The Sixmile Creek Wildlife Crossing Study is anticipated to take approximately 16 months to complete. The schedule shown provides details on the project activities and durations. A draft report is anticipated by June 2026 and a final report by August 2026.
The project schedule will be updated as the project progresses.
Preliminary Schedule for Sixmile Creek Wildlife Crossing Study
*Dates and milestones subject to change
| Milestone | Date |
|---|---|
| Public Involvement, Stakeholder Outreach, Resource Agency Coordination | May 2025 to August 2026 |
| Cultural Resource Investigation and Report | May 2025 to September 2025 |
| Environmental Existing Conditions/Baseline Reports | May 2025 to November 2025 |
| Geotech Investigations and Report | May 2025 to November 2025 |
| Hydraulic and Hydrologic Analysis | May 2025 to December 2025 |
| Alternatives Analysis | September 2025 to March 2026 |
| Public Meeting | October 2025 |
| Preliminary Bridge Layout | July 2025 to December 2025 |
| Stream Design | December 2025 to February 2026 |
| Cost Estimate | February 2026 to April 2026 |
| Alternatives Matrix and Selection | April 2026 |
| Develop Draft Feasibility Study | April 2026 to June 2026 |
| Draft Report | June 2026 |
| Address Comments/Revise Report | July 2026 |
| Share Final Report | August 2026 |