consideration after award.

-20-
Submitted: Tuesday 14-OCT-2025 10:43 AM
Company: Poteet Construction
Contact: Estimating
Special Provision 66 - Wide Load and Superload Accommidation- C - Wide Load Marshalling will be paid under the LS Bid Item. There is not a bid item for Wide Load Marshalling. How will Wide Load Marshalling be paid?
Answer
Submitted: Tuesday 14-OCT-2025 3:37 PM
Bid Item #618 030 215 WIDE LOAD MARSHALLING-LS is hereby added to the contract.
An amendment will be issued, updated bid files will be posted.

-21-
Submitted: Tuesday 14-OCT-2025 02:24 PM
Company: Hamilton Construction
Contact: Casey Shaw
Please clarify the incidental activities to the traffic control and crossover bid items (BI 760-820), as there appears that some items are currently incidental to both (traffic control and striping). Also, please clarify what striping is included in BI 980-1020, as it appears that a lot of the striping is incidental to the traffic control and crossover bid items (BI 760-820).
Answer
Submitted: Thursday 16-OCT-2025 12:55 PM
Refer to Special Provisions 61, 62, and 63 on what activities are incidental and included in the respective bid item for crossovers.  The pavement marking frame on Sheet 8 includes striping after paving and Cover-Type 1 activities.

-22-
Submitted: Tuesday 14-OCT-2025 03:14 PM
Company: Sundt
Contact: Joe Padon
Can the existing bridge plans for the EB structure next to the new bridge be made available.
Answer
Submitted: Thursday 16-OCT-2025 03:58 PM
The files linked below represent the as-built drawings for the structures. MDT provides them for informational purposes only. They do not include drawings for modifications to the structures, such as joint replacements and guardrail revisions and may not completely represent current conditions. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents. AS BUILTS

-23-
Submitted: Wednesday 15-OCT-2025 10:33 AM
Company: Wadsworth Brothers Construction
Contact: Jim Stoen
Please provide existing and proposed design files related to this project including existing and proposed surface models.
Answer
Submitted: Friday 17-OCT-2025 12:40 PM
The design files for the requested project are posted here: DESIGN FILES
The requested files do not represent the staked project but are only design files.  The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents.
In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.

-24-
Submitted: Wednesday 15-OCT-2025 10:50 AM
Company: Sundt
Contact: Joe Padon
Per Standard Spec 558.03.7 (4) corrosion protection is required for all permanent casing. One of the requirements (c.) for painting the casing gives some limits to apply paint when in water channel or when the steel is exposed. There are no requirements listed for galvanizing. On this project the permanent casing is not in the water channel or appear to be exposed above finished grade. Can you confirm if there is a requirement for corrosion protection on the permanent casing, and what is it?
Answer
Submitted: Thursday 16-OCT-2025 12:52 PM
Refer to 558.03.7.c which states the portion of the casings that would require paint.  Corrosion protection is not required if the permanent casing is not in the water channel or exposed above ground elevation.  Any permanent casing installed that is exposed must be painted in accordance with 558.03.7.4.

-25-
Submitted: Wednesday 15-OCT-2025 12:11 PM
Company: Sundt
Contact: Joe Padon
Does the drilled shaft concrete have to be self consolidating concrete?
Answer
Submitted: Thursday 16-OCT-2025 03:34 PM
Please refer to the plans where Drilled Shaft Concrete is called out for placement.  Refer to Section 551 of the standard specifications and special provision #54 for the requirements of Drilled Shaft Concrete and 551.03.2.G specifically for allowed use of SCC.

-26-
Submitted: Wednesday 15-OCT-2025 03:48 PM
Company: Garco Construction
Contact: Erik Wick
Our team has invested a considerable amount of effort in developing viable access plans for this challenging project site. These plans still require further subcontractor vetting and engineering analysis to validate means and methods and confirm cost accuracy. Maintaining the current bid date of October 23rd would limit our ability to adequately price our self-performed work and hinder our trade partners from submitting competitive proposals of their own in advance of our bid submission. We request a one-week bid extension to allow proper risk evaluation and to ensure a comprehensive, well-developed bid is submitted for MDT's consideration.
Answer
Submitted: Monday 20-OCT-2025 02:51 PM
The bid letting will remain as advertised.

-27-
Submitted: Wednesday 15-OCT-2025 05:45 PM
Company: Sundt
Contact: Joe Padon
Will the state allow the East bound bridge to be used for setting girders on the new structure? The traffic would be flagged at both ends allowing one lane of traffic to pass.
Answer
Submitted: Tuesday 21-OCT-2025 10:58 AM
The EB structure may be used to pick girders with an approved traffic control plan that allows EB and WB traffic to continue flowing without a complete stop.  This plan may include but is not limited to a rolling slowdown.  If utilizing the EB structure for girder picks, this work must be done between 8:00 pm and 8:00 am.

-28-
Submitted: Thursday 16-OCT-2025 09:37 AM
Company: Wadsworth Brothers Construction
Contact: Ashford Galbreath
We request the bid be postponed to provide additional time for the necessary access coordination with adjacent property owners. We have also heard from our engineers that the engineering analysis of the demolition and de-erection of the existing structure will take longer than anticipated, and additional bid time will allow us to reduce the risk contingency in our estimate. Additionally, the extensive design and analysis of the proposed temporary access and erection planning and stability requires much more engineering effort than a typical project. The state will benefit from reduced construction pricing by postponing the bid.
Answer
Submitted: Monday 20-OCT-2025 02:51 PM
The bid letting will remain as advertised.

-29-
Submitted: Thursday 16-OCT-2025 12:28 PM
Company: 3 Bull Contracting LLC
Contact: Kelsey l allen
The project calls for only wildlife fencing, but also calls out deadman as bid items. Typically they are used for wire strand fencing in a depression. Is it correct to have these with the wildlife fencing. Would a brace be more suitable? I'm not sure how you would pull 8' woven wire down for a deadman to be placed.
Answer
Submitted: Friday 17-OCT-2025 01:00 PM
Bid Item #607 100 720 DEADMAN is hereby deleted from the contract.
Updated plan sheet 10 can be viewed here: UPDATED SHEET 10
An amendment will be issued, updated bid files will be posted.

-30-
Submitted: Thursday 16-OCT-2025 12:52 PM
Company: Mountain West Holding Company
Contact: Chris Connors
Special provision 61 requires removal of all striping and traffic control devices upon winter shut down 2026 to 2027. Would the cable rail systems need to be reset for 2026/2027 winter shut down or just at the completion of the project?
Answer
Submitted: Friday 17-OCT-2025 11:22 AM
Close the crossover with 36” hinged flexible guideposts spaced every 8’ on center when not in use in-between seasons. Include the cost of this work in the 618 030 300 CROSSOVER-MAINTAIN, CLOSE bid item.

-31-
Submitted: Thursday 16-OCT-2025 01:34 PM
Company: Frontier West LLC
Contact: Kris Anderson
Would MDT please add 5 more days in spring of 2028 to perform "Bridge Deck Crack Seal"?
Answer
Submitted: Friday 17-OCT-2025 02:19 PM
Please see updated answer to Question #9.

-32-
Submitted: Thursday 16-OCT-2025 04:15 PM
Company: Wadsworth Brothers
Contact: Ashford Galbreath
The Montana Cadastral survey website shows the west end of the bridge is owned by a private individual. Will MDT commit to pursuing condemnation to provide contractor access if the owner is not willing to provide access? If not, does MDT realize that this individual has the ability to select the low bidder by withholding access or providing differential pricing to each of the bidding contractors?
Answer
Submitted: Wednesday 22-OCT-2025 01:37 PM
MDT does not participate in access agreements between private landowners and contractors.
Please see the following ROW Plans for more information: ROW PLANS
MDT has purchased right-of-way in the NW quadrant that facilitates contractor access as shown in the attached exhibit: EXHIBIT

-33-
Submitted: Friday 17-OCT-2025 12:43 PM
Company: Sundt
Contact: Joe Padon
The 404 permit obtained is good through March 14, 2026. Will the state get an extension on this permit through 2027 construction period
Answer
Submitted: Tuesday 21-OCT-2025 11:13 AM
The Department will coordinate with the US Army Corps of Engineers to maintain authorization of the 404 CWA Nationwide Permit 14 (NWP 14) as the project is built to plan.
The Nationwide Permit Verification Letter can be viewed here: USACE LETTER

-34-
Submitted: Friday 17-OCT-2025 03:23 PM
Company: Sundt
Contact: Joe Padon
In Spec section 1 subsection 22 Railroad Information Table it shows location RR DOT # 090343C. This structure is just East of the Clark Fork River Bridge. Please clarify the work that is required within the RR ROW
Answer
Submitted: Tuesday 21-OCT-2025
There is a small section of the project limits that fall within RR ROW on the east end of the project.  There is only a small amount of roadway work within the RR ROW, no bridge work of any kind on RR ROW or over the RR structure.  The contractor is required to have a permit with the RR for any work on RR ROW within highway easement no matter the distance to the tracks.  Follow the special provision to acquire the permit.

202 - BELGRADE-BOZEMAN - October 23, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Monday 06-OCT-2025 01:49 PM
Company: Alpine Sign Inc
Contact: John
Please provide Sign Design Calculations for this project
Answer
Submitted: Monday 06-OCT-2026 02:22 PM
The sign design files for the requested project are posted here: SIGN DESIGN CALCS
The requested files are only design files. The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents. In addition, the Department will not make any revisions to the electronic files prior to award. Changes needed via change ordered work, or changes that are made during construction to fit field conditions, will be provided at that time. See the requirements of Subsection 619.03.2.

MDT is transitioning towards including the Sign Design Calcs as part of the advertised bid package, when applicable. Advertised Bid Packages are linked here: 
Advertised Bid Packages | Montana Department of Transportation (MDT)

-2-
Submitted: Friday 10-OCT-2025 10:59 AM
Company: Mountain West Holding Company
Contact: Chris Connors
Would the Department consider changing this project to use crossovers so that workers have less exposure to the traveling public. It has been very evident on all of the active projects the last two seasons that the occurence of crashes in and around the Bozeman area are more frequent than other projects around Montana. The benefit that night construction offers to the public for congestion purposes is more than offset by the increased risk presented to workers at night. Traffic control devices, lights, and reflective clothing are not sufficient to protect workers from growing concerns of exposure to the traveling public in that corridor. Regardless of whether work is performed at day or night, there is a unusually higher risk to highway workers on this project.
Answer
Submitted Wednesday 15-OCT-2025 3:06 PM 
Due to the impact to interchange operations and larger global local road impacts, crossovers will not be allowed.

 

-3-
Submitted: Tuesday 14-OCT-2025 01:35 PM
Company: KNIFE RIVER - BELGRADE
Contact: Ira LeSage
SP 23 requires transport and stockpile of cold milled materials not incorporated into the project to be delivered to the Cooper Pit. Is this allowed at night, given the proximity of residential neighborhoods?
Answer
Submitted: Tuesday 21-OCT-2025 08:11 AM
Special Provision #23 Recycling and Disposal of Cold Millings is hereby replaced with the following special provision:  RECYCLING AND DISPOSAL OF COLD MILLINGS

 

-4-
Submitted: Tuesday 14-OCT-2025 01:58 PM
Company: KNIFE RIVER - BELGRADE
Contact: Ira LeSage
Contract time is stated as 65 working days. After review of the scope, quantities, sequencing, and conditions in SP 5, we feel that contract time should be in the 90 working day range. Please re-evaluate the allotted contract time.
Answer
Submitted: Tuesday 21-OCT-2025 01:47 PM
An additional 15 days will be added to the contract for a total of 80 working days.
Special Provision #2 Contract Time is hereby replaced with the following special provisionCONTRACT TIME

-5-
Submitted: Friday 17-OCT-2025 09:34 AM
Company: CK May
Contact: Josh McKenzie
1.) SP 4 references a noise exemption waiver requirement for the City of Bozeman along residential areas between Oak St. and Beall St. This appears to be a carryover from the N 7th Ave. project. If it isn't, can you clarify what residential work will require a noise waiver?
2.) Regarding question 2 above, night work on this section of interstate with single lane traffic next to the milling/paving operations is far more dangerous to our workers compared to the benefit to the travelling public to night work. Will MDT consider removing the night work requirement?
Answer
Submitted: Tuesday 21-OCT-2025 02:03 PM
A noise exemption waiver requirement will be required for this project. The night work requirement will not be removed.

-6-
Submitted: Saturday 18-OCT-2025 11:38 AM
Company: Mountain West Holding Company
Contact: Chris Connors
Special provision 5 states that if excessive queueing is experienced, the Department can direct changes to the allowed times. If that change includes reducing the hours of work time, will contract time be added to the project and how will it be calculated?
Answer
Submitted: Tuesday 21-OCT-2025 02:10 PM
In the event that the department directed a change, the process for requesting a time extension is outlined in MDT standard specifications section 108.

-7-
Submitted: Saturday 18-OCT-2025 11:51 AM
Company: Mountain West Holding Company
Contact: Chris Connors
The details in the project include milling and paving full width of the roadway. In areas that include guardrail work, guardrail would need to be removed prior to milling and then replaced following paving operations. Special provision 5 states that all areas where guardrail is removed, it must be installed the same shift prior to opening to traffic and lane closures are not allowed to remain in place. Realistically in areas where guardrails exist, the work area will be limited to approx 100ft per shift to allow time to set up traffic control, remove guardrail, mill, place tack oil, place pavement, allow to cool, install guardrail, and remove traffic control. Accordingly, this contract will need a minimum of 69 days alone for the work that is performed in guardrail areas. The Department will need to add at least 75 working days to the contract or clarify that guardrail work is not affected in any way by other contract work and can be performed independent of all other operations.
Answer
Submitted: Tuesday 21-OCT-2025 03:11 PM
In accordance with the special provision - Remove guardrail within 200 feet of bridge ends to pave full width. Remove guardrail, complete milling and paving, and replace all the removed guardrail at the end of each shift, prior to opening to traffic. Milling and paving through other guardrail sections can be completed with the rail in place.

-8-
Submitted: Saturday 18-OCT-2025 12:15 PM
Company: Mountain West Holding Company
Contact: Chris Connors
Special provision 5 includes language specific to the bridge end work at RP 303.6. As stated in a previous Q&A, the amount of listed work of 200 lineal feet can not be performed in one shift. Removing and installing bridge approach guardrail requires more time than standard guardrail and further requires forming and pouring a concrete curb taper with form stripping occuring at a later time. Additional resources have no ability to increase production as only so much equipment and personnel can fit into a 200ft area and none of the listed work can be ongoing simultaneously. The request is unrealistic and can not be performed as stated which will lead to the contractor failing to comply with the requirements in special provision 6.
Answer
Submitted: Tuesday 21-OCT-2025 03:25 PM
Please see response to questions 4 and 7.

-9-
Submitted: Saturday 18-OCT-2025 12:21 PM
Company: Mountain West Holding Company
Contact: Chris Connors
Special provision 30, Temporary Barrier Rail, describes payment for Reset Temporary Barrier to include any barrier previously used on the project. It has been understood for many years that Reset Temporary Barrier was the pay method used when temporary barrier was shifted in the work zone by use of lifts or cranes whereas temporary barrier that must be moved a greater distance than a shift was paid under Temporary Barrier. The distinction was accurate as the price for temporary barrier is significantly higher than reset temporary barrier as it includes loading, trucking, and unloading. The proposed method of payment in SP 30 will now intermix two distinctly different types of work into the same bid item, Reset Temporary Barrier. This will further cause problems if there are change orders or revisions to the project that include Reset Temporary Barrier. The temporray concrete barrier summary on page 9 indicates what quantities will be paid and how they will be paid. If one bridge is worked on first and the second bridge following completion of the first bridge, will the temporary barrier be paid as a reset to haul between the eastbound and westbound structure or does the payment method shown on sheet 9 apply?
Answer
Submitted: Wednesday 22-OCT-2025 07:03 AM
Bid resets in accordance with Special Provision 30. It is an unknown if the successful bidder will work on the structures simultaneously, temporary barrier rail and reset temporary barrier rail quantities on page 9 accurately reflect the quantity in the event that the successful bidder chooses to do so.

203 - SF 179 CURVE S OF CHURCHILL - October 23, 2025

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 22-OCT-2025 03:41 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Monday 20-OCT-2025 09:06 AM
The Cross Sections plans sheets have been updated to correct an error. The updated Cross Sections can be viewed here: CROSS SECTIONS
 

-2-
Submitted: Monday 20-OCT-2025 10:13 AM
Parcel 7, (Tract 1, Minor Subdivisions No. 411, geocode: 06-0797-08-2-01-15-0000) has not given permission to cross or trespass on the property.  Using this parcel to access the gravel pit location will not be allowed.  See attached ROW plans for more information: ROW_PLANS
 


Questions

-1-
Submitted: Thursday 25-SEP-2025 07:30 PM
Company: Riverside Contracting, Inc.
Contact: George Shick
Can MDT post the design files, dirt runs, mass diagram, and any additional geotechnical information.
Answer
Submitted: Wednesday 08-OCT-2025 11:11 AM
The design files for the requested project are posted here: DESIGN FILES
DESIGN FILES-ALL
The requested files do not represent the staked project but are only design files.  The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents.
In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.

Attached are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.). The documents can be found at: GEOTECHNICAL REPORTS

A mass diagram and dirt runs are not available for the project

UPDATE
Submitted: Monday 20-OCT-2025 12:46 PM
The DESIGN FILES link has been updated to include additional files requested in Question #5

 

-2-
Submitted: Friday 03-OCT-2025 08:57 AM
Company: Williams Civil Construction
Contact: Tosha Johnson
Contract time is stated to be 60 working days starting December 22nd. Can you clarify this is correct? There are concerns regarding the time allotted as well as paving not being possible in the winter months.
Answer
Submitted: Monday 06-OCT-2025 11:18 AM
Please see MDT Standard Specification 108.07.3 which outlines contract time assessment during the winter period.

-3-
Submitted: Monday 06-OCT-2025 08:30 AM
Company: Williams Civil Construction
Contact: Tosha Johnson
Can MDT post the CAD/design files for this project for 3D modeling purposes.
Answer
Submitted: Monday 20-OCT-2025 12:55 PM
Please see answer to Question #1

-4-
Submitted: Monday 06-OCT-2025 01:51 PM
Company: Alpine Sign Inc
Contact: John
Please provide Sign Design Calculations for this project
Answer
Submitted: Friday 10-OCT-2025 09:16 AM

The sign design files for the requested project are posted here: SIGN DESIGN CALCS
The requested files are only design files. The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents. In addition, the Department will not make any revisions to the electronic files prior to award. Changes needed via change ordered work, or changes that are made during construction to fit field conditions, will be provided at that time. See the requirements of Subsection 619.03.2.

MDT is transitioning towards including the Sign Design Calcs as part of the advertised bid package, when applicable. Advertised Bid Packages are linked here:  Advertised Bid Packages | Montana Department of Transportation (MDT)

-5-
Submitted: Wednesday 08-OCT-2025 02:16 PM
Company: CK MAY EXCAVATING INC
Contact: Josh McKenzie
Can you please include the existing grade and finish grade terrain files in .XML format instead of .DGN format?
Answer
Submitted: Monday 20-OCT-2025 12:56 PM
Please see updated link included in the answer to Question #1.

-6-
Submitted: Thursday 09-OCT-2025 03:00 PM
Company: CK MAY EXCAVATING INC
Contact: Josh McKenzie
1. A significant number of utilities appear to be in conflict with the road lowering. Has this work been completed, and if not, when is the anticipated completion date? 2. SP 19 states the 404 permit for the unnamed tributary to Yellow Dog Creek is valid until March 14th, 2026. Does this work need to be completed by March 14th 2026?
Answer
Submitted: Wednesday 15-OCT-2025 8:36 AM
1. Not all utilities have been moved. We are working with the last utility to determine when it will be moved.
2. The work on the unnamed tributary to Yellow Dog Creek does not need to be completed by March 14, 2026. Work described in the CWA 404 Nationwide Permit under contract prior to the expiration is permitted up to 12 months beyond the expiration to complete work. MDT will modify the permit if it becomes necessary to continue work beyond 12 months.

-7-
Submitted: Monday 13-OCT-2025 10:40 AM
Company: Montana Fence
Contact: Jon Likes
The quantity of metal braces in this project seems off. If there is a break in direction or an inline tie off these need to be double panels using the states design. Can the quantities be updated to address this?
Answer
Submitted: Thursday 16-OCT-2025 12:14 PM
The fencing summary frame has been updated on Sheet 10. Right-of-way breaks for metal fence should be constructed as shown in Detail Drawing 607-15. Right-of-way breaks for wood fencing should be installed as shown in Detail Drawing 607-20. Single panel fence is also to be used when tying to the wood rail at the stockpass.
Updated Sheet 10 can be viewed here: UPDATED SHEET 10

UPDATE
Submitted: Monday 20-OCT-2025 08:01 AM
Fencing quantities are hereby revised as follows:
Bid Item #607 100 152 – FARM FENCE-TYPE F3M-32IN WW – 3,580 LNFT.
Bid Item #607 100 360 – FARM FENCE-PANEL/SINGLE FW – 4 EACH.
Bid Item #607 100 362 – FARM FENCE-PANEL/SINGLE FM – 10 EACH.
Bid Item #607 100 380 – FARM FENCE-PANEL/DOUBLE FW is hereby deleted from the contract.
Bid Item #607 100 385 – FARM FENCE-PANEL/DOUBLE FM – 24 EACH.
An amendment will be issued, updated bid files will be posted.

-8-
Submitted: Monday 13-OCT-2025 10:51 AM
Company: Montana Fence
Contact: Jon Likes
On sheet 19 for the stockpass detail, it shows fence being ran u both sides to the stockpass. However, there is no stockpass fencing in the summary pages describing when it is supposed to be nor is there a detail for how that fence is to be tied in. These is a note calling out stockpass rail fence. This has been an oversight in the past and ends up being a change order. Will the state provide a detail as well as an updated bid form with this fencing as a bid item?
Answer
Submitted: Monday 20-OCT-2025 8:05 AM
Quantities for the stockpass fencing have been added. The Fencing Summary frame on sheet 10 has been updated to reflect the additional quantities for Type Wood 4 Rail. See Detail Drawing 607-17 for how to tie in the fencing. Please see updated Sheet 10 in the response to Question #7.
Bid Item #607 100 391 FENCE-WOOD-4 RAIL is hereby added with a quantity of 286.0 LNFT. An amendment will be issued, updated bid files will be posted.

-9-
Submitted: Monday 13-OCT-2025 03:28 PM
Company: Montana Fence
Contact: Jon Likes
In regards to the metal panels, there seems to be an over estimation of singles and an under estimation or doubles. I would assume that this is due to Right of Way breaks but the current state detailed drawing does not have a break detail so these would need to be offset doubles. Is it possible to amend the bid form to reflect the appropriate quantities?
Answer
Submitted: Monday 20-OCT-2025 02:53 PM
See response to Question #7.

-10-
Submitted: Monday 13-OCT-2025 03:31 PM
Company: Montana Fence
Contact: Jon Likes
In regard to the stockpass, there is currently no quantity or description for stockpass fencing. There is a brief reference to the stockpass rail fencing in the summary, however there is no bid item or detail for what is to be installed. Standard detail is 4 Rail Wood Post and Rail but we have seen others in the past and want to ensure this is covered in the initial bid letting.
Answer
Submitted: Monday 20-OCT-2025 02:54 PM
See response to Question #8.

-11-
Submitted: Monday 13-OCT-2025 06:09 PM
Company: CK May
Contact: Josh McKenzie
Based on the quantity of excavation and special embankment on the project, large diameter culverts, steel casing pipe, in-stream dewatering and culvert infill, this work needs to be done with a full road closure for the duration of the project to complete it in the 60 day timeframe. Will MDT consider extending the road closure for the duration of the project, or adding 20 days to the contract?
Answer
Submitted: Wednesday 15-OCT-2025 10:23 AM
An additional 20 days will be added to the contract for a total of 80 working days.
Special Provision #2 Contract Time is hereby replaced with the following special provision:
CONTRACT TIME

UPDATE
Submitted: Monday 20-OCT-2025 03:29 PM
An additional 40 days will be added to the contract for a total of 100 working days.
Special Provision #2 Contract Time is hereby replaced with the following special provision: CONTRACT TIME

-12-
Submitted: Monday 13-OCT-2025 12:24 PM
Company: Knife River
Contact: Estimating
Contract time is stated as 60 working days. After review of the scope / quantities / sequencing we feel that contract time should be in the 130-150 working day range. Please re-evaluate the allotted contract time.
Answer
Submitted: Wednesday 15-OCT-2025 10:25 AM
See response to Question #11.

-13-
Submitted: Tuesday 14-OCT-2025 04:45 PM
Company: Knife River
Contact: Estimating
Is the ditch/channel excavation/grading (outside of the slope flattening) for the 78" culvert at station 788+86 and the associated grading between Churchill Road and Anderson Road included in unclassified excavation? If not, how is this paid?
Answer
Submitted: Thursday 16-OCT-2025 12:40 PM
The Additional Grading Summary Frame on Sheet 8 has been updated to show the unclassified excavation for the channel at station 789+93 associated with the culvert at station 788+86 and is included in the Additional Grading line on the Grading Summary Frame. All other grading between Churchill Road and Anderson Road is accounted for the respective alignment grading quantities as shown in the updated Grading and Additional Grading Summary Frames. Grading is paid as unclassified excavation. See special provision 24 for information regarding channel restoration.
Updated Sheet 8 can be viewed here: UPDATED SHEET 8

UPDATE
Submitted: Monday 20-OCT-2025 8:07 AM
Bid Item #203 020 100 EXCAVATION-UNCLASSIFED is hereby increased to a quantity of 84,098.0 CUYD. An amendment will be issued, updated bid files will be posted.
UPDATE
Submitted: Wednesday 22-OCT-2025 03:18 PM
Sheet 8 has been updated due to a subsequent question: SHEET 8

-14-
Submitted: Wednesday 15-OCT-2025 12:14 PM
Company: CK May
Contact: Josh McKenzie
After reviewing the casing specifications we would like the following clarification:
- Coating requirement for the casing
- Wall thickness
- Type of pipe. Most commonly we see A53 Grade B Depending on the coating for corrosion protection, would fusible HDPE pipe be acceptable?
If so, we would need to know size and DR rating required.
Answer
Submitted: Monday 20-OCT-2025 8:37 AM
The 18-inch steel encasement pipes (i.e., SCP Irrigation-Stations 793+88/804+15) do not require coating. The minimum wall thickness is 0.25” meeting AWWA C-200 requirements.  A solid wall HDPE is not an acceptable option.

-15-
Submitted: Wednesday 15-OCT-2025 05:40 PM
Company: CK May
Contact: Josh McKenzie
Regarding Sp 24. Wetland Soil Salvage and Channel Restoration it states: This work consists of salvaging wetland soil from permanent impact areas and placing it in designated channel restoration areas as shown in the plans. Refer to the plan sheets and detail drawings for specific locations. Can you please provide more detail on the salvaging and placing of wetland material? The cross sections don't show the wetland soil replacement area. The 789+93 detail on page 17 doesn't reference where the wetland soil is to be placed, what the dimension/extents of the salvaged topsoil, or quantities. If this is to be included in Topsoil Replacement, an estimated quantity and clear detail need to be shown or a separate pay item for this salvaged material be added.
Answer
Submitted: Wednesday 22-OCT-2025 03:13 PM
The wetland soil is to be placed in the channel restoration area denoted in the detail on Sheet 17 on top of the High Performance ECB and shown in the channel cross sections. A quantity of 386 cubic yards of wetland soil is now shown in the plans to be salvaged and placed. This material quantity has been added to the Topsoil & Seeding Summary Frame on Sheet 8 and will be paid under wetland soil-salvage and place. The bid item WETLAND SOIL-SALVAGE AND PLACE (203080112) is hereby added to the contract and replaces the pay item Topsoil – Salvage and Placing for Special Provision 24. Special Provision #24 Wetland Soil Salvage and Channel Restoration is hereby replaced with the following special provision: WETLAND SOIL SALVAGE AND CHANNEL RESTORATION
Sheet 8 has been updated to show these changes and can be viewed in the answer to Question #13.
The total topsoil to be salvaged and placed shown in the Topsoil and Seeding summary frame has been reduced to 3,953 cubic yards. An amendment will be issued, updated bid files will be posted.

-16-
Submitted: Friday 17-OCT-2025 01:02 PM
Company: True North Steel
Contact: Amanda McCulloch
For Bid item 603010714 CSP 96in can 14ga 5x1 corrugation be used in place of the 3x1 corrugation?
Answer
Submitted: Wednesday 22-OCT-2025 12:56 PM
The use of 5x1 corrugations is acceptable. However, the minimum culvert thickness is incorrect on the plans and should be revised to 12-gage (0.109-inches) as the minimum thickness for the pipe. Sheet 9 was updated to reflect this: SHEET 9

-17-
Submitted: Monday 20-OCT-2025 09:09 AM
Company: Riverside Contracting, Inc.
Contact: George Shick
Preliminary Scheduling indicates that, given the volume of material to be hauled in for embankment and the material to be hauled to waste, 80 days is not sufficient to complete the job. Can MDT please add an additional 20 days to the contract.
Answer
Submitted: Monday 20-OCT-2025 03:34 PM
Please see the answer to Question #11.

-18-
Submitted: Monday 20-OCT-2025 09:56 AM
Company: CK MAY EXCAVATING INC
Contact: Josh McKenzie
After further review, 80 days is not feasible for this project, based on various factors related to quantities to be moved. Can MDT add an additional 25 days?
Answer
Submitted: Monday 20-OCT-2025 03:30 PM
Please see the answer to Question #11.

205 - PATH PRESERVATION-MISSOULA CO AND PATH PRESERVATION-RAVALLI CO - October 23, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Monday 13-OCT-2025 11:44 AM
Company: Knife River
Contact: Mike Eichner
Special Provision #20 speaks of placing isolation lifts of plant mix over rubberized crack sealing material. Can the Department provide a quantity of plant mix they plan on using for these areas. I do not see them called out in the summary tables.
Answer
Submitted: Wednesday 15-OCT-2025 7:11 AM
Refer to typical section No. 1 on plan sheet # 4 for the depth and placement locations of the isolation lift.  The quantity is included in the Plant Mix Surfacing frame and not broke out separately.

-2-
Submitted: Friday 17-OCT-2025 01:56 PM
Company: LHC
Contact: Sam Weyers
Please clarify what is required for Contractor Survey and Layout.
Answer
Submitted: Tuesday 21-OCT-2025 02:44 PM
This bid item compensates the contractor for the site-specific engineering and field work required to take the project's general design concepts for features like digouts and ADA ramps, calculate their exact coordinates, and physically lay them out on the ground with the necessary precision to meet MDT standards.

206 - LODGE GRASS-SOUTH - October 23, 2025

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 22-OCT-2025 12:56 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Thursday 25-SEP-2025 10:30 AM
MANDATORY PRE-BID CONFERENCE – Special Provision #5
A pre-bid conference will be held at the following time and location:
Thursday, October 09, 2025 at 10:00am,

Montana Department of Transportation
Billings District Conference Room
424 Morey St.
Billings, MT 59101
406-252-4138

Join Zoom Meeting
https://mt-gov.zoom.us/j/4065401203?pwd=cmFtanhSS0V4R2xYTGRlai9VMW1rQT09
Meeting ID: 406 540 1203
Passcode: 5401203
Dial by Telephone
+1 646 558 8656
Meeting ID: 406 540 1203
Passcode: 5401203
UPDATE
Submitted: Monday 29-SEP-2025 09:34 AM
There was issue with the Zoom meeting link. Please use updated link below.
Special provision #5 is hereby updated: MANDATORY PRE BID CONFERENCE


Join Zoom Meeting
https://mt-gov.zoom.us/j/4065401202?pwd=d1VJWW9vZXpyVWVTTVdQVDlkWklVdz09

Meeting ID: 406 540 1202
Passcode: 5401202

Dial by Telephone +1 646 558 8656
Meeting ID: 406 540 1202

Passcode: 5401202

UPDATE
Submitted: Thursday 09-OCT-2025 11:18 AM

Official Record of Attendance for the Mandatory Pre-Bid Conference: ATTENDENCE RECORD

 


Questions

-1-
Submitted: Monday 06-OCT-2025 01:53 PM
Company: Alpine Sign Inc
Contact: John
Please provide Sign Design Calculations for this project
Answer
Submitted: Wednesday 15-OCT-2025 12:28 PM
The sign design calcs, signing plans (sheets S1-S3), and bid items have been updated to reflect the 11th Edition of the MUTCD.  The following bid items have changed:

1. Revise            619010062 SIGNS-ALUM SHEET INCR XI – increase to 129.6 sqft
2. Revise            619010090 SIGNS-ALUM REFL SHEET XI – decrease to 6 sqft
3. Remove         619010240 REMOVE SIGN-GUIDE – delete 2 each
4. Revise            619010320 POSTS-STEEL STRUCTURAL SIGN – increase to 1,440 lbs
5. Remove         619010726 FRANG SIGN POST BKWY-W4 X 13 – delete 2 each
6. Revise            619010730 FRANG SIGN POST BKWY-W8 X 18 – increase to 4 each

An amendment will be issued. Updated bid files will be posted.

Please find linked the revised signing sheet S1-S3 here: UPDATED SIGNING PLANS

Please find linked the sign design calcs here: SIGN DESIGN CALCS

The requested files are only design files. The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents. In addition, the Department will not make any revisions to the electronic files prior to award. Changes needed via change ordered work, or changes that are made during construction to fit field conditions, will be provided at that time. See the requirements of Subsection 619.03.2.

-2-
Submitted: Monday 20-OCT-2025 07:30 AM
Company: Mountain West Holding Company
Contact: Chris Connors
Special provision 26, Temporary Barrier Rail, describes payment for Reset Temporary Barrier to include any barrier previously used on the project. It has been understood for many years that Reset Temporary Barrier was the pay method used when temporary barrier was shifted in the work zone by use of lifts or cranes whereas temporary barrier that must be moved a greater distance than a shift was paid under Temporary Barrier. The distinction was accurate as the price for temporary barrier is significantly higher than reset temporary barrier as it includes loading, trucking, and unloading. The proposed method of payment in SP 26 will now intermix two distinctly different types of work into the same bid item, Reset Temporary Barrier. This will further cause problems if there are change orders or revisions to the project that include Reset Temporary Barrier. The temporray concrete barrier summary on page 6 indicates what quantities will be paid and how they will be paid. If all bridges are not worked on at the same time, will the temporary barrier be paid as a reset to haul from bridge to bridge or does the payment method shown on sheet 6 apply?
Answer
Submitted: Monday 20-OCT-2025 01:32 PM
For this project Temporary Barrier Rail and associated Bid Items will be paid according to the plan summaries and not Special Provision #26. Reset Barrier Rail will be defined as:  Moves done without the use of a transport.  Temporary Barrier Rail will be paid for moves that require a transport to move the rail, i.e. moving from one bridge to another.

-3-
Submitted: Monday 20-OCT-2025 08:01 AM
Company: Mountain West Holding Company
Contact: Chris Connors
The bid item Foundation-Concrete has a bid qty of 2.0 CY. There are two foundations under this bid items that equate to 1.4 CY of concrete using the dimensions shown for the foundations. Will the bid qty of 2.0 CY shown be paid or is it paid at the actual neat line calculation?
Answer
Submitted: Tuesday 21-OCT-2025 11:28 AM
The Foundation-Concrete bid item will be paid by the actual neat line calculation to the hundredth.  Actual quantity is 1.4 CUYD. An amendment will be issued; updated bid files will be posted. Updated sheet E1 can be found at the following link: UPDATED SHEET E1

-4-
Submitted: Monday 20-OCT-2025 09:57 AM
Company: Montana Lines, Inc.
Contact: Estimating
Please confirm quantity of 617523010 SOL SIG-TRAF 1 COLOR-1-WAY 12. Plan quantity suggests 2 each, while plans indicate 4 each flashing beacons between two separate systems.
Answer
Submitted: Monday 20-OCT-2025  05:00PM
There are two installations of a solar flashing beacon system for the road closure signage.  At each installation there are two flashers, a controller cabinet, and solar system.  The bid item 617523010 is for each installation, bid the project as advertised.  Reference special provision 24 and electrical details for the advance warning beacons installation requirements.

Special provision #24, SOL SIG-TRAF 1 COLOR-1 WAY 12 has been updated. The special is hereby rescinded and replaced with the following linked provision: UPDATED SPECIAL

 

207 - D5 BRIDGE DECKS-COLUMBUS AREA - October 23, 2025

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 22-OCT-2025 12:59 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Monday 20-OCT-2025 02:05 PM
Traffic Actuated Temporary Signals – Day (618100007) is hereby deleted from this contract. The bid item Traffic Actuated Temporary Signals – LS (618100008) is hereby added to this contract. An amendment will be issued; updated bid files will be posted.

Special provision #29, Traffic Actuated Temporary Signals is rescinded and replaced with the linked provision: TRAFFIC ACTUATED TEMPORARY SIGNALS


Questions

-1-
Submitted: Thursday 16-OCT-2025 08:59 AM
Company: L & J Construction Group, LLC
Contact: Estimating
We need to assume a deck condition after Bridge Deck Milling for Engineering Analysis. Previous Q/A instructed the contractor to assume no debonding of the top mat of rebar. The Department also stated that changes in the contractor's operations resulting from reduced deck capacity would be considered extra work. Will this project follow the same guidelines?
Answer
Submitted: Monday 20-OCT-2025 08:56 AM
Bid this work under the assumption that the rebar remains bonded. If significant debonding is encountered during construction and requires changes to the contractor’s operations, it will be considered extra work and considered for time extension under 108.07.5. The STRUCTURE ANALYSIS bid item is included to pay for the engineering analysis and report.

-2-
Submitted: Friday 17-OCT-2025 11:29 AM
Company: Mountain West Holding Company
Contact: Chris Connors
Special provision 30, Temporary Barrier Rail, describes payment for Reset Temporary Barrier to include any barrier previously used on the project. It has been understood for many years that Reset Temporary Barrier was the pay method used when temporary barrier was shifted in the work zone by use of lifts or cranes whereas temporary barrier that must be moved a greater distance than a shift was paid under Temporary Barrier. The distinction was accurate as the price for temporary barrier is significantly higher than reset temporary barrier as it includes loading, trucking, and unloading. The proposed method of payment in SP 30 will now intermix two distinctly different types of work into the same bid item, Reset Temporary Barrier. This will further cause problems if there are change orders or revisions to the project that include Reset Temporary Barrier. The temporray concrete barrier summary on page 3 indicates what quantities will be paid and how they will be paid. If one bridge is worked on first and the second bridge following completion of the first bridge, will the temporary barrier be paid as a reset to haul between Columbus & Big Timber or does the payment method shown on sheet 3 apply?
Answer
Submitted: Monday 20-OCT-2025 04:58PM
For this project Temporary Barrier Rail and associated Bid Items will be paid according to the plan summaries and not Special Provision #30. Reset Barrier Rail will be defined as:  Moves done without the use of a transport.  Temporary Barrier Rail will be paid for moves that require a transport to move the rail, i.e. moving from one bridge to another.

-3-
Submitted: Friday 17-OCT-2025 11:53 AM
Company: Mountain West Holding Company
Contact: Chris Connors
The details on sheet 8 seem to indicate a short section of Protect in Place guardrail from the bridge end out to the joint between the bridge and the approach slab. Another note states to Remove 37.5 ft but it is unclear where the removal is to start. There is over 80ft of existing guardrail from the bridge end out to the end of the guardrail at each corner. Another note shows the new guardrail to start at the bridge end overlapping the section shown as protect in place, but does not include any bridge approaches. Is the intent to remove 37.5ft from the end of the rail toward the bridge, then start the new guardrail installation from there using the plan quantities?
Answer
Submitted: Tuesday 21-OCT-2025 12:02 PM
The intent of the guardrail removal is to remove all existing guardrail except for the Bridge Approach Sections. Removal should begin at the end of these Bridge Approach Sections, leaving the existing ±25’ sections in place.  Remove Guardrail lengths and quantities have been updated accordingly.
The following bid item quantities have been changed:
606 010 385      REMOVE GUARDRAIL  LNFT     250.00
The following plan sheets have been updated: UPDATED SHEETS 4 AND 8
Sheet 4 : Revised quantities of Remove Guardrail
Sheet 8: Revised limits of guardrail removal.
An amendment will be issued, updated bid files will be posted.

209 - SIDEWALKS-SUNBURST - October 23, 2025

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 22-OCT-2025 12:42 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Monday 06-OCT-2025 01:47 PM
Company: Alpine Sign Inc
Contact: John
Is it the Departments intention to use the sizes shown in the Signing and Delineation Summary for the D3-1 Street Name signs?
Answer
Submitted: Tuesday 14-OCT-2025 8:07 AM
Revisions to D3’s have been made to reflect 11th Edition of the MUTCD.
The following bid item quantities have been changed.
619 010 090    SIGNS-ALUM REFL SHEET XI has been increased from 134.20 SQFT to 144.70 SQFT.
619 010 340    POSTS-TUBULAR STEEL-SQ-PERF has been increased from 879.00 LB to 1,182 LB.
619 010 770    SQ TUBLR SLIP BASE BKWY-3IN has been decreased from 19 EACH to 2 EACH.

The following plan sheets have been updated:
Updated Sheet 9
Updated Sheet 10


An amendment will be issued; updated bid files will be posted.

UPDATE
Submitted: Friday 17-OCT-2025 09:07 AM
Revisions to D3’s have been made to reflect 11th Edition of the MUTCD.

The following bid item quantities have been changed.
619 010 090    SIGNS-ALUM REFL SHEET XI has been increased from 144.70 SQFT to 159.90 SQFT.
619 010 340    POSTS-TUBULAR STEEL-SQ-PERF has been increased from 1,182 LB to 1,199 LB.
619 010 770    SQ TUBLR SLIP BASE BKWY-3IN has been decreased from 19 EACH to 2 EACH.
619 010 230    REMOVE SIGN has been increased from 18 EACH to 25 EACH

The following plan sheets have been updated:

UPDATED PLAN SHEETS 9 & 10
UPDATED PLAN SHEETS 33, 37,39, & 40


An amendment will be issued; updated bid files will be posted.

UPDATED: 
Tuesday 21-OCT-2025 07:55 AM
Revisions to D3’s have been made to reflect 11th Edition of the MUTCD.

The following bid item quantities have been changed.
619 010 090    SIGNS-ALUM REFL SHEET XI has been decreased from 159.90 SQFT to 149.30 SQFT.
619 010 340    POSTS-TUBULAR STEEL-SQ-PERF has been decreased from 1,199 LB to 1,067 LB.
619 010 230    REMOVE SIGN has been decreased from 25 EACH to 18 EACH

The following items have been deleted from the project.
619 010 770    SQ TUBLR SLIP BASE BKWY-3IN has been decreased from 19 EACH to 2 EACH.

The following plan sheets have been updated:
Updated Plan Sheet 9 & 10 (10/21/25)
Updated Plan Sheet 33, 37, 39 & 40 (10/21/25)

An amendment will be issued; updated bid files will be posted.

-2-
Submitted: Monday 06-OCT-2025 01:48 PM
Company: Alpine Sign Inc
Contact: John
Please provide Sign Design Calculations for this project
Answer
Submitted: Thursday 09-OCT-2025 10:50 AM
The sign design files for the requested project are posted here: SIGN DESIGN CALCS

The requested files are only design files. The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents. In addition, the Department will not make any revisions to the electronic files prior to award. Changes needed via change ordered work, or changes that are made during construction to fit field conditions, will be provided at that time. See the requirements of Subsection 619.03.2.


MDT is transitioning towards including the Sign Design Calcs as part of the advertised bid package, when applicable. Advertised Bid Packages are linked here: 
Advertised Bid Packages | Montana Department of Transportation (MDT)

-3-
Submitted: Friday 10-OCT-2025 11:42 AM
Company: Century Companies, Inc.
Contact: Estimating
Will there be any striping or curb painting, incidental or otherwise required on this project?
Answer
Submitted: Tuesday 14-OCT-2025 11:52 AM
No striping or painting is required for this project.

210 - SF 229 BILLINGS DIST GUARDRAIL - October 23, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

101 - TWO MEDICINE RIVER BRIDGE - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Friday 17-OCT-2025 01:22 PM
MANDATORY PRE-BID CONFERENCE – Special Provision #7
A pre-bid conference will be held at the following time and location:
Wednesday, October 29, 2025 at 10:00am.

Join Zoom Meeting
https://mt-gov.zoom.us/j/4065401100?pwd=L0RrTzFka0pGRHovS3dyWVl3SmR0UT09

Meeting ID: 406 540 1100
Passcode: 5401100

Dial by Telephone
+1 646 558 8656
Meeting ID: 406 540 1100
Passcode: 5401100
Find your local number: https://mt-gov.zoom.us/u/aetZIZTFTM

Join by SIP
mdtcnfvmr100@mt.gov

Join by H.323 (Polycom)
162.255.37.11##4065401100#5401100

Join by Skype for Business
https://mt-gov.zoom.us/skype/4065401100

UPDATE
Submitted: Thursday 30-OCT-2025 11:49 AM
Official Record of Attendance for the Mandatory Pre-Bid Conference: ATTENDANCE RECORD

-2-
Submitted: Friday 31-OCT-2025 11:54 AM
Bid Item #618 100 008 TRAFFIC ACTUATED TEMPORARY SIGNALS-LS is hereby deleted from the contract.
Bid Item #618 100 007 TRAFFIC ACTUATED TEMPORARY SIGNALS is hereby added to the contract with a quantity of 60 DAYS.
An amendment will be issued, updated bid files will be posted.
 


Questions

-1-
Submitted: Thursday 23-OCT-2025 10:13 AM
Company: Hamilton Construction
Contact: Neal Spoon
Please provide a copy of the as-builts for the existing bridge.
Answer
Submitted: Friday 31-OCT-2025
The files linked below represent the as-built drawings for the structures. MDT provides them for informational purposes only. They do not include drawings for modifications to the structures, such as joint replacements and guardrail revisions and may not completely represent current conditions. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents.

AS-BUILTS

-2-
Submitted: Monday 27-OCT-2025 12:17 PM
Company: Dywidag-Systems International, USA, Inc.
Contact: Mark Oliphant
Please provide the meeting location and point of contact for the Box Girder Interior Review scheduled for Oct. 28.
Answer
Submitted: Monday 27-OCT-2025 01:15 PM
The Box Girder Interior Review is tomorrow, October 28, 2025 from 10:00am -1:00pm at the project site. Meet at the west end of the bridge (East Glacier side). You may contact Joe Grosswiler (406-788-1362).

-3-
Submitted: Wednesday 29-OCT-2025 08:58 AM
Company: Battle Ridge Builders
Contact: Cody Ham
Would the state consider a flex date start for this project for temporary access facilities, or can this work be done outside contract time as long as traffic is not impacted?
Answer
Submitted: Thursday 30-OCT-2025 11:45 AM
The Notice to Proceed is hereby changed to a Flexible Notice to Proceed date of April 15th, 2026. Special provision #2, Contract Time is hereby rescinded and replaced with the linked special, Contract Time – Flex Time Proceed Date: FLEX NTP

Contract time will be charged per Standard Specification 108.07.3. Contract time will not be charged during Winter Period days when the work has no impact to the traveling public.

-4-
Submitted: Wednesday 29-OCT-2025 08:56 AM
Company: Battle Ridge Builders
Contact: Cody Ham
Due to the nature of all the specialty work on this project would the state consider removing the 40% self performance requirement?
Answer
Submitted: Thursday 30-OCT-2025 12:28 PM

The requirement for the Prime contractor to perform at least 40% of the original contract cost will remain. Specialty Items referred to in 108.01.2 are listed under Special Provision #23.

-5-
Submitted: Wednesday 29-OCT-2025 11:38 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
The 3" deck sleeves appear to be covered from previous overlays. Are the locations and/or spacing of the 3" sleeves known?
Answer
Submitted: Thursday 30-OCT-2025 11:53 AM
The 3” I.D. form traveler sleeves are detailed and located on the Segment Drawings as part of the available shop drawings, and the locations are visible from below on the deck soffit. See Sheet No. PT1, PT4, and PTL-1 through 6 (pdf pages 27, 30 and 35-40 of 237). Verification of the as-built locations is the Contractor’s responsibility.

-6-
Submitted: Wednesday 29-OCT-2025 11:38 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Section 32.C.2 references an inspection report for approximate locations of crack widths and locations. Can this report be made available?

-7-
Submitted: Wednesday 29-OCT-2025 11:38 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Can a verifiable, experienced QA/QC person replace the manufacturer's rep for the first 1,000 LF of epoxy injection?
Answer
Submitted: Thursday 30-OCT-2025 11:51 AM
Subject to further review and acceptance of the independent QAQC person’s written qualifications, experience, training, and familiarity with the manufacture’s product. As a minimum, on-site training from the qualified manufacturer’s representative is required along with the manufacture’s verification of proper installation for at least the first 100-ft of successful crack injection as approved by the Project Manager.

-8-
Submitted: Wednesday 29-OCT-2025 11:39 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Will temporary openings be allowed through the top deck? What rebar and post-tensioning reinforcement is in the deck? Can a complete set of as-built and PT shop drawings be made available?
Answer
Submitted: Friday 31-OCT-2025 09:50 AM
Additional temporary openings are not allowed due to the presence of transverse PT in the top slab.  Access openings are shown on sheet B5 of the contract drawings.  As-Built plans and Segment Drawings are provided in the Q&A forum responses to Questions No. 1 and 5, respectively.

-9-
Submitted: Wednesday 29-OCT-2025 11:39 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Clarify which AISC certification is required for the fabricator that will produce the tendon braces, and if so which class of certification is required.
Answer
Submitted: Thursday 30-OCT-2025 11:54 AM
MDT will require Intermediate Bridges (IBR) as the minimum quality certification as defined in Standard Specification 556.03.1.

-10-
Submitted: Wednesday 29-OCT-2025 11:39 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
What are the details of the utility relocation contract? What is the anticipated completion date for this work?

-11-
Submitted: Wednesday 29-OCT-2025 11:39 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
What is the maximum load allowed at each of the existing 3" deck sleeves to support the platform? If multiple platforms are installed, does the 50,000 lb dead load weight limit for each span?
Answer
Submitted: Friday 31-OCT-2025 10:15 AM
The sum of the deck Anchor Bar connections as detailed in the plan schematic (Sheet B11) which utilize the existing 3” sleeves may not exceed a total service load of 20-kips over a 15-ft length measured parallel to the roadway.
The total service dead load for all platform connections within a span may not exceed 50-kips.

-12-
Submitted: Wednesday 29-OCT-2025 11:40 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Bid items 30, 100, & 330 are fixed dollar amounts. What is MDT intention and application for these bid items?

-13-
Submitted: Wednesday 29-OCT-2025 11:40 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Is there a posted load restriction on the bridge?

-14-
Submitted: Wednesday 29-OCT-2025 11:40 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Will prepackaged SCC concrete be allowed in lieu of the batched SCC mix specified? Wil the design requirements be the same for prepackaged material?

-15-
Submitted: Wednesday 29-OCT-2025 11:40 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Does the 3% excise tax apply in addition to the IOS and TERO fees, and what specifically does it cover?

-16-
Submitted: Wednesday 29-OCT-2025 11:41 AM
Company: Structural Technologies, LLC
Contact: Tina Carter
Can a MDT right of way plan be made available?

-17-
Submitted: Wednesday 29-OCT-2025 12:37 PM
Company: Hamilton Construction Co.
Contact: Jan Lusso
Please provide the organizations and contact information for services within the Blackfeet Indian Reservation as discussed by Blackfeeet TERO during the mandatory pre-bid meeting (i.e. disposal services, sanitary facilities, etc.).

-18-
Submitted: Friday 31-OCT-2025 01:56 PM
Company: Hamilton Construction Co.
Contact: Jan Lusso
Please provide specification language and payment provisions for Bid Item 200 TRANSVERSE DECK GROOVING (5,650.80 SQYD)

102 - TERRY-NORTH - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

103 - BRIDGE REHAB-THOMPSON FALLS - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Sunday 26-OCT-2025 02:16 PM
Company: RAZZ Construction, Inc.
Contact: Don Rasmussen
Please provide as-builts of existing bridge deck and traffic barrier.
Answer
Submitted: Wednesday 29-OCT-2025 07:12 AM
The files linked below represent the as-built drawings for the structures. MDT provides them for informational purposes only. They do not include drawings for modifications to the structures, such as joint replacements and guardrail revisions and may not completely represent current conditions. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents.

As-Builds Links:

LINK 1
LINK 2

-2-
Submitted: Thursday 30-OCT-2025 07:03 AM
Company: Hamilton Construction Co.
Contact: Wendell Snook
Plan Sheet No. B1 has and Estimated Overlay Volume of 81.6cy. Based on deck area and a 2" overlay it apears this quantity should be doubled to 163.2cy. Would MDT please verify the estmated quantity.
Answer
Submitted: Friday 31-OCT-2025 08:35 AM
Estimated Bridge Plan Quantities are hereby revised as follows:
**Estimated Overlay Volume has been increased from 81.6 CUYD to 163.2 CUYD
The following plan sheet have been updated.
Link
An amendment will be issued; updated bid files will be posted.

-3-
Submitted: Thursday 30-OCT-2025 07:08 AM
Company: Hamilton Construction Co.
Contact: Wendell Snook
Bid Item 0140 Refurbish Expansion Joint quantity of 84 LNFT appears to be in error and should be doubled. Would MDT please verify the bid quantity.
Answer
Submitted: Friday 31-OCT-2025 08:37 AM
Estimated Bridge Plan Quantities are hereby revised as follows:
Bid Item # 552 011 040 – Refurbish Expansion Joint has been increased from 84.0 LNFT to 168.0 LNFT
The following plan sheet have been updated.
Link
An amendment will be issued; updated bid files will be posted.

 

-4-
Submitted: Thursday 30-OCT-2025 04:12 PM
Company: Sletten Construction
Contact: Russ Robertson
For Special Provision 31, REMOVE ASPHALT FROM DECK, it states that use of rotomilling to remove plant mix from deck is not permitted. However, under Special Provision 30, the specification allows us to use mechanical milling to reach a shallower depth prior to hydrodemolition. With that in mind, why are prohibiting rotomilling the plant mix? Wouldn't you achieve both outcomes, both removing the asphalt and achieving the shallower depth prior to hydrodemolition, at the same time?

104 - GRANT-WEST - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

No Questions available for this project.

105 - W HOLLY ST PED BRIDGE-SIDNEY - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Thursday 23-OCT-2025 02:08 PM
Company: Rinker Materials - Rapid City, SD
Contact: Brian Jenner
For clarification, is the beam height 37 inches instead of 35 inches as shown in the Bulb Tee Dimensions Table on Sheet B11?
Answer
Submitted: Wednesday 29-OCT-2025 02:02 PM
The girder depth is 35 inches, and the bridge contractor will need to install a PPC overlay over the entire length of the bridge with a minimum thickness of ¾” at mid-span and up to 2 ¼” at each end.

Special Provision #29 POLYMER OVERLAY is hereby replaced with Special Provision: POLYESTER POLYMER CONCRETE OVERLAY

The following items are hereby deleted from the contract:
Bid item #563 000 040 POLYMER OVERLAY - 99.89 SQYD
Bid item #563 000 045 POLYMER OVERLAY PRIMER - 99.89 SQYD

The following items are hereby added to the contract:
Bid item #563 000 030 PLACE PPC OVERLAY - 99.89 SQYD is added to the contract.
Bid item #563 000 020 FURNISH PPC OVERLAY – 5.1 CUYD is added to the contract.

Sheets B1, B2, B5, B8 and B11 have been updated and can be found here:  UPDATED SHEETS

An amendment will be issued;  updated bid files will be posted.

106 - THREE FORKS AREA BRIDGE DECKS - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Thursday 30-OCT-2025 09:41 AM
This project is being re-advertised.  Changes may have been made to the prior bid package.  If you submitted a question when this project was previously advertised and believe your question is still applicable, please ask the question on the Q&A forum again. By doing so, your question and MDT’s corresponding answer will become part of the contract.


Questions

No Questions available for this project.

107 - I-15 BRIDGE DECKS-BUTTE AREA - November 13, 2025

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Thursday 30-OCT-2025 09:43 AM
This project is being re-advertised.  Changes may have been made to the prior bid package.  If you submitted a question when this project was previously advertised and believe your question is still applicable, please ask the question on the Q&A forum again. By doing so, your question and MDT’s corresponding answer will become part of the contract.


Questions

No Questions available for this project.

301 - GF DISTRICT ADA UPGRADES & OFF SYSTEM SIDEWALKS - GF - November 12, 2025

Notifications

-1-
Submitted: Monday 30-JUN-2025 02:45 PM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the tied Design-Build project identified below. The advertisement for the Requests for Qualifications has been opened and contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on July 21, 2025.

Project Name:           GF District ADA Upgrades
Project No.:               CM 57-1(14)0
Control No.:              10589000

The Great Falls District ADA Upgrades project is intended to improve accessibility and mobility within the City of Great Falls.  Existing facilities do not meet current ADA standards, and upgrades to the existing infrastructure are warranted, and have been previously identified as a part of MDT’s ADA transition plan.  Possible treatments to remove accessibility barriers include replacement of non-compliant ADA curb ramps, installing pedestrian actuated pushbuttons, eliminating tripping hazards, deteriorated sections, and non-compliant cross slopes. Locations include 1st Avenue North, 2nd Avenue North, 14th Street, and 15th Street.

Tied with:
Project Name:            Off System Sidewalks - GF
Project No.:                CMGF STWD(977)
Control No.:               10190000

The Off System Sidewalks – Great Falls project is intended to improve sidewalk connectivity through construction of new sidewalk facilities where existing pedestrian routes have only intermittent sidewalks. This project is located primarily in the northwest quadrant of the City of Great Falls.  Major improvements include the construction of new sidewalks and ADA-compliant curb ramps

The project RFQ and attachments can be found at the following link: RFQ ATTACHMENTS

-2-
Submitted: Tuesday 05-AUG-2025 08:08 AM
Notification 1:
Short-listed Firms (in alphabetical order)

  • Century-Stahly
  • Montana Materials & Construction-KLJ
  • United Materials-DOWL

Notification 2:
MDT will delay issue of the Request for Proposals for the subject tied projects. MDT will provide an updated procurement schedule when it becomes available.

-3-
Submitted: Tuesday 12-AUG-2025 12:04 PM
The revised procurement schedule has not yet been determined.  As such, the Pre-proposal Meeting scheduled for August 14, 2025, will not take place as originally planned.  The Pre-proposal Meeting will be rescheduled to occur after issuance of the RFP.

-4-
Submitted: Tuesday 26-AUG-2025 09:20 AM
The revised procurement schedule for the tied Great Falls sidewalk design-build project (UPNs 10589 and 10190) is as follows:

DATE EVENT
August 5, 2025 Short List posted on Q&A Forum
September 17, 2025 Request for Proposal Issue
September 24, 2025 Pre-Proposal Meeting – 11:00AM MDT
October 22, 2025 Q&A Forum Closes – 5:00PM MDT
October 29, 2025 Technical Proposal Due Date – 11:00AM MDT
November 12, 2025 Bid Price Proposal Due Date – 11:00AM MDT MST
December 16, 2025 Award Date
December 30, 2025 Notice to Proceed (*Approximate)

UPDATE:
Submitted: Friday 03-OCT-2025 12:37 PM
November 12, 2025 - Bid Price Proposal Due Date time corrected to 11:00 AM MST

-5-
Submitted: Wednesday 15-OCT-2025 10:30 AM
Linked below is the Pre-proposal Meeting Agenda.  Questions and other discussion topics from the meeting are documented in the Clarifications and Questions sections of this Q&A Forum.
PRE-PROPOSAL MEETING AGENDA

-6-
Submitted Wednesday 15-OCT-2025 3:09 PM
Pursuant to an interim final rule issued by the US Department of Transportation (see 90 Fed. Reg. 47969 (Oct. 3, 2025)), the previously published DBE aspirational goal of 14.4% for this project is removed and revised to a DBE aspirational goal of 0%.
 


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Friday 03-OCT-2025 12:08 PM
The intent of the signal upgrades outlined in the project scope is to enhance pedestrian accessibility and safety through the installation of new pedestrian push buttons and countdown signals, which provide both visual and audible cues to users. The project does not include changes to the existing traffic signal timing or overall intersection operations.

-2-
Submitted: Monday 06-OCT-2025 03:57 PM
Construct new concrete sidewalk sections with reinforcement in accordance with the City of Great Falls standard details. Include all costs associated with reinforced concrete sidewalk sections in the lump sum Bid Price Proposal.


Questions

-1-
Submitted: Tuesday 08-JUL-2025 10:52 AM
Company: Stahly Engineering & Associates
Contact: Alisa Etzel
Regarding the Public Involvement portion of the RFQ. Section VII.A.1. states that we are to include qualified public involvement personnel on our team. Does this requirement mean we must use a firm from the MDT term roster, or can we utilize our own qualified in-house staff?
Answer
Submitted: Thursday 10-JUL-2025 12:39 PM
Proposing Firms may, but are not required, to utilize a public involvement consultant from MDT’s term contract roster.  Firms may assign the Public Relations Coordinator role to any qualified individual.

-2-
Submitted: Wednesday 24-SEP-2025 03:05 PM
Company: DOWL
Contact: Marissa Madsen
If an existing ramp is a "parallel" ramp, does we have to maintain a "parallel" ramp? This question is also pertinent to other ramp types and if they are intended to be the same type upon completion of the project.
Answer
Submitted: Monday 29-SEP-2025 11:10 AM
The Firm is responsible for determining the final ramp configuration for crossing locations throughout the project. The final design must comply with all applicable design and accessibility standards, while also fulfilling with the project intent to construct permanent improvements within existing right-of-way.

-3-
Submitted: Thursday 25-SEP-2025 03:43 PM
Company: KLJ
Contact: Dan Richardson
If the existing curb and gutter is determined to be in good condition in a location where the RFP states it to be replaced, can the curb and gutter remain in place?
Answer
Submitted: Monday 29-SEP-2025 11:05 AM
MDT identified locations where curb and gutter replacement may be necessary to address existing curb condition, enhance drainage, improve sidewalk constructability, and achieve PROWAG compliant facilities. However, it is the responsibility of the Firm to evaluate all project locations and determine the final limits of curb and gutter replacement based on the Firm’s final sidewalk design, and construction means and methods.

-4-
Submitted: Wednesday 01-OCT-2025 09:21 AM
Company: Montana Lines, Inc.
Contact: Estimating
Please provide electrical as-builts for all intersections that involve electrical work.
Answer
Submitted: Wednesday 08-OCT-2025 02:18 PM

Some as-built plan information, including documentation of existing electrical components, is provided in RFP Attachment H. Additional available as-built information can be accessed at the following link: AS BUILT INFO
The accuracy and completeness of the as-built information cannot be guaranteed and should be independently verified by the Firm as needed for design, bidding, and construction purposes.

-5-
Submitted: Monday 06-OCT-2025 10:54 AM
Company: DOWL
Contact: Marissa Madsen
If an existing ramp is 4’ wide and the City of Great Falls design standard is 5’ minimum width, does the new ramp width need to comply with City of Great Fall Standards?
Answer
Submitted: Wednesday 08-OCT-2025 09:37 AM
Design and construct all new curb ramps in accordance with the City of Great Falls Standard Details. Ensure full compliance with the Public Rights-of-Way Accessibility Guidelines (PROWAG) to meet federal accessibility requirements. When PROWAG standards exceed local requirements, PROWAG governs.

-6-
Submitted: Monday 06-OCT-2025 10:55 AM
Company: DOWL
Contact: Marissa Madsen
Installing push buttons on several existing poles isn’t going to result in an ADA compliant facility. Does MDT want teams to bid the project per the scope if it results in non-ADA compliant facilities?
Answer
Submitted: Wednesday 08-OCT-2025 09:33 AM
Quantities provided in the RFP are for informational purposes only and should not be used for bidding purposes. The RFP is not prescriptive; an additional separated pole, or a suitable innovation may be required at some locations to provide an ADA / PROWAG compliant facility. Per RFP section V.B.3.a.iii, the Firm should identify locations where standard sidewalk design details may not be suitable, or where it may be technically infeasible to implement improvements that are compliant with ADA / PROWAG requirements.

-7-
Submitted: Thursday 09-OCT-2025 01:42 PM
Company: Century Companies, Inc.
Contact: Estimating
Section R Paragraph 8 of the RFP provides unit prices for incentives and deductions. 6" and 8" sidewalk prices are provided but 4" sidewalk is not shown. It appears that both City of Great Falls and MDT design standards would allow for 4" sidewalk at mid-block areas. Is it the intention of MDT that all sidewalk including mid-block be at least 6" thick?
Answer
Submitted: Tuesday 14-OCT-2025 9:07 AM
The unit price for establishing material incentives and deductions for 4-inch sidewalk was inadvertently omitted from the RFP. Sidewalk thickness should be determined in accordance with the applicable standard design details. The RFP is hereby revised to include the following unit prices for use in evaluating incentives and deductions:
    a.  Sidewalk Concrete, 4-inch - $151 per sqyd
    b.  Sidewalk Concrete, 6-inch - $199 per sqyd
    c.  Sidewalk Concrete, 8-inch - $225 per sqyd

-8-
Submitted: Monday 13-OCT-2025 02:20 PM
Company: DOWL
Contact: Marissa Madsen
Will the City of Great Falls have any approval authority of final plans and/or final acceptance of construction in addition to MDT for off-system work?
Answer
Submitted: Wednesday 15-OCT-2025 12:22 PM
In accordance with applicable agreements and the MDT Standard Specifications, MDT holds primary responsibility for preconstruction project development oversight, construction contract administration, and final project acceptance. The City of Great Falls will maintain an active advisory role throughout the duration of the project, providing input and coordination support as needed.

-9-
Submitted: Thursday 16-OCT-2025 04:19 PM
Company: KLJ
Contact: Dan Richardson
What are the expectations for pavement markings? If they do not exist and we are adding a new crossing, do we need to add cross walk pavement markings with signage?
Answer
Submitted: Friday 24-OCT-2025 07:50 AM
Install new pavement markings for pedestrian crossings in accordance with the Manual on Uniform Traffic Control Devices (MUTCD). Evaluate all existing pavement markings for compliance with MUTCD standards, and replace, remove, or update them as necessary to ensure full compliance.

When transverse lines are used to delineate a pedestrian crossing, where permitted under MUTCD guidelines, the City of Great Falls prefers the following specifications:
    -     The minimum gap between transverse lines should be at least 8-feet.
    -     The white boundary striping of the crosswalk should be at least 8-inches wide.

-10-
Submitted: Wednesday 22-OCT-2025 04:22 PM
Company: DOWL
Contact: Erin Karlin
Adding pedestrian-guiding poles to the corners of this project will require wire to them from each existing traffic signal controller cabinet. This requires cabling to cross under the street(s) of the intersection. Conduit and cabling currently exist for street crossings under these intersections, but the size, condition, and fill-capacity of existing street crossings is unknown. Further, it is not known if the existing cable is free to move or has been locked up over the years, especially in long-buried steel conduit present throughout these corridors. If the existing cabling cannot move within the conduit, more cabling cannot be added. Whether the cabling is free or not cannot be determined from simple inspection. One solution is to install all new conduit street crossings at each instance throughout the project, which would add a significant amount to our proposal. Please provide direction as to what assumptions to make about using existing conduit street crossings. Would the Department consider adding a per LF bid/pay item for instances where new conduit crossings are required?
Answer
Submitted: Friday 24-OCT-2025 02:51 PM
For bidding purposes, assume the existing conduit is in usable condition. Any necessary adjustments due to differing field conditions will be addressed through miscellaneous work or a change order.

-11-
Submitted: Wednesday 22-OCT-2025 04:55 PM
Company: DOWL
Contact: Erin Karlin
We understand that signs impacted by the project need to be relocated or replaced. Some signs along the project corridors appear to be MDT-maintained signs, and others are Great Falls-maintained signs. For signs that are impacted and need replacement, what standard should be used? If the Great Falls standards are to be followed, please provide the necessary information.
Answer
Submitted: Friday 24-OCT-2025 03:46 PM
All signs impacted by the project must be relocated or replaced in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), 11th Edition. This includes compliance with MUTCD standards for sign face design, location, color, font, size, and type, etc.  Where installation of new sign supports is required, all support structures must conform to the applicable MDT Detailed Drawings.

302 - KAGY BLVD - S 19TH TO WILLSON - April 15, 2026

Notifications

-1-
Submitted: Wednesday 01-OCT-2025 10:00 AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by
11:00 a.m., local time on October 29, 2025.

Project Name: KAGY BLVD – S 19TH TO WILLSON
Project No: STPU-SSS 1212(8)
Control No: 8931000

This project is located within the City of Bozeman on Kagy Boulevard from S. 19th Avenue to S. Willson Avenue. The scope of work for this project includes widening and reconstruction of Kagy Boulevard from S. 19th Avenue to S. Willson Avenue with intersection improvements. This includes two travel lanes in each direction, new curb and gutter, boulevard, multi-use path on both sides of the roadway, lighting, landscaping, storm drain, pedestrian crossing facilities via grade separation and/or at-grade solutions and raised median/turn lanes. Intersection improvements include two multi-lane roundabouts: one at the S. 11th Avenue intersection and another at the S. 7th Avenue intersection and signal improvements and protected intersection components at the S. Willson Avenue intersection.

The project RFQ and attachments can be found at the following link: RFQ and ATTACHMENTS
 

-2-
Submitted: Tuesday 07-OCT-2025 07:27 AM
The draft Preliminary Plans, referred to on page 3 of the Request for Qualifications, can be found here: 8931-Kagy-Prelminary-Plans.  The Preliminary Plans that will be provided with the RFP transmittal may differ from the draft Plans provided in the link.


Amendments

No Amendments available for this project.


Clarifications

No Clarifications available for this project.


Questions

-1-
Submitted: Thursday 16-OCT-2025 05:56 AM
Company: Sundt Construction
Contact: Ben Becker
The RFQ states: Firms must attach a notarized statement from an admitted surety insurer authorized to issue bonds in the State of Montana that states: a. Firm's current bonding capacity is sufficient for the project and referenced payment and performance bonds; and b. Firm's current available bonding capacity. Is this required to be included in the SOQ or is this only to be included in the RFP? This isn't mentioned in the SOQ submittal requirements and want to confirm it should be included and if so that it won't count as a page in the page count.
Answer
Submitted: Tuesday 21-OCT-2025 07:15 AM
The RFP Section VIII applies only to the short-listed Design-Build firms. The bonding requirements listed in VIII.E.  will be included as a proposal submittal requirement.

-2-
Submitted: Thursday 16-OCT-2025 05:51 AM
Company: Sundt Construction
Contact: Ben Becker
Based on the recent DBE developments and guidance, will those requirements be removed from the RFP? If so, will it switch to just SBE requirements?
Answer
Submitted: Tuesday 21-OCT-2025 07:03 AM
Pursuant to an interim final rule issued by the US Department of Transportation (see 90 Fed. Reg. 47969 (Oct. 3, 2025), the previously published DBE aspirational goal of 10.3% for this project is removed and revised to a DBE aspirational goal of 0%. The requirement of 10.3% SBE participation will remain as outlined in the RFQ.

-3-
Submitted: Thursday 16-OCT-2025 05:49 AM
Company: Sundt Construction
Contact: Ben Becker
For the requirement to provide Proof of Professional Liability Insurance, is it acceptable to have that provided by the just the Prime Firm (Contractor) or is it also needed from the Lead Design Firm on the team.
Answer
Submitted: Monday 20-OCT-2025 07:05 AM
Proof of Professional Liability Insurance for the Lead Design Firm is required.