The Sixmile Creek Wildlife Crossing Study is anticipated to take approximately 16 months to complete. The schedule shown provides details on the project activities and durations. A draft report is anticipated by June 2026 and a final report by August 2026.

The project schedule will be updated as the project progresses.

Sixmile Creek Wildlife Crossing Study schedule

Preliminary Schedule for Sixmile Creek Wildlife Crossing Study

*Dates and milestones subject to change

Milestone Date
Public Involvement, Stakeholder Outreach, Resource Agency Coordination May 2025 to August 2026
Environmental Existing Conditions/Baseline Reports May 2025 to October 2025
Cultural Resource Investigation and Report May 2025 to November 2025
Geotech Investigations and Report May 2025 to December 2025
Location Hydraulic Study Report (LHSR) Analysis May 2025 to June 2025
Hydraulic and Hydrologic Analysis, Stormwater Analysis May 2025 to January 2026
Alternatives Analysis June 2025 to December 2025
Preliminary Bridge Layout July 2025 to March 2026
Stream Design February 2026 to April 2026
Alternatives Selection April 2026
Develop and Draft Feasibility Report April 2026 to July 2026
Share Final Feasibility Report August 2026