July 14, 2025

The Montana Department of Transportation and Ti-Zack Concrete continue work on the 6th Street NW/SW rehabilitation project.

The crossover detour has been removed, and traffic is now traveling in the outside northbound lane and the outside southbound lane. This configuration will remain in place for the time being, with no additional traffic changes currently planned.

Crews are grinding the road surface from the north end of the Sun River Bridge to Central Avenue West. This work involves slow-moving equipment in the closed, inside lanes and will also result in shifting lane restrictions in the repair-only section of the project from American Avenue to Central Avenue West. Drivers are encouraged to stay alert through this stretch of the corridor.

Work continues to form and pour new concrete medians in the reconstructed section of the project. Roadway repairs between Central Avenue West and the Northwest Bypass are also ongoing. Repairs are expected to be complete by the end of the week, weather and other unforeseen factors permitting. Single-lane closures and flaggers will remain in place in this area until work is done.

On Fox Farm Road, repair work is anticipated to begin once the work between Central Avenue West and the Northwest Bypass is complete.

Please drive with caution and watch for crews and signage in the work zone.

July 7, 2025

The Montana Department of Transportation (MDT) and Ti-Zack Concrete continue construction to rehabilitate the 6th Street NW/SW corridor. Traffic remains shifted to the newly paved northbound lanes, and this configuration will remain in place for the time being, with no changes to traffic control currently planned.

Crews are continuing to repair the roadway and beginning median work and joint sealing. Median work will take place only in the reconstructed section of the project. Joint sealing will occur across the entire project area and require single-lane closures in both directions.

Repair work on Fox Farm Road is anticipated to begin the week of July 14.

On 6th Street NW, between American Avenue and the NW Bypass, single-lane closures and reduced speed limits remain in effect. The location of active work zones will continue to shift throughout the week.

As always, work is dependent on weather and unforeseen circumstances. Thank you for staying cautious and watching for signage and crews in the work zone.

June 30, 2025

Construction continues along 6th Street SW. Traffic remains shifted to the newly paved northbound lanes. This configuration will stay in place through the holiday weekend, with no changes to traffic control.

Crews aim to finish placing new concrete in the southbound lanes before the 4th of July holiday. Work will is anticipated to pause on Thursday, July 3 at approximately 3 p.m. and resume on Monday, July 7.

Traffic control continues at the Fox Farm Road intersection, where only one through lane remains open to access 6th Street SW. Drivers should be alert and watch for signage and lane restrictions in this area.

Repair work also continues on 6th Street NW between American Avenue and the NW Bypass. Single-lane closures and reduced speed limits are still in effect, and the location of active work zones will be shifting throughout the week. All traffic control on 6th Street NW will be removed over the holiday weekend and reinstated after July 7.

Work is dependent on weather and unforeseen circumstances. Thank you for staying cautious, slowing down, and looking out for crews in the work zone.

June 23, 2025

Construction activity along 6th Street SW continues, and no major changes to traffic patterns are expected this week. Traffic remains shifted to the newly paved northbound lanes while crews continue pavement removal and concrete work on the southbound lanes. This configuration will remain in place for the foreseeable future.

Traffic control continues at the Fox Farm Road intersection, where only one through lane remains open to access 6th Street SW. Drivers should be alert and watch for signage and lane restrictions in this area.

Repair work is ongoing between American Avenue and the NW Bypass. Single-lane closures and reduced speed limits are still in effect, and the location of active work zones is shifting throughout the week.

As always, all work is dependent on weather and unforeseen circumstances. Thank you for staying cautious, slowing down, and looking out for crews in the work zone. Your continued patience helps ensure everyone’s safety.

June 16, 2025

Traffic remains shifted to the newly paved northbound lanes of 6th Street SW, as crews begin pavement removal and concrete pouring on the southbound lanes. This traffic configuration will continue for the coming weeks.

Additional traffic control remains in place at the Fox Farm Road intersection, where only one through lane is open to access 6th Street SW. Please use caution and watch for flaggers and lane restrictions in this area.

Repair work continues between American Avenue and the NW Bypass, with single-lane closures and reduced speeds. Locations of active work may change throughout the week.

All work depends on weather and other unforeseen conditions. Thank you for driving carefully and staying alert in the work zone. Your patience and caution help keep the community and workers safe.

June 9, 2025

Significant traffic changes are coming to the 6th Street NW/SW roadway resurfacing project in Great Falls. Concrete pouring in the northbound lanes of 6th Street SW has been completed.

Beginning Tuesday, traffic will be switched to the opposite side of the road. As crews begin concrete removal on the southbound side, northbound and southbound traffic will be detoured to the newly completed northbound lanes.

Additional traffic control will be in place at the Fox Farm Road intersection, where only one through lane will remain open to access 6th Street SW. Please watch for lane restrictions and flaggers.

Repair work will also begin north of American Avenue and along 6th Street NW. Expect single-lane closures and reduced speeds in these areas.

Drainage facility work at the south intersection of Crescent Circle is now finished, and the intersection has reopened to traffic.

Gas line replacement is also complete throughout the project area.

As always, please drive cautiously, follow posted signage, and be alert for lane shifts, flaggers, and construction equipment. Thank you for your continued patience during this important improvement project.

June 2, 2025

On the 6th Street NW/SW roadway resurfacing project in Great Falls, northbound traffic remains shifted to the southbound lanes just past the Sun River Bridge. This crossover pattern will stay in place as work continues. Please watch for cones, yield signs, and crews in the area.

This week, crews are pouring concrete in the northbound lanes of 6th Street SW.

Drainage facility work at the north intersection of Crescent Circle continues, and the closure is expected to last a few more weeks as crews install the remaining drainage features and pave the intersection.

Gas line replacement is now complete throughout the project area. No closures are in place for gas work, and paving is beginning through the intersections where this work occurred, with access to side streets maintained.

There is no active work occurring on 6th Street NW at this time.

As always, please drive cautiously, follow posted signage, and be alert for lane shifts, flaggers, and construction equipment. Thank you for your continued patience during this improvement project.

May 27, 2025

On the 6th Street NW/SW roadway resurfacing project in Great Falls, northbound traffic remains shifted to the southbound lanes just past the Sun River Bridge. This crossover traffic pattern will stay in place as work continues. Please watch for cones, yield signs, and crews in the area.

This week, concrete removal and replacement continues on the northbound side in various locations. Pavement installation and grading are also underway in the crossover section between the Sun River Bridge and American Avenue.

Gas line replacement continues mainly behind the sidewalks and at intersections with side streets. As concrete placement around the new gas line continues through the intersections of 9th Avenue SW and 10th Avenue SW, drivers should watch for detour signage.

Storm drain work is ongoing in Crescent Circle. The south intersection of 6th Street SW and Crescent Circle remains closed. Access is available from the north intersection. The closure is expected to last about three more weeks.

If paving on 6th Street SW is delayed due to weather or other unforeseen factors, repair work will continue on 6th Street NW. Expect single-lane closures with crews and equipment present. Only one lane will be closed at a time to maintain traffic flow.

May 19, 2025

On the 6th Street NW/SW Roadway Resurfacing project in Great Falls, northbound traffic remains shifted to the southbound lanes just past the Sun River Bridge. This crossover traffic pattern will stay in place while work continues. Please watch for cones, yield signs, and crews as you travel through the crossover.

This week, pavement installation and grading will begin in the crossover section of the project, between the Sun River Bridge and American Avenue.

Gas line installation is ongoing and will require temporary detours.

  • While crews work near 9th Avenue SW, traffic will be detoured to 10th Avenue SW.
  • As crews move to 10th Avenue SW, traffic will be detoured to 9th Avenue SW.

Storm sewer and utility work is in progress. The south intersection of 6th Street SW and Crescent Circle remains closed. It is expected to reopen in about a month. In the meantime, access is available from the north intersection.

If paving on 6th Street SW cannot proceed due to weather or other unforeseen factors, repair work will continue on 6th Street NW. Expect single-lane closures with crews and equipment present. Only one lane will be closed at a time to maintain traffic flow.

To accommodate holiday traffic over Memorial Day weekend, no work will occur from Friday afternoon, May 23, through Monday, May 26. Normal work hours will resume Tuesday, May 27.

May 12, 2025

On the 6th Street NW/SW Roadway Resurfacing project in Great Falls, northbound traffic remains shifted to the southbound lanes just past the Sun River Bridge. This crossover traffic pattern will stay in place while work continues. Please watch for cones, yield signs, and crews as you travel through the crossover.

Gas line replacement is now underway and will require temporary detours.

  • While crews work near 9th Avenue SW, traffic will be detoured to 10th Avenue SW.
  • As crews move to 10th Avenue SW, traffic will be detoured to 9th Avenue SW.

The south intersection of 6th Street SW and Crescent Circle is now closed for storm drain installation. Please use alternate routes and watch for updates.

Crews have also started repair work in the northern section of the corridor, on 6th Street NW. Expect single-lane closures with crews and equipment present. Only one lane will be closed at a time to maintain traffic flow.

May 5, 2025

Construction continues on the 6th Street NW/SW Roadway Resurfacing project between 10th Avenue South and American Avenue. This is the only active work zone in the project area at this time.

Crews have started removing the concrete pavement, and northbound traffic has shifted onto the southbound lanes just past the Sun River Bridge. This crossover will remain in place for the foreseeable future while work continues on the northbound side. Please follow all posted signage and use caution in the work zone.

Over the next several days:

  • Concrete removal will continue heading south.
  • Gas line replacement is expected to begin.
  • The south intersection of 6th Street SW and Crescent Circle may temporarily close for storm drain work. Watch for signage and crews in the area.

Surveying may continue along other parts of the corridor to prepare for future repairs.

Looking ahead to the week of May 12, resurfacing work may begin in the other sections of the corridor. We will provide more details as work progresses.

April 28, 2025

This week, work will continue on the 6th Street NW/SW Roadway Resurfacing project, with crews focused on the section between 10th Avenue South and American Avenue. This is the only area currently under construction.

Crews will begin breaking pavement and removing medians in this section of the project. Northbound and southbound traffic patterns will initially be unchanged, but single-lane restrictions will be in place and may change daily. Please watch for cones and signage.

You may also see crews surveying in other parts of the corridor to prepare for upcoming repairs. Please drive carefully and watch for workers and vehicles.

A traffic crossover may happen as early as this Friday or Saturday. When it begins, northbound traffic will shift to the southbound lanes just after the bridge. This will become the long-term traffic pattern while crews work on the northbound side.

Thank you for your continued patience and safe driving as this project moves forward.

April 21, 2025

6th Street Traffic Control Starting April 22

Traffic-controlled work on 6th Street SW in Great Falls will start Monday afternoon, April 22. Crews will first close the right northbound lane and the east shoulder, starting at the Sun River Bridge and heading north toward American Avenue.

The old concrete will be saw-cut and then cracked for removal. During this work, the speed limit will be reduced to 30 miles per hour. Please watch for lane closures, signage, workers, and large equipment.

Later in the week, crews will saw-cut and crack the curbs on the southbound side and the center of the road to prepare for further work.

National Work Zone Awareness Week

April 21-25, 2025 | nwzaw.org [nwzaw.org]

Respect the zone, so we all get home.

In 2023, 282 work zone crashes occurred in Montana. This construction season, MDT urges Montana drivers and visitors to use extra caution while traveling through work zones by paying attention and following posted signage.

Our families thank you.