The Sixmile Creek Wildlife Crossing Study is anticipated to take approximately 16 months to complete. The schedule shown provides details on the project activities and durations. A draft report is anticipated by June 2026 and a final report by August 2026.

The project schedule will be updated as the project progresses.

Sixmile Creek Wildlife Crossing Study schedule

Preliminary Schedule for Sixmile Creek Wildlife Crossing Study

*Dates and milestones subject to change

Milestone Date
Public Involvement, Stakeholder Outreach, Resource Agency Coordination May 2025 to August 2026
Cultural Resource Investigation and Report May 2025 to September 2025
Environmental Existing Conditions/Baseline Reports May 2025 to November 2025
Geotech Investigations and Report May 2025 to November 2025
Hydraulic and Hydrologic Analysis May 2025 to December 2025
Alternatives Analysis September 2025 to March 2026
Public Meeting October 2025
Preliminary Bridge Layout July 2025 to December 2025
Stream Design December 2025 to February 2026
Cost Estimate February 2026 to April 2026
Alternatives Matrix and Selection April 2026
Develop Draft Feasibility Study April 2026 to June 2026
Draft Report June 2026
Address Comments/Revise Report July 2026
Share Final Report August 2026