US 191 – Mobridge Slide Repairs logo

Construction Update

Construction on the shear key embankment is underway and is expected to continue for a couple more weeks, depending on weather and other unforeseen factors. Expect traffic control, including lane closures and traffic signals during shear key construction.

Beware of trucks entering and exiting the roadway.

July 30, 2025

Construction on the shear key embankment along U.S. Highway 191 near the James Kipp Recreation Area and Fred Robinson Bridge over the Missouri River is underway. The Montana Department of Transportation (MDT) and M.A. DeAtley Construction, Inc., will continue shear key work for a couple more weeks, depending on weather and other unforeseen factors.

Traffic control, including lane closures and traffic signals, can be expected during this construction.

Please watch for workers and equipment when traveling through the project area.

Shear key construction is underway
Shear key construction is underway.

July 14, 2025

Crews began construction on the shear key embankment near U.S. Highway 191 last week. This work is expected to continue for a couple of weeks.

Traffic control, including lane closures and traffic signals, can be expected during this construction.

Please watch for workers and equipment when traveling through the project area.

Location of shear key construction.
Location of shear key construction.

Project Camera

July 2, 2025

Crews are continuing to install temporary ditches and haul gravel this week. Construction on the shear key embankment is expected to begin after the holiday, depending on weather conditions and other unforeseen factors. Traffic control including lane closures and flaggers can be expected during active construction. Please watch for workers and equipment when traveling through the project area.

4th of July Work Schedule
Construction will pause starting Thursday, July 3 at noon in observance of the July 4th holiday; work will resume on Tuesday, July 8.

Crews hauling at the stockpile area.
Crews hauling at the stockpile area.

June 25, 2025

Initial site work and preparation efforts are progressing. Crews are continuing to haul gravel as well as install temporary ditches.

Construction on the embankment is anticipated to begin after the preparation work is complete, tentatively in early July, depending on weather conditions and other unforeseen factors.

Please watch for workers and equipment when traveling through the project area.

4th of July Work Schedule
Construction will pause starting Thursday, July 3 at noon in observance of the July 4th holiday; work will resume on Tuesday, July 8.

Preparation work underway at the gravel pit
Preparation work underway at the gravel pit.

May 22, 2025

Initial site work and preparation efforts are progressing.

Fergus Electric crews have completed drilling (boring) under the southwest side of the roadway to install underground utilities.

Minimal traffic disruption is anticipated at this time. Please watch for workers and equipment when traveling through the project area. All work is dependent on weather conditions and other unforeseen factors.

Cleared area of the future shear key.
Cleared area of the future shear key.

May 2, 2025

The Montana Department of Transportation (MDT) and its partner M.A. DeAtley Construction, Inc., are continuing work on the US 191 – Mobridge Slide Repairs project. Currently, site preparation efforts are progressing and include:

  • Clearing vegetation
  • Hauling and sorting rock fill
  • Mobilizing equipment and creating stockpiles
  • Installing tools and instrumentation to monitor the landslide movement during construction

Initial site work will continue for the next couple of weeks.

Burning as well as clearing the trees and brush in the project area is complete.

This week, Fergus Electric crews began drilling (boring) under the southwest side of the roadway to install underground utilities.

All work is dependent on weather conditions and other unforeseen factors. Minimal traffic disruption is anticipated at this time. Please watch for workers and equipment when traveling through the project area.

The team has installed instrumentation to monitor the landslide movement during construction
The team has installed instrumentation to monitor the landslide movement during construction.
Materials being prepped for the project at an offsite pit.
Materials being prepped for the project at an offsite pit.

February 5, 2025

The Montana Department of Transportation (MDT) and its partner M.A. DeAtley Construction, Inc., has begun initial site preparation, including dirt work and staging. This work is expected to continue until April.

Minimal traffic disruption is anticipated until April and much of the work will be off-site and not seen from the road.

While traveling through the project site, please be mindful of the speed limit as well as the large trucks and other equipment in the area.

Following site preparation in April, full construction activities are anticipated to begin and continue through the 2025 construction season.

If you have questions or comments, please do no hesitate to contact the project communications team at us191XYZdowlABCcom or calling the project hotline at 406-970-7591.