The Sixmile Creek Wildlife Crossing Study is anticipated to take approximately 16 months to complete. The schedule shown provides details on the project activities and durations. A draft report is anticipated by June 2026 and a final report by August 2026.
The project schedule will be updated as the project progresses.
Preliminary Schedule for Sixmile Creek Wildlife Crossing Study
*Dates and milestones subject to change
Milestone | Date |
---|---|
Public Involvement, Stakeholder Outreach, Resource Agency Coordination | May 2025 to August 2026 |
Environmental Existing Conditions/Baseline Reports | May 2025 to October 2025 |
Cultural Resource Investigation and Report | May 2025 to November 2025 |
Geotech Investigations and Report | May 2025 to December 2025 |
Location Hydraulic Study Report (LHSR) Analysis | May 2025 to June 2025 |
Hydraulic and Hydrologic Analysis, Stormwater Analysis | May 2025 to January 2026 |
Alternatives Analysis | June 2025 to December 2025 |
Preliminary Bridge Layout | July 2025 to March 2026 |
Stream Design | February 2026 to April 2026 |
Alternatives Selection | April 2026 |
Develop and Draft Feasibility Report | April 2026 to July 2026 |
Share Final Feasibility Report | August 2026 |