October 31, 2024
The Montana Department of Transportation (MDT), along with construction partner Acme Concrete Paving, Inc., have completed construction activities in the eastbound lanes of Interstate 90 (I-90). The project location begins 3 miles east of the Montana/Idaho border and continues east for approximately 3 miles, ending near the Taft Interchange. The project runs from mile marker 3.4 to mile marker 5.7.
This summer, crews replaced deteriorating asphalt pavement with new, durable concrete pavement, as well as upgraded surface drainage, replaced culverts, replaced concrete barriers, improved roadway lighting, and updated signage. Crews will return in 2025 to complete the same work in the westbound lanes.
The public is encouraged to contact Joan Redeen at 406-396-1978 with any questions or comments.
July 29, 2024
The Montana Department of Transportation (MDT) and Acme Concrete Paving, Inc., are scheduled to begin pouring concrete as part of the Taft West project the week of August 5, weather and other factors permitting.
Traffic control remains in place. Travelers in both directions can expect to travel in the westbound lanes of I-90, with no passing through the project area. Expect reduced speeds. Eastbound Interstate 90 (I-90) travelers wanting to access Taft, please take the Saltese Interchange, Exit 10, and detour back on I-90 west to Taft.
For more information, or to sign up for updates, please contact Joan Redeen at 406-396-1978.
July 2, 2024
The Montana Department of Transportation (MDT) and Acme Concrete Paving, Inc., will begin laying storm drainpipes as part of the Taft West project the week of July 8, weather and other factors permitting.
**No oversized load piloting July 4-7. Loads over 12 feet wide MUST use an alternate route. Normal piloting operations will resume Monday, July 8.**
Eastbound Interstate 90 (I-90) travelers wanting to access Taft, please take the Saltese Interchange, Exit 10, and detour back on I-90 west to Taft.
Traffic control will be in place. Travelers in both directions can expect to travel in the westbound lanes of I-90, with no passing through the project area. Expect reduced speeds.
For more information, or to sign up for updates, please contact Joan Redeen at 406-396-1978.
May 10, 2024
The Montana Department of Transportation (MDT) and Acme Concrete Paving, Inc., will begin milling the eastbound lanes of Interstate 90 (I-90) on Saturday, May 11, weather and other factors permitting. Work is expected to last approximately 10 days.
Crews are also beginning work on the Taft Interchange eastbound ramp. Eastbound I-90 travelers wanting to access Taft, please take the Saltese Interchange, Exit 10, and detour back on I-90 west to Taft.
Traffic control will be in place. Travelers in both directions can expect to travel in the westbound lanes of I-90, with no passing through the project area. Expect reduced speeds.
For more information, or to sign up for updates, please contact Joan Redeen at 406-396-1978.
April 25, 2024
The Montana Department of Transportation (MDT), along with construction partner Acme Concrete Paving, Inc., will begin pavement reconstruction activities on Interstate 90 (I-90). The project begins 3 miles east of the Montana/Idaho border and continues east for approximately 3 miles, ending near the Taft Interchange. The project runs from mile marker 3.4 to mile marker 5.7.
The project is anticipated to begin the week of May 6 and will take 2 construction seasons to complete. Crews will be working from 7 a.m. to 8 p.m. The purpose of this construction project is to extend the service life of the roadway.
Expect 10 to 15-minute delays, reduced speeds of 35mph, lane shifts with crossovers to shift all traffic to the westbound side, and single-lane traffic when traveling through the project area. Traffic may be routed onto the interstate shoulder when work is occurring. Wide loads must be staged and are allowed to travel through the project area between 7 a.m. to 9 a.m. Mountain Standard Time Monday through Friday. Wide loads may contact Poteet at 406-360-8187 to schedule passage. For the most up-to-date width restrictions and road conditions visit 511mt.net.
The public is encouraged to contact Joan Redeen at 406-396-1978 with any questions or comments.