Preliminary Design

  • The proposed lane configuration was revised based on comments received since the last public meeting. We now propose to include two segments where the pavement will be striped as two lanes with passing allowed where adequate sight distance is available: Updated Lane Configuration
  • A 4-legged roundabout was added at the Ambrose Creek Rd. Intersection based on comments received during the November 2021 Open House, and after further analysis and funding considerations by MDT.
  • The engineering survey, cadastral survey, and soil sampling are complete.
  • The design plans are about 75% complete.
  • The project has now reached the right-of-way acquisition phase.

Construction

  • The project will be advertised and let when the design is complete and all the permits and necessary Right-of-Way acquisition is finalized.