Open House

The project team held an in-person open house at Elder Grove Middle School on Monday, November 2, 2026.

Open House Display Boards: King Avenue & 64th Street – Billings

Project overview graphic for the King Avenue West and South 64th Street West intersection improvement project in Billings, Montana. The Montana Department of Transportation (MDT), in partnership with engineering consultant Sanbell, is designing a roundabout at the intersection. The graphic explains that traffic and crashes have increased as new businesses and homes have developed in southwest Billings. The project aims to achieve four goals: enhance safety at the intersection, improve traffic flow, reduce vehicle conflict points, and better accommodate current and future traffic needs. Icons illustrate each goal: a traffic signal, multiple vehicles, a roadway intersection, and a construction worker with traffic control equipment. MDT and Sanbell logos appear at the bottom.
MDT and Sanbell are designing a roundabout at King Avenue West and South 64th Street West in Billings. The project aims to enhance intersection safety, improve traffic flow, reduce vehicle conflict points, and accommodate current and future traffic needs.
Project map showing the plan area for the King Avenue West and South 64th Street West intersection improvements in Billings, Montana. The plan area is highlighted in orange along King Avenue West on both sides of South 64th Street West and along South 64th Street West immediately north and south of the intersection. Nearby streets include Central Avenue, Western Way, Black Hawk Street, Ollie Street, April Drive, Jewel Lane and Victoria Lane. Laurel is west of the project area, and Billings is east. Hesper is south of the project area. A compass indicates north is at the top of the map.
Project location map for the King Avenue West and South 64th Street West intersection improvements in Billings. The proposed roundabout plan area is highlighted in orange.
Project layout aerial image showing the proposed roundabout at the intersection of King Avenue West and South 64th Street West. The roundabout is centered at the intersection, with construction limits extending along both roads. The image identifies existing and proposed drainage and irrigation features, including an existing private pond northwest of the intersection, a detention pond northeast of the intersection, a retention pond southwest of the intersection, a drainage chute, roadway drainage culvert, irrigation culvert, irrigation ditch flowline, and irrigation piping network. Additional labeled features include the edge of new asphalt and a private approach southeast of the intersection. A compass indicates north is at the top.
Proposed project layout for the King Avenue West and South 64th Street West roundabout in Billings. The aerial image identifies the construction limits, proposed roundabout, roadway improvements, drainage features, irrigation infrastructure, and nearby properties.
Informational graphic titled
Why a roundabout? Roundabouts reduce vehicle speeds and delays and can significantly decrease crashes. According to MDT, roundabouts are associated with reductions of 90% in fatal crashes, 75% in injury crashes, and 37% in overall crashes. Learn more at MDT's roundabout information webpage.
Anticipated project timeline for King Avenue and 64th Street in Billings, showing design milestones from fall 2026 through winter 2027, right-of-way and utility negotiations in 2028, and estimated construction start in 2029. The schedule is subject to design completion, funding availability, and unforeseen factors.
King Avenue and 64th Street Project – Anticipated Timeline: Design is expected to reach 30–50% completion in fall 2026, with final plans expected in winter 2027. Right-of-way and utility negotiations are anticipated in 2028. Construction is estimated to begin in 2029, depending on design completion, funding availability, and any unforeseen factors that may affect the schedule.
Project funding overview stating that the final budget is to be determined during the design phase, with an initial estimated total budget of $4.5–$5.5 million. Funding sources include City of Billings local funds, the federal Highway Safety Improvement Program (HSIP), and the federal Surface Transportation Program – Secondary (STPS), which includes a state match.
Project Funding: The initial estimated project budget ranges from $4.5 million to $5.5 million. Funding is provided through City of Billings local funds, the federal Highway Safety Improvement Program (HSIP), and the Surface Transportation Program – Secondary (STPS). The final project budget will be determined during the design phase.