December 16-20, 2024
The Montana Department of Transportation (MDT), in partnership with the city of Kalispell, Schellinger Construction, and DJ&A Engineering, will continue work on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. During the week of December 16, utility work will continue along the project corridor. Work is dependent on weather and other unforeseen factors.
Utility crews will be present on the north side of West Reserve Drive, directly across from West Reserve Plaza at 770 West Reserve Drive. Two-way traffic will continue with traffic candles and barrels present to direct drivers to temporary lane shifts.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time. Follow all posted signage and please watch for workers and equipment alongside the road.
Additionally, a public notice has been issued for waterway passage on the Stillwater River where it intersects near West Reserve Drive. Sletten Construction is preparing to begin work soon on a temporary bridge over the Stillwater River.
While crews are working in and near the water, all river users are encouraged to be aware of the river navigation restriction. The restricted opening will be a minimum of 20 feet wide with a 6-foot high clearance and will remain in place through May. Sletten Construction is dedicated to expediting this project and apologizes for any inconvenience it may cause.
We appreciate the Kalispell communities’ partnership in adhering to all signage and flaggers while we work to create a safer roadway. Please remember that fines are doubled when workers are present.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes, including a center turn lane and a shared-use path. The intersections of West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road will feature dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
This project aims to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during the construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
November 25-29, 2024
The Montana Department of Transportation (MDT), in partnership with the city of Kalispell, Schellinger Construction, and DJ&A Engineering, will continue work on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. Over the next two weeks, utility work will continue along the west end of the project. Work is dependent on weather and other unforeseen factors.
Crews will be present Monday through Friday from 6 a.m. to 8 p.m. Work will pause on Thursday, November 28 for the Thanksgiving holiday. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours and temporary lane shifts. Approaches within the work zone follow a right-in and right-out traffic pattern.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes, including a center turn lane and a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
This project aims to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during active construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
November 18-22, 2024
The Montana Department of Transportation (MDT), in partnership with the city of Kalispell, Schellinger Construction, and DJ&A Engineering, will continue work on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. During the week of November 18, utility work will begin along the west end of the project. Work is dependent on weather and other unforeseen factors.
Crews will be present Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours with temporary lane shifts. Approaches within the work zone follow a right-in and right-out traffic pattern. Stay alert for trucks entering and exiting the project site, which will be controlled by a flagger.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes, including a center turn lane and a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during active construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
November 11-15, 2024
During the week of November 11, the Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction, and DJ&A Engineering, will continue roadwork on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. Work will consist of striping along the west end of the project, winter cleanup, and possible utility work at the Stillwater River bridge.
Crews will be present Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours with temporary lane shifts. Approaches within the work zone follow a right-in and right-out traffic pattern. Stay alert for trucks entering and exiting the project site.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes, including a center turn lane and a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during active construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
November 4-8, 2024
During the week of November 4, the Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction, and DJ&A Engineering, will continue roadwork on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. Along the west end of the project, work will consist of paving approaches and tie-ins to existing lines. Crews will also be cleaning up for the upcoming winter months.
Crews will be present Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours with temporary lane shifts. Approaches within the work zone follow a right-in and right-out traffic pattern. Stay alert for trucks entering and exiting the project site.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes, including a center turn lane and a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during active construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
October 14, 2024
The Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction and DJ&A Engineering, will continue roadwork on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project during the week of October 14. Along the west end of the project, concrete road work, curb, gutter, and sidewalk upgrades will continue for the next three to four weeks, weather and other factors permitting. The next update will be to share the next phase of the project or to announce any unforeseen changes to this schedule.
Crews will be present Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours with temporary lane shifts. Approaches within the work zone follow a right-in and right-out traffic pattern. Be alert for trucks entering and exiting the project site.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes, including a center turn lane and adding a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during active construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
October 7-11, 2024
During the week of October 7, the Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction and DJ&A Engineering, will continue construction on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. Roadwork will involve curb and sidewalk upgrades along with concrete work on the west end of the project; weather and unforeseen factors permitting.
Crews will be present Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours with temporary lane shifts. Approaches within the work zone follow a right-in and right-out traffic pattern. Be alert for trucks entering and exiting the project site.
Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes including a center turn lane and adding a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive. MDT appreciates your continued patience and understanding during active construction.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].
September 30, 2024
The Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction and DJ&A Engineering, continue construction activities on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project the week of September 30. Work is dependent on weather and other unforeseen factors.
Crews will work Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue with traffic candles and barrels present to direct drivers to adjacent detours with temporary lane shifts. Approaches follow a right-in and right-out traffic pattern. Be alert for trucks entering and exiting the project site. Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes including a center turn lane and adding a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. More information.
September 23, 2024
The Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction and DJ&A Engineering, continue construction with milling and excavating on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project the week of September 23. Work is dependent on weather and other unforeseen factors.
Crews will work Monday through Friday from 6 a.m. to 8 p.m. Two-way traffic will continue, but traffic candles and barrels will be present to direct drivers to adjacent detours with temporary lane shifts. Drivers should expect reduced speeds of 35 mph. Please allow for additional travel time due to daytime construction. Follow all posted signage and please watch for workers and equipment on the side of the road.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes including a center turn lane and adding a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. More information.
September 16, 2024
added 9/23/2024
The Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction and DJ&A Engineering, will start construction on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project the week of September 16. Work is dependent on weather and other unforeseen factors.
Crews will work weekdays from 6 a.m. to 8 p.m. Two-way traffic will continue, but adjacent detours with temporary lane shifts will be present. Motorists can expect reduced speeds of 35 mph. Follow all posted signage and please watch for workers and equipment.
This project includes widening West Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes including a center turn lane and adding a shared-use path. The West Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing. Crews will also replace the Stillwater River Bridge deck to include sidewalks.
The purpose of this project is to enhance roadway safety for all users, increase accessibility, and improve traffic flow on West Reserve Drive.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. More information.
September 12, 2024
The Montana Department of Transportation (MDT) in partnership with the city of Kalispell, Schellinger Construction and DJ&A Engineering, anticipate survey work later this week on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. Drivers may notice crews on the side of the roadway gathering data. Please be mindful of workers in the area. Construction is scheduled to begin this fall, depending on weather and other unforeseen factors.
The purpose of this project is to enhance roadway safety for all users, increase nonmotorized accessibility, and improve traffic operations on Reserve Drive.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. More information.
July 16, 2024
The Montana Department of Transportation (MDT) in partnership with the City of Kalispell, has selected Schellinger Construction and DJ&A Engineering to complete the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road design-build project. A design-build project allows collaborative problem-solving and innovation from the construction company and design engineers, who work jointly throughout the duration of the project to provide a cohesive plan to fit the project timeline and budget. This method has been used for its unique project scope of work, time requirements, deadlines, and in an effort to minimize disruption to traffic. Construction is scheduled to begin later this year, depending on weather and other unforeseen factors.
In 2023, this project was awarded $25 million from the U.S. Department of Transportation Multimodal Project Discretionary Grant (MPDG) to address transportation and traffic challenges. The MPDG Rural grant funds were matched with Montana’s Surface Transportation Program – Primary (STPP) funds in the amount of $13.4 million. Additionally, this project will receive $1.44 million from the SAFER Montana Roads and Bridges Fund.
This project will include widening Reserve Drive between Hutton Ranch Road and Whitefish Stage Road from three to five lanes with a center turn lane, and adding a shared-use path. Crews will also replace the Stillwater River Bridge deck to include sidewalks. The Reserve Drive with Hutton Ranch Road and Whitefish Stage Road intersections will receive dedicated turn lanes, new traffic signals, and concrete surfacing.
The purpose of this project is to enhance roadway safety for all users, increase nonmotorized accessibility, and improve traffic operations on Reserve Drive. More information will be provided as construction approaches.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. More information.
April 2, 2024
Schellinger Construction, teamed with DJ&A, has been selected to complete the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. We are working on an Open House for later this spring. If you would like to attend, or to learn more, please contact Dawn at
October 6, 2023
The City of Kalispell, in partnership with MDT, are taking steps forward on the Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. A request for proposal (RFP) has recently been issued for design-build teams to begin submitting proposals for the recommended improvement option selected through the West Reserve Drive Corridor Planning Study. Project design is anticipated to begin in the spring of 2024, and construction is scheduled to begin later that year or in 2025, weather and other factors permitting.
In 2023, this project was awarded a U.S. Department of Transportation Multimodal Project Discretionary Grant (MPDG) to address transportation and traffic challenges. Project improvements will include widening Reserve Drive from Hutton Ranch Road to Whitefish Stage Road from three to five lanes, adding a center turn lane, replacing the Stillwater River Bridge deck to include sidewalks, and adding a shared-use path. Intersection improvements to Hutton Ranch Road and Whitefish Stage Road will also include dedicated turn lanes, signals, and concrete surfacing.
The selected design-build team will prepare detailed plans for construction based on the study's selected design. Surrounding businesses and stakeholders will be notified if right-of-way is impacted.
More information will be provided as construction approaches.
Questions? To receive email updates on the project, please contact Dawn at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/.
May 19, 2023
Happy Spring! The City of Kalispell, in partnership with the Montana Department of Transportation (MDT), is moving forward with the highly anticipated Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project.
This year, MDT and the City of Kalispell will select a project team and begin designing the recommended improvement option selected through the West Reserve Drive Corridor Planning Study. Soon, MDT will be receiving Statements of Qualifications from design-build teams to then release the official Request for Proposals in July. A design-build team is anticipated to be selected later this year. Construction will occur in late 2024 or 2025.
Project improvements will ultimately include widening Reserve Drive from Hutton Ranch Road to Whitefish Stage Road from three to five lanes, including a center turn lane, replacing the Stillwater River bridge deck to include sidewalks, and adding a shared use path and a pedestrian sidewalk. In addition, intersection improvements to Hutton Ranch Road and Whitefish Stage Road will include dedicated turn lanes, signals, and concrete surfacing.
Please note, this is the first phase of construction made possible by the US Department of Transportation Multimode Project Discretionary Grant (MPDG) to address transportation and traffic challenges. As funding is acquired, future phases of the project will take place east of Whitefish Stage Road and at the intersections with US 2 and US 93.
Questions? To receive email updates on the project, please contact Becca at
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/.
April 7, 2023
The City of Kalispell, in partnership with the Montana Department of Transportation (MDT), kick off the highly anticipated Reserve Drive: Hutton Ranch Road to Whitefish Stage Road project. In 2023, MDT and the City of Kalispell will select a project team and begin design of the recommended improvement option selected through the West Reserve Drive Corridor Planning Study. Construction will occur in late 2024 or 2025.
The 2020-2021 US Census named Kalispell the fastest growing micropolitan area in the country. Traffic volumes have increased dramatically, causing significant delays on Reserve Drive and Whitefish Stage Road. In 2022, this project was awarded the US Department of Transportation Multimodal Project Discretionary Grant (MPDG) to address transportation and traffic challenges.
Project improvements will include widening Reserve Drive from Hutton Ranch Road to Whitefish Stage Road from three to five lanes, including a center turn lane, replacing the Stillwater River bridge deck to include sidewalks, and adding a shared-use path and a pedestrian sidewalk. In addition, intersection improvements to Hutton Ranch Road and Whitefish Stage Road will include dedicated turn lanes, signals and concrete surfacing.
Updates will be sent out via mail, news releases, and public meetings held to ensure the Flathead community is kept informed on this project and other Reserve Drive and Whitefish Stage Road projects that are taking place within the next few years.
Interested in signing up to receive text updates? To sign up for text updates, text RESERVEDRWHITEF to 41411. Message and data rates may apply. Message frequency may vary. Text STOP to cancel. Texting alerts are not managed by MDT and may have different privacy and security policies. For more information, see https://smstc.us/t41411/ [smstc.us].