September 27, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting, Inc. have significantly completed the Ronan-North project. The project will now be paused until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized.
Construction is tentatively scheduled for later this year, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
MDT appreciates the input from those who shared concerns about navigating the intersection, especially for larger vehicles. MDT is committed to improving the intersection and thanks you for your patience.
Project updates will resume once design changes are finalized, and a construction date is scheduled.
September 20, 2024
Riverside Contracting, Inc. plans to complete the final sign installations next week. Single-lane closures may be required where work is occurring.
Crews will be on-site Monday, September 23, to Friday, September 27, between 7 a.m. and 6:30 p.m. All work is subject to weather and unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once sign installations are complete, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized. This construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
September 13, 2024
Riverside Contracting, Inc. is still awaiting the parts necessary to complete the remaining sign installations. Once the parts are received, the crews will proceed with the sign installations.
Single-lane closures may be required where work is occurring.
Work will occur at various times from Monday, September 16, to Friday, September 20, between 7 a.m. and 6:30 p.m. All work is subject to weather and unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once sign installations are complete, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized. This construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
September 6, 2024
Riverside Contracting, Inc. will conduct finishing work on the Ronan-North project next week. All work will occur off the roadway with little to no impact on traffic.
Crews will be onsite Monday, September 9, through Friday, September 13, between 7 a.m. and 6:30 p.m. All work is subject to weather and unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once work is complete, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized. This construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
August 30, 2024
Riverside Contracting, Inc. is awaiting the arrival of parts needed to finish the remaining sign installations, including the sign bridge, located just north of the intersection of US Highway 93 (US 93) with Adams Avenue Southeast. This sign bridge is an overhead support structure designed to hold multiple directional signs.
The parts are expected to arrive this week. Once they do, crews will complete the sign installations.
Single-lane closures may be required where work is occurring.
Work will occur at various times from Tuesday, September 3, to Friday, September 6, between 7 a.m. and 6:30 p.m. All work is subject to weather and unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once sign installations are complete, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized. This construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
LABOR DAY: Crews will pause construction activities for the Labor Day weekend by 3 p.m. on Friday, August 30, and resume on Tuesday, September 3.
August 23, 2024
Riverside Contracting, Inc. crews will continue with sign installations next week, including the sign bridge, just north of the intersection of US Highway 93 (US 93) with Adams Avenue Southeast. This is an overhead support structure that will hold multiple directional signs.
Single-lane closures may be required where work is occurring.
Work will occur Monday, August 26, through Friday, August 30, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once clean-up activities and sign installation are finished, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized. This construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
August 16, 2024
Riverside Contracting, Inc. is nearly finished with cleanup work on the Ronan-North project. Crews will continue with sign installations next week, including the sign bridge, just north of the intersection of US Highway 93 (US 93) with Adams Avenue Southeast. This is an overhead support structure that will hold multiple directional signs.
Single-lane closures may be required where work is occurring.
Work will occur Monday, August 19, through Friday, August 23, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once clean-up activities are finished, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized. This construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
August 9, 2024
Riverside Contracting, Inc. will conduct site clean-up activities on the Ronan-North project this week.
Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone.
Work will occur Monday, August 12, through Friday, August 16, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Once clean-up activities are finished, the project will be put on hold until the design changes for the intersection of US Highway 93 (US 93) with Old US 93 and 3rd Avenue are finalized.
Construction is tentatively scheduled for October, but this date may change based on factors such as the final design completion, contractor availability, weather, and unforeseen circumstances.
August 2, 2024
Riverside Contracting, Inc. crews will be onsite next week wrapping up electrical work and road sign installation throughout the project area.
Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone.
Work will occur Monday, August 5, through Friday, August 9, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Update on the intersection of US 93 with Old US 93 and 3rd Avenue:
The Montana Department of Transportation (MDT) thanks everyone who shared their concerns about navigating the intersection, especially for larger vehicles.
MDT has reviewed the original design plans for the intersection with the community's feedback in mind. The engineering team has determined that changes are necessary, and new design plans for the intersection are underway.
Construction is tentatively planned for October. This schedule is subject to change due to the completion of the final design, contractor availability, weather, and possible unforeseen factors.
July 26, 2024
Riverside Contracting, Inc. will be installing road signs along Round Butte Road, as well as continuing to install the sign bridge, an overhead sign support structure that will have multiple directional signs posted on it, just north of the intersection of US Highway 93 (US 93) with Adams Avenue Southeast.
Crews will also be finishing up electrical work throughout the project area.
Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone.
Work will occur Monday, July 29, through Friday, August 2, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Update on the intersection of US 93 with Old US 93 and 3rd Avenue:
The Montana Department of Transportation (MDT) thanks everyone who shared their concerns about navigating the intersection, especially for larger vehicles.
MDT has reviewed the original design plans for the intersection with the community's feedback in mind. The engineering team has determined that changes are necessary, and new design plans for the intersection are underway.
Construction is tentatively planned for October. This schedule is subject to change due to the completion of the final design, contractor availability, weather, and possible unforeseen factors.
July 19, 2024
The week of July 22, Riverside Contracting, Inc. will begin installing a sign bridge, an overhead sign support structure that will have multiple directional signs posted on it, just north of the intersection of US Highway 93 (US 93) with Adams Avenue Southeast.
Crews will also be installing the permanent epoxy paint on the curbs within the project area. Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone.
Work will occur Monday, July 22, through Friday, July 26, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Update on the intersection of US 93 with Old US 93 and 3rd Avenue:
The Montana Department of Transportation (MDT) thanks everyone who shared their concerns about navigating the intersection, especially for larger vehicles.
MDT has reviewed the original design plans for the intersection with the community's feedback in mind. The engineering team has determined that changes are necessary, and new design plans for the intersection are underway.
Construction is tentatively planned for October. This schedule is subject to change due to the completion of the final design, contractor availability, weather, and possible unforeseen factors.
In the meantime, the new traffic signal poles at the intersection of US 93 with Old US 93 and 3rd Avenue have been installed, and the traffic signal will be operational soon. It will remain operational until construction begins.
July 12, 2024
Riverside Contracting, Inc. will continue streetlight installation the week of July 15. Single-lane closures may be required along US Highway 93 (US 93) where work is occurring. The speed limit remains at 35 mph in the construction zone.
Crews will also finish installing road signs on Round Butte Road.
Work will occur Monday, July 15, through Friday, July 19, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Work on a solution to address the community’s concerns regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue continues. The Montana Department of Transportation (MDT) is committed to improving the intersection. We appreciate your patience and will provide an update as soon as possible.
July 5, 2024
Riverside Contracting, Inc. will continue miscellaneous site cleanup throughout the project area next week.
Streetlight installation will also resume along US Highway 93 (US 93). Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone.
On Round Butte Road, crews will be installing road signs.
Crews will be onsite Monday, July 8, through Friday, July 12, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
Please follow all posted signage and watch for workers and equipment.
Work on a solution to address the community’s concerns regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue continues. MDT is committed to improving the intersection. We appreciate your patience and will provide an update as soon as possible.
June 28, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting, Inc. will continue streetlight installation along US Highway 93 (US 93) and miscellaneous site cleanup throughout the project area the week of July 1.
Single-lane closures may be required where work is occurring. The speed limit remains at 35 mph in the construction zone. Please follow all posted signage and watch for workers and equipment.
Crews will be onsite Monday, July 1, and Tuesday, July 2, from 7 a.m. to 6:30 p.m. and Wednesday, July 3, from 7 a.m. to 3 p.m. All work is dependent on weather and other unforeseen factors.
Fourth of July Holiday: Crews will pause construction activities at 3 p.m. on Wednesday, July 3, and resume on Monday, July 8.
Work on a solution to address the community’s concerns regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue continues. MDT is committed to improving the intersection. We appreciate your patience and will provide an update as soon as possible.
June 21, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting, Inc., have the following work planned for the week of June 24.
Crews will install the final pavement markings in the turn lanes on US Highway 93 (US 93). Traffic control will be in place. The turn lane will be closed for a short period where this work is occurring.
Installation of streetlights along US 93 will also continue. Single-lane closures may be required where electrical crews are working.
Fence installation and miscellaneous site cleanup will occur throughout the project area.
The speed limit remains at 35 mph in the construction zone. Please follow all posted signage and watch for workers and equipment.
Sidewalk work on the north side of Round Butte Road is substantially complete. Crews will be paving approaches and completing clean-up activities throughout the project area.
Crews will be onsite Monday, June 24, through Friday, June 28, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
MDT appreciates the community’s feedback regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue. Solutions are being evaluated and we will provide an update as soon as possible.
June 14, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have the following work planned for the week of June 17.
Crews are continuing to install streetlights along US Highway 93 (US 93) and complete site cleanup throughout the project area.
Traffic control will be in place. Single-lane closures may be required where crews are working. The speed limit remains at 35 mph in the construction zone. Please follow all posted signage and watch for workers and equipment.
Sidewalk work also continues on the north side of Round Butte Road, east of the railroad tracks. The road shoulders are closed where work is underway, and flaggers will periodically assist with safe travel.
Crews will be onsite Monday, June 17, through Friday, June 21, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
MDT appreciates the community’s feedback regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue. Solutions are being evaluated. We will update the community once a decision has been made.
June 7, 2024
Riverside Contracting Inc. continues work on the Ronan-North project the week of June 10. Electrical crews will be onsite installing streetlight poles along US Highway 93 (US 93), and miscellaneous site cleanup will occur throughout the project area.
Traffic control will be in place. Single-lane closures may be required where crews are working along US 93. The speed limit remains 35 mph in the construction zone. Please follow all posted signage and watch for workers and equipment.
On the north side of Round Butte Road, sidewalk work continues east of the railroad tracks. The road shoulders are closed where work is underway, and flaggers will periodically assist with safe travel.
Crews will be onsite Monday, June 10, through Friday, June 14, from 7 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
In response to community feedback, the Montana Department of Transportation (MDT) is evaluating the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue. An update will be provided soon. We appreciate everyone’s patience as we work to deliver a safe solution.
May 31, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have the following work planned for June 3 to June 7.
Sidewalk work continues on the north side of Round Butte Road, east of the railroad tracks. The road shoulders are closed where work is underway, and flaggers will periodically assist with safe travel.
Crews will install streetlight poles along US Highway 93 (US 93), and miscellaneous site cleanup will occur throughout the project area.
Traffic control will be in place. Single-lane closures may be required where crews are working along US 93. The speed limit remains 35 m.p.h. in the construction zone. Please follow all posted signage and watch for workers and equipment.
Crews will be onsite Monday, June 3, through Friday, June 7, from 7 a.m. to 6:30 p.m.
MDT is aware of the concerns regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue and is actively working to evaluate the situation. We appreciate everyone’s patience as we work to deliver a safe solution and will provide an update soon.
May 24, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. will pause construction activities for the Memorial Day weekend starting today, Friday, May 24, and will resume on Tuesday, May 28.
When crews return on Tuesday, pavement clean-up will occur on US Highway 93 (US 93), and the electricians will continue installing streetlights.
Crews will also be completing sidewalk work on the north side of Round Butte Road and installing pedestrian handrails and gates throughout the project area.
Traffic control will be in place. Single-lane closures will occur where crews are working along US 93. The speed limit remains 35 m.p.h. in the construction zone. Please follow all posted signage and watch for workers and equipment.
Crews will be onsite Tuesday, May 28, through Saturday, June 1, from 7 a.m. to 6:30 p.m.
MDT is aware of the concerns regarding the newly realigned intersection of US 93 with Old US 93 and 3rd Avenue and is actively working to assess the situation. We recognize that this is a new intersection configuration and is taking some time to adjust. We appreciate everyone’s patience as we work to deliver a safe solution and will provide an update soon.
May 17, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have the following work planned for May 20 to May 23. All work is dependent on weather and other unforeseen factors.
On Round Butte Road, sidewalk work continues east of the railroad tracks. Flaggers will periodically help facilitate safe travel where work is underway.
Installation of the traffic signal poles and streetlights along US Highway 93 (US 93) also continues. Single-lane closures may be required where work is occurring.
Other planned site work includes installing pedestrian handrails and gates throughout the project area.
Crews will be onsite tomorrow, Saturday, May 18, and Monday, May 20, through Thursday, May 23, from 7 a.m. to 6:30 p.m.
Work will pause for the Memorial Day holiday weekend starting on Friday, May 24, through Monday, May 27 to accommodate increased holiday traffic and to give workers time to spend with their families. Crews will return on Tuesday, May 28.
May 10, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have the following work planned for May 13 to May 17. All work is dependent on weather and other unforeseen factors.
Electrical crews will continue installing the traffic signal poles and streetlights along US Highway 93 (US 93). Single-lane closures may be required where work is underway.
Seeding operations will begin along the highway. The road shoulder will be closed where this work is occurring.v
Sidewalk work also continues on the north side of Round Butte Road, east of the railroad tracks. The road shoulders are closed where work is underway, and flaggers will periodically be helping to facilitate safe travel.
Crews will be onsite Monday, May 13, through Friday, May 17, from 7 a.m. to 6:30 p.m.
May 3, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. crews will continue sidewalk work on the north side of Round Butte Road, east of the railroad tracks.
The road shoulders are closed where work is underway, and flaggers will periodically direct traffic.
Electrical work, including streetlight and traffic signal pole installation, is also ongoing and should be completed in the coming weeks.
All work is dependent on weather and other unforeseen factors.
Crews will be onsite Saturday, May 4, and Monday, May 6, through Friday, May 10, from 7 a.m. to 6:30 p.m.
April 26, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. crews will be finishing up sidewalk work, starting near Dairy Queen then moving to Round Butte Road, starting on the south end of the project and moving west. Riverside Contracting Inc. plans to work in sections. This will also include building small retaining walls in areas along the corridor, where needed.
Riverside Contracting Inc. will also be paving approaches to residences and businesses. Flaggers will be helping to facilitate safe travel.
Electrical work is also ongoing and should be completed in the coming weeks.
Other activities to be completed this construction season include paving the shared-use path along US 93, painting the final epoxy road markings, and other finishing work. These activities will be off of US 93 and are not anticipated to impact traffic.
Streetlights and the new traffic signal at the US 93 intersection with Old US 93 and 3rd Avenue will also be installed. The installation of the traffic signal has been delayed due to unforeseen supplier issues. MDT is working to ensure the traffic signal is installed as soon as possible.
The Round Butte Road Path - Ronan project will also be completed. This project includes building two new sections of sidewalk on the north side of Round Butte Road. This schedule is subject to change due to weather and other unforeseen factors.
April 18, 2024
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. will be conducting milling and paving operations on US Highway 93 (US 93) from the intersection with Round Butte Road north to the intersection with 3rd Avenue and Old US 93.
All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday, April 22, through Friday, April 26, from 7 a.m. to 5 p.m. until paving is complete.
Traffic will be reduced to one lane in each direction where work is underway. Please follow all traffic control and watch for workers and equipment.
These additional milling and paving operations are required because the top layer of asphalt applied in one section of the project last fall failed to meet MDT’s standards. MDT is continually testing the materials used on Montana’s roadways to ensure they are the highest quality, will withstand our harsh climate, and provide a smooth driving surface for decades to come. If a material fails to meet MDT’s standards, it is removed, and new material is installed. This occurred only in one section. While we understand this causes more disruptions, it is critical that we keep Montana moving forward by using only the very best materials that will last for years to come.
Other activities to be completed this construction season include paving the shared-use path along US 93, painting the final epoxy road markings, and other finishing work. These activities will be off of US 93 and are not anticipated to impact traffic.
Streetlights and the new traffic signal at the US 93 intersection with Old US 93 and 3rd Avenue will also be installed. The installation of the traffic signal has been delayed due to unforeseen supplier issues. MDT is working to ensure the traffic signal is installed as soon as possible.
The Round Butte Road Path - Ronan project will also be completed. This project includes building two new sections of sidewalk on the north side of Round Butte Road. This schedule is subject to change due to weather and other unforeseen factors.
December 1, 2023
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have paused construction activity on the Ronan-North project for the year.
Thank you for your patience and support during the busy construction season. Crews look forward to completing the project next year. Updates will be provided as 2024 work approaches.
Activities to be completed next year include paving the shared-use path along US 93, painting the final epoxy road markings, and other finishing work.
Streetlights and the new traffic signal at the US 93 intersection with Old US 93 and 3rd Avenue will also be installed. The installation of the traffic signal is delayed due to unforeseen supplier issues. MDT is working to ensure the traffic signal is installed as soon as possible.
The Round Butte Road Path - Ronan project will also be completed in early 2024. This project includes building two new sections of sidewalk on the north side of Round Butte Road. This schedule is subject to change due to weather and other unforeseen factors.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 17, 2023
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. will continue paving operations on US Highway 93 (US 93) north of the 3rd Avenue with Old US 93 intersection.
All work is dependent on weather and other unforeseen factors.
Crews will be onsite Saturday, November 18, and Monday, November 20, through Wednesday, November 22, from 6 a.m. to 6:30 p.m. until paving is complete.
Interim road markings will be painted once paving is complete.
Traffic will be reduced to one lane in each direction in all project areas where work is underway. Please follow all traffic control and watch for workers and equipment.
Other work planned includes seeding and clean-up activities.
Starting Thursday, November 23, all work on the Ronan-North project will be suspended until spring.
The installation of a new traffic signal at the intersection of US 93 with 3rd Avenue and Old US 93 has been delayed due to unforeseen supplier issues. MDT has sourced another supplier and will keep the public updated.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 15, 2023
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. will continue paving operations on US Highway 93 (US 93) north of the intersection with 3rd Avenue and Old US 93 this week. Work could begin as soon as today, Wednesday, November 15, when weather permits.
Traffic will be reduced to one lane in each direction through the project area where work is underway. Please follow all traffic control and watch for workers and equipment.
Once this work is complete, paving operations will be suspended until spring.
Concrete work will also continue along Round Butte Road, along with seeding on the sides of US 93.
Crews will be onsite Wednesday, November 15, through Friday, November 17, from 6 a.m. to 6:30 p.m.
During the week of November 20, crews will continue seeding and clean-up activities throughout the project area.
Crews will be onsite Monday, November 20, through Wednesday, November 22, from 6 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
The installation of a new traffic signal at the intersection of US 93 with 3rd Avenue and Old US 93 has been delayed due to unforeseen supplier issues. MDT has sourced another supplier and will keep the public updated.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 3, 2023
The Montana Department of Transportation (MDT) and Riverside Contracting Inc. have completed paving operations from the US Highway 93 (US 93) intersection with Round Butte Road, and Terrace Lake Road to the intersection with 3rd Avenue and Old US 93.
Next week, crews will paint temporary road markings on this section of the highway. Drivers should anticipate turn-lane and single-lane closures where this work is underway.
Paving operations will focus on the approach to the Sinclair gas station and the intersection of Round Butte Road with 1st Avenue. Round Butte Road will be reduced to one lane when this work occurs. Flaggers will be present.
Once this work is complete, paving operations will be suspended until spring.
Crews plan to continue sidewalk construction along Round Butte Road and the southbound couplet, the short segment of roadway connecting 1st Avenue to US 93.
The southbound couplet will be closed to traffic over the winter.
The installation of a new traffic signal at the intersection of US 93 with 3rd Avenue and Old US 93 has been delayed due to unforeseen supplier issues. MDT has sourced another supplier and will keep the public updated.
Crews will be onsite Monday, November 6, through Friday, November 10, from 6 a.m. to 6:30 p.m. All work is dependent on weather and other unforeseen factors.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 1, 2023
Riverside Contracting Inc. will be paving the south end of the US Highway 93 (US 93) Ronan-North project today, Wednesday, November 1, weather and other factors permitting.
The stoplight at the intersection of US 93 with Round Butte Road and Terrace Lake Road will be deactivated, and traffic will be reduced to a single lane and directed by flaggers. Expect delays.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
October 27, 2023
Due to the weather, Riverside Contracting Inc. will now begin paving operations on US Highway 93 (US 93) on Monday. Crews will be onsite Monday, October 30, through Friday, November 3, from 6 a.m. to 6:30 p.m., weather permitting.
Paving will begin on the southbound lanes of US 93, starting at the north end of the project area. Once work on the southbound lanes has been completed, crews will begin paving the northbound lanes.
Traffic will be reduced to one lane in each direction through the project area. Please follow all traffic control and watch for workers and equipment.
When paving operations reach the south end of the project area, near the intersection of US 93 with Round Butte Road and Terrace Lake Road, traffic will be reduced to a single lane and directed by flaggers.
Fence installation along US 93 is also planned for next week.
All work is dependent on weather and other unforeseen factors.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
October 20, 2023
Riverside Contracting Inc. will begin paving operations this week on US Highway 93 (US 93), weather permitting. Paving crews will be onsite Thursday, October 26, through Saturday, October 28, from 6 a.m. to 6:30 p.m.
The final layer of pavement will be installed on the southbound lanes of US 93, starting at the north end of the project area. Once work on the southbound lanes has been completed, crews will begin paving the northbound lanes.
Traffic will be reduced to one lane in each direction through the project area. Please follow all traffic control, and watch for workers and equipment.
When paving operations reach the south end of the project area, near the intersection of US 93 with Round Butte Road and Terrace Lake Road, traffic will be reduced to a single lane and directed by flaggers.
Crews also plan to continue concrete work, US 93 fencing installation, and sidewalk construction along Round Butte Road and the southbound couplet, the short segment of roadway connecting 1st Avenue to US 93.
All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday, October 23, through Saturday, October 28, from 6 a.m. to 6:30 p.m.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
October 13, 2023
Riverside Contracting Inc. crews will continue concrete work next week. This includes pouring concrete for property approaches on the southbound couplet, the short segment of roadway connecting 1st Avenue to US Highway 93 (US 93), and the sidewalks along the southbound couplet and Round Butte Road. Fencing installation will also continue along US 93.
Lane closures are not anticipated for these activities. All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday, October 16, through Friday, October 20, from 7 a.m. to 6:30 p.m.
Paving operations on the Ronan-North project are anticipated to resume the week of October 23, weather permitting. The final layer of pavement will be installed at that time.
Unrelated to this project, the City of Ronan will continue work to install a water pipe across Terrace Lake Road East in front of the Ronan Indian Senior Center next week. Terrace Lake Road East will be closed at the intersection with US 93.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
October 6, 2023
Next week, Riverside Contracting Inc. crews will be pouring concrete for the approaches to the Sinclair gas station and properties on the southbound couplet, the short segment of roadway connecting 1st Avenue to US Highway 93 (US 93).
Concrete work will also occur on the sidewalks along the southbound couplet and Round Butte Road, and fencing installation will continue along US 93.
Lane closures are not anticipated for these activities. All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday, October 9, through Friday, October 13, from 7 a.m. to 6:30 p.m.
Unrelated to this project, the City of Ronan will install a fire hydrant on the north side of Terrace Lake Road East in front of the Ronan Indian Senior Center today, Friday, October 6.
Next week, the city will install a water pipe across Terrace Lake Road East at this location, requiring the road to be closed at the intersection with US 93.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
Paving operations on the Ronan-North project will resume in mid-October. The final layer of pavement will be installed at that time.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
September 29, 2023
Next week, Riverside Contracting Inc. crews will continue to install fencing and signage throughout the project area, as well as beginning work on approaches for the Sinclair gas station and properties on the southbound couplet, the short segment of roadway connecting 1st Avenue to US Highway 93 (US 93). It is anticipated that lane closures will not be required for these activities.
Work will occur on Round Butte Road at the intersection with Acre Lawn Court. Crews will be installing manholes, requiring the road to be reduced to one lane. Flaggers will be present. Expect short delays.
All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday, October 2, through Friday, October 6, from 7 a.m. to 6:30 p.m.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
Paving operations on the Ronan-North project will resume in mid-October. The final layer of pavement will be installed at that time.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
September 22, 2023
Progress continues on the Ronan-North project. This week, streetlight foundations will continue to be installed along US Highway 93 (US 93), south of the intersection of Old US 93/3rd Avenue. Traffic control will be in place. Lane closures will be necessary where this work is underway. Expect reduced speeds and delays.
Riverside Contracting Inc. crews will begin installing fencing on the east side of US 93 and working north. Signage, topsoil, and cattle guard installation will occur throughout the project area. It is anticipated that lane closures will not be required for these activities.
All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday, September 25, through Friday, September 29, from 7 a.m. to 6:30 p.m.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment. The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
Paving operations on the Ronan-North project will resume in mid-October. The final layer of pavement will be installed at that time.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
September 15, 2023
Work continues on the US Highway 93 (US 93) Ronan-North project. Riverside Contracting crews will continue to work on the drainage channel on the east side of the road, across from Dairy Queen.
Topsoil placement in preparation for seeding and landscaping will continue on both sides of the highway, and guardrail installation will begin on the northbound side of US 93. Lane closures will be necessary where work is underway. Traffic control will be in place.
Work planned for next week also includes project area cleanup and installation of streetlight foundations. All work is dependent on weather and other unforeseen factors.
The speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
Paving operations on the Ronan-North project will resume in mid-October. The final layer of pavement will be installed at that time.
Next week, crews will be onsite Monday, September 18, through Friday, September 22, from 7 a.m. to 6:30 p.m.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
September 8, 2023
Next week, the Montana Department of Transportation (MDT) and Riverside Contracting Inc. crews will continue placing topsoil in preparation for seeding and landscaping. Traffic lane closures may be necessary where work is underway.
Crews also plan to finish installing cattle guards, begin installing streetlight foundations, and continue project area clean-up. All work is dependent on weather and other unforeseen factors.
Next week, crews will be onsite Monday, September 11, through Friday, September 15, from 7 a.m. to 6:30 p.m.
When traveling through the construction zone, slow down, follow all traffic control, and watch for workers and equipment.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
September 1, 2023
We hope you have a safe and happy Labor Day!
Work on the Ronan-North project has paused starting today, Friday, September 1, for the holiday weekend. Work will resume on Tuesday, September 5.
Even though crews will not be onsite, the speed limit remains at 35 mph. Please remember to follow posted speed limits when driving through the project site.
When Riverside Contracting crews return, topsoil placement in preparation for seeding and landscaping will continue. Lanes will be closed in the areas where this work is underway.
Erosion control and electrical work will also be occurring. All work is dependent on weather and other unforeseen factors.
Next week, crews will be onsite Tuesday, September 5, through Friday, September 8, from 7 a.m. to 6:30 p.m.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
August 25, 2023
Next week, Riverside Contracting crews will be paving the northbound lanes of US Highway 93 (US 93). Northbound and southbound traffic are now traveling on a paved surface throughout the project area.
Gravel installation is occurring on the section of Spring Creek Road that is being reconstructed in front of Lake Seed. Once gravel installation is complete, this section of roadway will be paved.
Cattle guard installation, work on farm field approaches, and topsoil placement in preparation for seeding and landscaping also continue. All work is dependent on weather and other unforeseen factors.
Next week, crews will be onsite Monday through Thursday from 7 a.m. to 6:30 p.m. and Friday from 7 a.m. to 3 p.m.
Labor Day holiday work schedule: Work will pause starting Friday, September 1 at 3 p.m., and resume Tuesday, September 5, to accommodate increased holiday traffic and give workers time to spend with their families.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
August 18, 2023
Next week paving will resume on the US Highway 93 (US 93) Ronan-North project. Riverside Contracting crews will also be working on highway approaches throughout the project area.
Drivers continue to travel on a gravel surface between the intersections of Baptiste Road to the project's north end. Watch for shifting travel lanes and surface transitions.
Other work planned includes reconstructing 390 feet of Spring Creek Road in front of Lake Seed. Electrical work at the Round Butte Road intersection and topsoil placement in preparation for seeding and landscaping is also planned. All work is dependent on weather and other unforeseen factors.
Next week, crews will be onsite Monday through Saturday from 7 a.m. to 6:30 p.m.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
August 11, 2023
Construction of the southbound lanes of US Highway 93 (US 93) is underway. Crews will be installing gravel next week. Watch for trucks entering and exiting the project site.
Drivers continue to travel on a gravel surface between the intersection of Baptiste Road to the project's north end. Watch for shifting travel lanes and surface transitions.
Next week, crews also plan to continue installing approaches and cattle guards on the west side of the roadway, and working on the drainage channel on the east side of the road, across from Dairy Queen. Electrical work will also resume at the Round Butte Road intersection. All work is dependent on weather and other unforeseen factors.
Crews will be onsite Monday through Friday from 7 a.m. to 6:30 p.m. next week.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
August 4, 2023
Construction of the northbound lanes of US Highway 93 (US 93) continues next week on the Ronan-North project. Gravel placement is ongoing at the north end of the project. Drivers traveling north of Baptiste Road should watch for shifting lanes and expect to travel on gravel surfaces.
Additional work on the project includes the installation of the underground electrical conduit that will support the new streetlights at the intersection of Old US 93 with 3rd Avenue, the addition of cattle guards at select approaches at the northern end of the project, and work on drainage channels.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
July 28, 2023
Milling operations are now complete on the Ronan-North project. Next week, crews anticipate finishing the northbound lanes, weather and other factors permitting.
When traveling through the northern end of the project area, north of Baptiste Road, drivers should watch for shifting lanes and expect to travel on gravel surfaces.
Work continues on the intersection of Old US 93 with 3rd Avenue to install the underground electrical conduit that will support the new streetlights.
Next week, crews will be onsite Monday through Friday from 7 a.m. to 6:30 p.m.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
July 21, 2023
Excavation operations continue next week at the project's north end, north of Baptiste Road. Traffic will be traveling on the southbound lanes, and drivers should anticipate traveling on a gravel surface through this section of the project area.
Installation of underground electrical conduit to support the new streetlights and the Old US 93 and 3rd Avenue intersection traffic signal also continues.
On Round Butte Road, sidewalk and curb construction has been suspended until early fall.
Next week, crews will be onsite Monday through Friday from 7 a.m. to 6:30 p.m.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
July 14, 2023
The week of July 17, crews will be onsite Monday through Friday, from 7 a.m. to 6:30 p.m.
Milling operations will continue next week at the north end of the project area, past Baptiste Road.
At the project's south end area, crews will be working on drainage improvements at the stormwater pond located northeast of the Round Butte Road/Terrance Lake Road and US Highway 93 (US 93) intersection, near the Ronan Indian Senior Center.
Crews continue installing underground electrical conduit for the new streetlights and traffic signal at the Old US 93 and 3rd Avenue intersection.
Sidewalk and curb construction on Road Butte Road has been suspended until early fall.
Spring Creek Road Update:
Spring Creek Road at US 93 is now permanently closed.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
July 11, 2023
Spring Creek Road at US Highway 93 (US 93) is now permanently closed. Riverside Contracting Inc. crews have begun breaking up the roadway, and US 93 can no longer be accessed from Spring Creek Road.
To enter the Spring Creek Road area, drivers should use Old US 93 or Mudd Creek Lane.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
July 7, 2023
Next week, paving operations on the northbound lanes of US Highway 93 (US 93) will continue. Concrete crews will also be onsite, installing curb and sidewalk in the area around Dairy Queen and the southbound couplet - the short, 600-foot two-lane segment connecting 1st Avenue to US 93, just north of the Round Butte Road and US 93 intersection.
Installation of underground electrical conduit for the new streetlights and traffic signal at the Old US 93 and 3rd Avenue intersection is scheduled to begin.
North of the Old US 93 and 3rd Avenue intersection, crews are continuing to work on building the new road’s subbase will continue, and milling operations are underway south of Baptiste Road. Drivers should anticipate traveling on a gravel surface through this section of the project area.
Crews will be onsite tomorrow, Saturday, July 8, and next week Monday through Friday, from 5 a.m. to 6:30 p.m.
Spring Creek Road Update
Work continues on the new approach to Lake Seed. Paving is anticipated to occur next week, and once complete, Spring Creek Road at US 93 will be permanently closed. The closure is expected to take place late next week.
Round Butte Road Mill & Fill - Ronan
The Round Butte Road resurfacing project is complete. The project began at the intersection of Round Butte Road with Ag Services Lane and extended west for four miles, ending just past Guenzler Lane. Improvements completed include resurfacing the roadway, seal and cover (chip seal), fog seal, new pavement markings, and installing rumble strips. For more information on the Round Butte Road Mill & Fill project, visit the project webpage.
Glover Road and US 93 Safety Improvements
MDT and its partner Riverside Contracting are wrapping up a safety project near Pablo on Glover Road, just west of US 93 that also includes pavement preservation, extending from just north of Ronan to north of Pablo, ending at the intersection of US 93 with Minesinger Trail. For more information on the Glover Road and US 93 Safety Improvements project, visit the project webpage.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
June 30, 2023
We hope you have a safe and happy Fourth of July!
Work will pause for the Fourth of July starting Saturday, July 1, through Tuesday, July 4, to accommodate increased holiday traffic and to give workers time to spend with their families. Crews will return on Wednesday, July 5.
Over the holiday, traffic will be traveling on a paved surface and no delays are anticipated.
When crews return on July 5, paving operations will continue on the northbound lanes, the approaches to 3rd Avenue and Old US 93, and the southbound couplet - the short, 600-foot two-lane segment connecting 1st Avenue to US Highway 93 (US 93), just north of the Round Butte Road and US 93 intersection.
Milling will also continue on the northbound and southbound lanes at the north end of the project. Traffic will be traveling on a gravel surface in the work zone.
Crews will be onsite Wednesday through Saturday, from 5 a.m. to 6:30 p.m.
Spring Creek Road Update
Work continues on the new approach to Lake Seed. Once the approach is complete, Spring Creek Road at US 93 will be permanently closed. The closure is expected to take place the second week of July.
Round Butte Road Mill & Fill - Ronan
Work continues on the Round Butte Road resurfacing project. Crews returned this morning, Friday, June 30, to paint temporary road stripes and will remove traffic control once complete.
After the holiday, crews will be on-site Wednesday, July 5, and Thursday, July 6 to chip seal, sweep, fog seal, and paint the permanent road markings. Traffic control will be in place.
If conditions allow, the project will be completed on Thursday, July 6 and crews will not have to return later this summer as originally planned.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, have almost completed work on a safety project near Pablo on Glover Road, just west of US 93 that also included pavement preservation, extending from just north of Ronan to the north of Pablo, ending at the intersection of US 93 with Minesinger Trail.
This project is currently paused. Crews will return in mid-July to place the final roadway epoxy.
For more information on the Glover Road and US 93 Safety Improvements project, visit the project webpage.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
June 23, 2023
Paving operations are underway on the US Highway 93 (US 93) Ronan-North project! Crews are working on the centerline from the Sinclair gas station north to the Old US 93 and 3rd Avenue intersection.
Gravel installation continues north of the Old US 93 with 3rd Avenue intersection.
Concrete work and construction of curbs, gutters, and sidewalks will continue at the Round Butte Road intersection.
The week of June 26, crews will be onsite Monday through Thursday, from 5 a.m. to 6:30 p.m., and Friday until midday.
Work will pause for the Fourth of July starting Saturday, July 1, through Tuesday, July 4, to accommodate increased holiday traffic and to give workers time to spend with their families. Crews will return on Wednesday, July 5.
It is anticipated that there will be fewer traffic delays when traveling through the construction zone. However, flaggers will still be present at the truck turnarounds at the intersections of Round Butte Road with Terrace Lake Road and Old US 93 with 3rd Avenue.
Spring Creek Road Update: Work continues on the new approach to Lake Seed. Once the approach is complete, Spring Creek Road at US 93 will be permanently closed. The closure is expected to take place at the end of June.
Round Butte Road Mill & Fill-Ronan
Work continues on the Round Butte Road resurfacing project. The westbound lane is now paved, and milling operations are underway on the eastbound lane. The project is anticipated to be completed early next week.
For the latest project update, visit https://www.mdt.mt.gov/pubinvolve/gloverroad/updates.aspx.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
June 16, 2023
Progress continues on the US Highway 93 (US 93) Ronan-North project. Riverside Contacting crews will be onsite tomorrow, Saturday, June 17, from 6 a.m. to 6:30 p.m., installing gravel on the roadway between the Old US 93 and 3rd Avenue intersection near Dairy Queen, just north of the Round Butte Road intersection.
Next week, at the project's north end, crews will continue constructing the roadway base of the new lanes of US 93 and begin installing pipe in the median. Concrete work will also continue at the Round Butte Road intersection.
Crews will be onsite Monday to Friday, from 6 a.m. to 6:30 p.m.
It is anticipated that there will be fewer traffic delays when traveling through the construction zone, however, flaggers will still be present at the truck turnarounds at the Round Butte Road/Terrace Lake Road and Old US 93/3rd Avenue intersections.
Spring Creek Road Update: Work continues on the new approach to Lake Seed. Once the approach is complete, Spring Creek Road at US 93 will be permanently closed. The closure is anticipated to take place the week of June 26.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, has begun work on a safety project near Pablo on Glover Road, just west of US 93. In addition, pavement preservation work is also underway and extends from just north of Ronan to the north of Pablo, ending at the intersection of US 93 with Minesinger Trail.
For the latest project update, visit https://www.mdt.mt.gov/pubinvolve/gloverroad/updates.aspx.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
June 9, 2023
Riverside crews will be constructing the sub-base of the new southbound lanes of US Highway 93 (US 93) next week.
Crews will be onsite Monday to Saturday, from 6 a.m. to 6:30 p.m.
Night work is planned for next week, Tuesday through Thursday, from 9 p.m. to 7 a.m. as conditions allow. Overnight, concrete crews will be working at the intersection of Round Butte Road and US 93, and traffic flaggers will be present.
It is anticipated that there will be fewer traffic delays when traveling through the construction zone going forward; however, flaggers will still be present at the truck turnarounds at the Round Butte Road/Terrace Lake Road and Old US 93/3rd Avenue intersections.
Spring Creek Road Update: Work on the approach to Lake Seed will resume next week. Once the approach is complete, Spring Creek Road at US 93 will be permanently closed. The closure is anticipated to take place the week of June 19.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, have begun work on a safety project near Pablo on Glover Road, just west of US 93. Pavement preservation work is also underway and extends from just north of Ronan to the north of Pablo, ending at the intersection of US 93 with Minesinger Trail.
For the latest project update, visit https://www.mdt.mt.gov/pubinvolve/gloverroad/updates.aspx.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
June 2, 2023
Crews will be working on widening the new southbound couplet, the short segment of roadway connecting 1st Avenue to US Highway 93 (US 93), from Round Butte Road to behind the Dairy Queen next week.
Construction of the sub-base of the new northbound lanes of US 93 is also underway.
Work on the new alignment of 3rd Avenue at the intersection with US 93 is wrapping up, and traffic will begin traveling on the new alignment early next week.
It is anticipated that there will be fewer traffic delays when traveling through the construction zone going forward; however, flaggers will still be present at the truck turnarounds at the Round Butte Road/Terrace Lake Road and Old US 93/3rd Avenue intersections.
Next week, crews will be working Monday to Saturday, from 6 a.m. to 6:30 p.m.
Spring Creek Road Update: The planned permanent closure of Spring Creek Road at US 93 has been delayed due to wet weather. We will notify you when the new closure date has been determined.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, have begun work on a safety project near Pablo on Glover Road, just west of US 93. In addition, pavement preservation work is also underway and extends from just north of Ronan to the north of Pablo, ending at the intersection of US 93 with Minesinger Trail.
For the latest project update, visit https://www.mdt.mt.gov/pubinvolve/gloverroad/updates.aspx.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
May 26, 2023
Thank you to our Veterans, those currently serving our country and their families. We are forever in your debt. We wish everyone a safe and enjoyable Memorial Day!
Crews are not working today, Friday, May 26. They will return on Tuesday, May 30, and be onsite Tuesday to Saturday, from 7 a.m. to 6:30 p.m.
Over the holiday weekend, a water truck will be present for dust control.
When crews return, milling operations will continue at the southern end of the project by Dairy Queen, just north of the US Highway 93 (US 93) and Round Butte Road/Terrace Lake Road intersection.
Two lanes of traffic will be maintained; however, watch for road alignment changes. Drivers should anticipate traveling on a gravel surface and delays of approximately 15 minutes. Left turns will be prohibited in certain areas.
Other work planned on the project site includes installing a pipe at the intersection of Old US 93/3rd Avenue and US 93 and the continued construction of the new approach for US 93 to Lake Seed in preparation for the closure of Spring Creek Road at US 93.
Spring Creek Road Update: The planned permanent closure of Spring Creek Road at US 93 has been delayed due to wet weather. We will notify you when the new closure date has been determined.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, have begun work on a safety project near Pablo on Glover Road, just west of US 93. In addition, pavement preservation work is also underway and extends from just north of Ronan to the north of Pablo, ending at the intersection of US 93 with Minesinger Trail.
Traffic control will be present throughout the work zone. Drivers can anticipate 10- to 15-minute delays when traveling through the project area.
For the latest project update, visit https://www.mdt.mt.gov/pubinvolve/gloverroad/updates.aspx.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
May 19, 2023
Thank you for your patience regarding Wednesday’s unplanned lane closure. We know that construction can be frustrating, and we're doing all we can to work quickly and efficiently to complete the project as soon as possible.
Next week, milling operations will continue south on US Highway 93 (US 93) past the intersection of Old US 93/3rd Avenue. Crews will also continue storm drain installation on the west side of US 93 in front of the car dealerships.
Drivers should expect to travel on gravel surfaces via one-lane traffic, and experience delays of approximately 15 minutes. Left turns will be prohibited in certain areas.
Crews will be on-site on Saturday, May 20, from 7 a.m. to 6:30 p.m.
Spring Creek Road Update: The planned permanent closure of Spring Creek Road at US Highway 93 (US 93) has been delayed due to wet weather. We will notify you when the new closure date has been determined.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, have begun work on a safety project near Pablo on Glover Road, just west of US 93. In addition, pavement preservation work is also underway and extends from just north of Ronan to the north of Pablo, ending at the intersection of US 93 with Minesinger Trail. For more information, visit https://mdt.mt.gov/pubinvolve/gloverroad/.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
May 12, 2023
We wish everyone celebrating Mother’s Day a wonderful day!
Spring Creek Road Update: The planned permanent closure of Spring Creek Road at US Highway 93 (US 93) has been delayed due to the wet weather we have been experiencing. We will notify you when the new closure date has been determined.
Over the next week, Riverside Contracting will continue milling operations on the northbound lane of US 93. Storm drain installation on the west side of US 93 also continues.
Drivers should anticipate extended sections of gravel surfaces and one-lane traffic, resulting in travel delays of up to 15 minutes. Left turns will be prohibited in certain areas.
Crews will work on-site Monday to Saturday, from 7 a.m. to 6:30 p.m. until the holiday weekend (Memorial Day), weather permitting.
Glover Road and US 93 Safety Improvements
North of the Ronan-North project, MDT, in partnership with Riverside Contracting, will begin work on Glover Road and US 93 Monday, May 15. This safety project is near Pablo on Glover Road, just west of US 93. In addition, pavement preservation work will be completed and extends from just north of Ronan to north of Pablo, ending at the intersection of US 93 with Minesinger Trail.
This week, pavement preservation work from just north of Ronan to north of Pablo will kick off with crack sealing. In addition, signpost installation and bridge deck sealing (concrete, water repellent sealant) will begin on US 93. Traffic control will be present. Drivers can anticipate 10 – 15-minute delays when traveling through the work zone. In addition, electrical work in preparation for the yellow flashing light will take place on Glover Road, weather permitting. For more information, visit https://mdt.mt.gov/pubinvolve/gloverroad/.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
May 5, 2023
Riverside Contracting is making good progress on the Ronan-North US Highway 93 (US 93) project.
We thank you for your continued patience and support during this period of increased construction activity. The goal is to complete all work requiring single-lane traffic before the Memorial Day holiday weekend and the busy summer season. Over the holiday weekend and for the remaining duration of construction, at least two lanes of traffic, one southbound and one northbound, will be maintained.
Milling operations will continue this week on the northbound lane of US 93 between Dairy Queen and Old US Hwy 93.
Installation of a storm drain on the west side of US 93 and other pipework also continues.
Drivers should anticipate extended sections of gravel surfaces and one-lane traffic, resulting in travel delays of up to 15 minutes. Left turns will be prohibited in certain areas.
Crews will work on-site Monday to Saturday, from 7 a.m. to 6:30 p.m. until the holiday weekend (Memorial Day), weather permitting.
Please note: The planned permanent closure of Spring Creek Road at US 93 is scheduled for Thursday, May 11. To access the Spring Creek Road area, east of US 93, drivers should use Old US 93 or Mud Creek Lane as an alternate route.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
May 3, 2023
As mentioned in the previous project update, below, Riverside Contracting will be installing a manhole at the intersection of Round Butte Road and 1st Avenue Southwest this week
Starting tomorrow, Thursday, May 4 through Friday, May 5, drivers should expect 20 minute delays when traveling on Round Butte Road through this intersection.
Drivers are strongly encouraged to avoid the Round Butte Road and 1st Avenue Southwest intersection and choose an alternate route.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
April 28, 2023
Riverside Contracting will ramp up construction activity on the Ronan-North US Highway 93 (US 93) project over the next four weeks.
The goal is to complete all work requiring single-lane traffic before the Memorial Day holiday weekend and the busy summer season. Over the holiday weekend and for the remaining duration of construction, at least two lanes of traffic, one southbound and one northbound, will be maintained.
To progress the project quickly and achieve this goal, crews will work on-site Monday to Saturday, from 7 a.m. to 6:30 p.m. until the holiday weekend, weather permitting.
Drivers should anticipate traveling on a gravel surface for a longer period and one-lane traffic resulting in travel delays of up to 15 minutes. Left turns will be prohibited in certain areas.
We understand that construction and the resulting delays are frustrating. We thank you for your patience and support and are doing everything we can to complete this project as quickly as possible.
Next week, Riverside Contracting will begin milling operations south of the Old US 93/3rd Avenue and US 93 intersection. Improvements underway at this intersection will also be ongoing.
Work to install a storm drain on the west side of US 93 and slope work at the project's north end at Baptiste Road also continue.
At the intersection of Round Butte Road and 1st Avenue Southwest, crews will begin the installation of a manhole.
Please note: The planned permanent closure of Spring Creek Road at US 93 is scheduled for Thursday, May 11. To access the Spring Creek Road area, east of US 93, drivers should use Old US 93 or Mudd Creek Road as an alternate route.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
April 25, 2023 - Update
Due to inclement weather, minor adjustments have been made to the schedule on the US Highway 93 (US 93) Ronan-North project for the remainder of the week. Drivers should now expect traffic flaggers to intermittently control traffic at the US 93 and Round Butte Road intersection. Also, Riverside Contracting crews will be on-site this Saturday, April 29, from 7 a.m. to 6:30 p.m.
Please do not hesitate to reach out with any questions or concerns. Email Sloane directly at
April 21, 2023
It looks like beautiful weather is on the way next week! The Montana Department of Transportation and Riverside Contracting will take advantage of the improving conditions by continuing work on the Ronan-North US Highway 93 (US 93) project.
Next week, crews will begin installing a storm drain on the west side of US 93 and slope work will be underway at the north end of the project at Baptiste Road.
Riverside Contracting will also continue milling operations and intersection improvements at Old US 93/3rd Avenue and US 93.
Watch for road alignment and marking changes from Round Butte Road to just past the Pierce car dealership. Drivers should anticipate traveling on a gravel surface and up to 15-minute delays due to lane closures. Left turns will be prohibited in certain areas.
Riverside Contracting crews will be on-site Monday to Friday, from 7 a.m. to 6:30 p.m., weather permitting.
Please note: The planned permanent closure of Spring Creek Road at US 93 is scheduled for Thursday, May 11. To access the Spring Creek Road area, east of US 93, drivers should use Old US 93 or Mudd Creek Road as an alternate route.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
April 14, 2023
Riverside Contracting will continue milling operations next week. A crane will also be onsite, setting the inlet and outlet structures on the 54-inch siphon pipe crews have been installing. Work to install an additional pipe across US Highway 93 (US 93) at the Pierce car dealership will also get underway.
Watch for road alignment and marking changes. Drivers should anticipate traveling on a gravel surface and up to 15-minute delays due to lane closures. Left turns will be prohibited in certain areas.
Other scheduled work for the coming week includes starting improvements to the US 93 and 3rd Avenue intersection and laying geotextile on the north side of the southbound couplet, the short two-lane segment connecting 1st Avenue to US 93. This is a permeable fabric used to increase soil stability and prevent erosion.
Riverside Contracting crews will be on-site Monday to Friday, from 7 a.m. to 6:30 p.m., weather permitting.
Please note: The planned permanent closure of Spring Creek Road at US 93 is scheduled for Thursday, May 11.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
April 7, 2023
Work continues throughout the Ronan-North project site. Embankment operations continue at Baptiste Road and the north side of the southbound couplet, the short two-lane segment connecting 1st Avenue to US 93, just north of the Round Butte Road and US 93 intersection.
Riverside Contracting will also continue milling the northbound lane roadway and shoulder and excavating the ditch beside the northbound lane on the east side of the highway. Due to the installation of a 54-inch siphon pipe, crews will be excavating across the roadway.
Drivers should anticipate traveling on a gravel surface and up to 15-minute delays due to lane closures. Watch for road alignment and marking changes. Left turns will be prohibited in certain areas.
Next week, Riverside Contracting crews will be on-site Monday to Friday, from 7 a.m. to 6:30 p.m., weather permitting.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
March 31, 2023
Next week will be a busy one on the Ronan-North US Highway 93 (US 93) project. Riverside Contracting will begin installing a 54-inch siphon pipe, requiring excavation through the roadway. Crews will also start milling the roadway and shoulder of the northbound lane, the east side of the highway, starting at the south end of the project. Due to this work, drivers should anticipate shifting traffic lanes and transitioning to and from gravel surfaces.
Also, embankment operations will be underway on the west side of US 93 at Baptiste Road and the northbound side of the couplet, the short, 600-foot two-lane segment connecting 1st Avenue to US 93, just north of the Round Butte Road and US 93 intersection. Excavation operations will be occurring on the southbound side of the couplet.
Riverside Contracting crews will be working tomorrow, Saturday, April 1. Next week crews will only be on site from 7 a.m. to 6:30 p.m., weather permitting.
Drivers should plan for short delays when traveling through the project area. Traffic control, including traffic lights and flaggers, and reduced speeds will be in place.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
March 24, 2023
It appears winter is not quite done with us, as a mixture of rain and snow is forecasted for the coming week. Riverside Contracting crews will not be working today or Saturday this week on the Ronan-North project. Next week crews will only be on site from 7 a.m. to 6:30 p.m., weather permitting.
Crews will be installing storm drains on the west side of US Highway 93 (US 93), and embankment and excavation operations will continue on the east side. Work has also begun on the new southbound couplet: a short, 600-foot two-lane segment connecting 1st Avenue to US 93, just north of the Round Butte Road and US 93 intersection. Other work planned includes construction around approaches off US 93 and utility work.
Drivers should expect increased truck traffic as materials are being hauled throughout the project area.
Traffic will continue to travel on the current highway during this first phase of construction.
Drivers should plan for short delays when traveling through the project area. Traffic control, including traffic lights and flaggers, and reduced speeds will be in place.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
March 20, 2023 – Update Amendment
Due to ground conditions, Riverside Contracting has decided not to work night shifts this week, March 20 – 25. We will update you on next week's work schedule in the regularly scheduled Friday update.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
March 17, 2023
This week, Riverside Contracting will continue excavating operations on the east side of the roadway and fill operations on the west side of US Highway 93 (US 93).
A new approach to Lake Seed from US 93 is also being constructed in preparation for the closure of Spring Creek Road at US 93 later this year. North of the US 93 and Round Butte Road/Terrace Lake Road intersection, across from Dairy Queen, crews are also constructing a new storm drain.
Due to these activities, drivers should expect increased truck traffic as materials are being hauled throughout the project area.
Traffic will continue to travel on the current highway during this first phase of construction.
Drivers should plan for short delays when traveling through the project area. Traffic control, including traffic lights and flaggers, will be in place, and speeds reduced.
Riverside Contracting crews will continue to work double shifts, weather permitting. Work will occur from 7 a.m. to 5:30 p.m. and 6 p.m. to 4:30 a.m. Going forward, crews will also work on Saturdays, as conditions allow, to progress the project quickly.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
March 10, 2023
Roadwork will begin next week on the Ronan-North US Highway 93 (US 93) project! Construction will be completed in three phases, starting with widening the west half of the road to include two new southbound lanes.
This first phase will be underway with Riverside Contracting excavating the south side of the roadway at the project’s north end.
Traffic will continue to travel on the current highway during the first phase of construction.
In phase two, the northbound lanes will be constructed on the east side of the highway. During this phase, drivers will be traveling on a gravel surface. In preparation for this phase, excavating operations will also begin this week on the east side next to the highway.
Crews will also be installing culverts throughout the project area. Construction of a new approach off US 93 for Lake Seed will begin in preparation for the closure of Spring Creek Road at US 93 later this year.
Drivers should plan for short delays when traveling through the project area. Traffic control will be in place, including traffic flaggers and reduced speeds.
Riverside Contracting crews plan to work double shifts to progress the project quickly. Weather permitting, work will occur from 7 a.m. to 5:30 p.m. and 6 p.m. to 4:30 a.m.
The final phase will involve paving, road marking installation, and finishing work. The project is expected to be completed this year; however, this schedule is subject to change due to weather and other unforeseen factors.
When traveling through the construction zone, remember the three Ss of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
February 27, 2023
Riverside Contracting will be working on the US Highway 93 (US 93) Ronan-North project this week, as weather permits. Operations will be limited and focused on preparations for full construction this spring.
Crews will be working on the side of the highway around Baptiste Road and north of the US 93 and Round Butte Road/Terrace Lake Road intersection, across from Dairy Queen.
All work will occur off the roadway, so there will be little to no traffic disruptions. When traveling through the project site, drivers should be mindful of their speed and watch for workers and equipment.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
December 9, 2022
Work on the US Highway 93 (US 93) Ronan-North project has been suspended due to weather. Riverside Contracting has been conducting earthwork operations at Baptiste Road and plans to resume this work when weather permits. We will send another update before work on the project begins again.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
December 2, 2022
Weather permitting, Riverside Contracting will return next week, December 5-9, to the US Highway 93 (US 93) Ronan-North project and continue earthwork operations at Baptiste Road. Traffic flaggers will be on site, and drivers should expect short delays.
When traveling through the construction zone, remember the three Ss of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 25, 2022
Construction activity on the US Highway 93 (US 93) Ronan-North project continues. Starting next week, November 28 – December 4, Riverside Contracting will begin earthwork operations at Baptiste Road, which should take 5 to 10 days to complete, weather permitting. Traffic flaggers will be on-site, and drivers should expect short delays.
When traveling through the construction zone, remember the three Ss of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 18, 2022
Work is underway on the US Highway 93 (US 93) Ronan-North project. Today, Friday, November 18, Riverside Contracting will be removing and hauling away trees near the US 93 and Baptiste Road/Spring Creek Road intersection, resulting in temporary single-lane closures. Traffic flaggers will be on-site directing traffic.
Crews will continue to clear surface and underground vegetative materials alongside the road as weather permits. This includes grass, trees, roots, and topsoil, in preparation for construction in early 2023. Earthwork operations on Baptiste Road may also begin as weather conditions allow.
There will be no construction activity on Thursday, November 24, so workers can spend time with friends and family for the Thanksgiving holiday.
Remember the three Ss of work zone safety when traveling through the construction zone: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 11, 2022
Riverside Contracting anticipates starting work on the US Highway 93 (US 93) Ronan-North project on November 15, weather permitting. Crews will be clearing surface and underground vegetative materials alongside the road. This will include grass, trees, roots, and topsoil, in preparation for construction in early 2023. Earthwork operations on Baptiste Road may also begin as weather conditions allow.
Most of the work will occur adjacent to the roadway. Traffic control will be on-site, speed limits reduced, and shoulder closures in place within the construction zone. Brief, single-lane road closures may be periodically required.
When traveling through the construction zone, remember the three Ss of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
Thank you again to those who attended the pre-construction open houses. A recording of the virtual open house is now available on our Public Involvement page.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
November 4, 2022
Weather permitting, Riverside Contracting will begin work on the US Highway 93 (US 93) Ronan-North project. Crews will be clearing surface and underground vegetative materials along the roadside, including grass, trees, roots, and topsoil, in preparation for construction in early 2023. Additional work planned for this fall includes the installation of a 54-inch irrigation pipe and beginning earthmoving operations at the project’s north end.
Most of the work will occur adjacent to the roadway. Traffic control will be on-site, speed limits reduced, and shoulder closures in place within the construction zone. Brief, single-lane road closures may be periodically required.
When traveling through the construction zone, remember the three S’s of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.
Thank you again to those who attended the pre-construction open houses. A recording of the virtual open house is now available on our Public Involvement page.
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at
October 31, 2022
Thank you to those who stopped by the Ronan-North open house this past Wednesday or attended the virtual open house on Thursday. We hope you found the experience as informative and helpful as we did. Your feedback and questions are essential to the project’s success. If you were not able to attend, watch the virtual open house here.
The Montana Department of Transportation (MDT) and Riverside Contracting are excited to announce that construction will begin next week. Construction activity planned for this fall is dependent on the weather. In preparation for construction in 2023, Riverside Contracting will start clearing surface and underground vegetative materials along the roadside, including grass, trees, roots, and topsoil.
Weather permitting, crews will also install a 54-inch irrigation pipe and may begin earthmoving operations at the project’s north end.
Most of the work will occur adjacent to the roadway; however, traffic control will be on-site, speed limits reduced, and shoulder closures in place within the construction zone. Brief, single-lane road closures may be periodically required.
When driving through the active construction site, slow down, watch for workers and equipment, and follow all signs. Your safety is our priority!
If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at