June 28, 2024

The Montana Department of Transportation (MDT) and Hollow Contracting Inc. have completed crack sealing on Amherst Avenue, Grand Avenue, and Elizabeth Warren Avenue. Crews anticipate completing paving on Four Mile Road this week, weather and other factors permitting.

The only work anticipated for the week of July 1 is cutting and concrete work for manhole and water main holes on the newly paved Four Mile Road. No work will take place between July 4 and July 7.

Crews plan to return to work on July 8 and begin chip sealing the project areas.

What to expect:

  • Flaggers or traffic-sensing smart signals may direct traffic.
  • Reduced speed limits.
  • Possible delays.
  • On-street parking may be limited at times during construction.
  • Wide loads may be restricted on a case-by-case basis for the roadways. Visit 511mt.net for the most up-to-date information.

June 21, 2024

The Montana Department of Transportation (MDT) and Hollow Contracting Inc. anticipate completing crack sealing work on Grand Avenue this week. After this work on Grand Avenue, crews plan to begin crack sealing on Amherst Avenue. Following Amherst Avenue, crack sealing on Elizabeth Warren Avenue is anticipated to begin the week of June 24.

Milling and paving on Shields Avenue and Farrell Street is nearly complete. Crews anticipate beginning milling and paving on Four Mile Road the week of June 24.

All work is weather and other factors permitting.

What to expect:

  • Flaggers or traffic-sensing smart signals may direct traffic.
  • Reduced speed limits.
  • Possible delays.
  • On-street parking may be limited at times during construction.
  • Wide loads may be restricted on a case-by-case basis for the roadways. Visit 511mt.net for the most up-to-date information.

June 13, 2024

The Montana Department of Transportation (MDT) and Hollow Contracting Inc. are beginning work on the Butte Urban Pavement Preservation project, which will rehabilitate several streets in Butte. Work is anticipated to begin on Grand Avenue, Amherst Avenue, and Elizabeth Warren Avenue the week of June 17, weather and other factors permitting.

What to expect:

  • Flaggers or traffic-sensing smart signals may direct traffic.
  • Reduced speed limits.
  • Possible delays.
  • On-street parking may be limited at times during construction.
  • Wide loads may be restricted on a case-by-case basis for the roadways. Visit 511mt.net for the most up-to-date information.