Project Overview
Updated
The Montana Department of Transportation (MDT) has partnered with Riverside Contracting, Inc., to complete Americans with Disabilities Act (ADA) upgrades in Billings. This project is taking place along King Avenue West, from 24th Street West to the Interstate 90 (I-90) City Center westbound on-ramp.
Improvements include upgrading 19 ADA corner ramps, reconstructing one approach at the Lithia Dealership, upgrading the electrical pedestrian crossing signals, and updating pavement markings to enhance safety and accessibility for all users.
Construction Update
Construction is progressing and is expected to continue into spring, depending on weather and other unforeseen factors.
Completed work:
- Concrete work is complete, including the reconstructed approach and upgraded corner ramps
- Upgraded electrical pedestrian crossing signals
- Updated striping and pavement markings
Upcoming work:
- Remaining electrical work is expected to be completed within the next couple of months, depending on weather and other unforeseen factors.
Project Map
Billings District ADA Upgrades
The Billings ADA phase is one section of the Billings District ADA Upgrades project, which also includes improvements in the Lewistown and Bridger communities. As a part of MDT’s statewide effort to improve pedestrian facilities across Montana, this project will bring sidewalks in each of these communities into compliance with current ADA standards, allowing greater accessibility for all.
UPN 10431000