Anaconda & Deer Lodge Signal Upgrades logo

September 18, 2025

The Montana Department of Transportation (MDT) and Montana Lines Inc. plan to begin signal pole installation in Anaconda next week, Sept. 22. Following completion of the pole installation, crews will be restriping the crosswalks at the Main Street intersections with Commercial Avenue and Park Avenue. Work will continue throughout the week on this project.

In Deer Lodge, crews tentatively plan to begin sidewalk demolition, which had previously been delayed. When this work begins, pedestrian traffic will be disrupted at the intersection of Main Street and Milwaukee Avenue. Work crack sealing Main Street in Deer Lodge has been completed.

All work is dependent on weather and other unforeseen factors.

During construction motorists should expect:

  • Intersection sidewalks will be closed, and pedestrians will be detoured.
  • Flaggers and/or temporary signals will direct traffic at times.
  • Temporary lane closures.
  • Speed limits will be reduced.
  • Delays of up to 15 minutes.
  • On-street parking will be briefly disrupted during paving work.
  • Wide loads may be restricted at times (visit 511mt.net for the most up-to-date information on restrictions).
  • Work will take place during daylight hours.

September 12, 2025

The Montana Department of Transportation (MDT) and Montana Lines Inc. will continue replacing curb and gutter and sidewalk in Anaconda next week. Crews will continue to work on underground utilities and pouring concrete at the Main Street intersections with Commercial Avenue and Park Avenue.

In Deer Lodge, crews hope to begin sidewalk demolition which has been delayed slightly.

All work is dependent on weather and other unforeseen factors.

During construction motorists should expect:

  • Intersection sidewalks will be closed, and pedestrians will be detoured.
  • Flaggers and/or temporary signals will direct traffic at times.
  • Temporary lane closures.
  • Speed limits will be reduced.
  • Delays of up to 15 minutes.
  • On-street parking will be briefly disrupted during paving work.
  • Wide loads may be restricted at times (visit 511mt.net for the most up-to-date information on restrictions).
  • Work will take place during daylight hours.

September 4, 2025

The Montana Department of Transportation (MDT) and Montana Lines Inc. will be working on curb and gutter in Anaconda the week of September 8. Following completion of that work, crews will begin pouring concrete for the new sidewalk. This will disrupt pedestrian traffic while concrete is curing.

In Deer Lodge, crews began work crack sealing Main Street the week of September 1. The following week, crews anticipate beginning sidewalk demolition followed by work on underground utilities and traffic signal foundations.

All work is dependent on weather and other unforeseen factors.

During construction motorists should expect:

  • Intersection sidewalks will be closed, and pedestrians will be detoured.
  • Flaggers and/or temporary signals will direct traffic at times.
  • Temporary lane closures.
  • Speed limits will be reduced.
  • Delays of up to 15 minutes.
  • On-street parking will be briefly disrupted during paving work.
  • Wide loads may be restricted at times (visit 511mt.net for the most up-to-date information on restrictions).
  • Work will take place during daylight hours.

August 29, 2025

The Montana Department of Transportation (MDT) and Montana Lines Inc. will begin sidewalk demolition and crack sealing Main Street in Deer Lodge the week of Sept. 1. During this time, pedestrian traffic may be disrupted at the intersection of Main Street and Milwaukee Avenue.

In Anaconda, crews will continue work on the sidewalks at the Main Street intersections with Commercial Avenue and Park Avenue.

All work is dependent on weather and other unforeseen factors.

In observance of Labor Day, crews will pause construction activities after 3 p.m. on Friday, August 29, and resume on Tuesday, September 2.

During construction motorists should expect:

  • Intersection sidewalks will be closed, and pedestrians will be detoured.
  • Flaggers and/or temporary signals will direct traffic at times.
  • Temporary lane closures.
  • Speed limits will be reduced.
  • Delays of up to 15 minutes.
  • On-street parking will be briefly disrupted during paving work.
  • Wide loads may be restricted at times (visit 511mt.net for the most up-to-date information on restrictions).
  • Work will take place during daylight hours.

August 22, 2025

The Montana Department of Transportation (MDT) and Montana Lines Inc. will continue sidewalk demolition and utility work in Anaconda the week of August 25. This work will take place at the intersections of Main Street with Park Avenue and Commercial Avenue.

Additionally, sidewalk demolition work is anticipated to begin in Deer Lodge the week of September 1. This work will take place at the intersection of Main Street and Milwaukee Avenue in Deer Lodge.

All work is dependent on weather and other unforeseen factors.

In observance of Labor Day, crews will pause construction activities after 3 p.m. on Friday, August 29, and resume on Tuesday, September 2.

During construction motorists should expect:

  • Intersection sidewalks will be closed, and pedestrians will be detoured.
  • Flaggers and/or temporary signals will direct traffic at times.
  • Temporary lane closures.
  • Speed limits will be reduced.
  • Delays of up to 15 minutes.
  • On-street parking will be briefly disrupted during paving work.
  • Wide loads may be restricted at times (visit 511mt.net for the most up-to-date information on restrictions).
  • Work will take place during daylight hours.