June 30, 2025
Travel Advisories:
- On Monday, July 7, crews plan to start paving the eastbound Interstate 90 (I-90) ramps. The ramps will remain open to traffic but there may be delays as traffic is moved onto the shoulder.
- On Sunday, July 13, crews plan to start milling and paving the eastbound I-90 ramps and a section of Zoo Drive between the overpass and South Frontage Road at night. This work will take approximately one week to complete and will require temporary closures of the eastbound ramps from 7 PM to 5 AM.
Active and upcoming work:
- Median storm drain modifications are in progress along Zoo Drive to prepare for road widening later this summer.
- Underground electrical work is in progress along Zoo Drive, Pierce Parkway, and Gabel Road to prepare for intersection and traffic signal modifications.
June 19, 2025
Active and upcoming work:
- Median storm drain modifications are in progress along Zoo Drive to prepare for road widening later this summer.
- Underground electrical work is in progress near the I-90 eastbound on and off ramps. This work will continue along Zoo Drive, Pierce Parkway, and Gabel Road in the coming weeks to prepare for intersection and traffic signal modifications.
Travel Advisories:
- Single-lane traffic is active in areas where work is being completed. Please use caution, expect minor delays, and watch for workers near the roadway as you travel through the project area.
- The sidewalk along the north side of Zoo Drive is expected to be closed for the duration of the project.
June 12, 2025
Active and upcoming work:
- Underground electrical work is in progress near the I-90 eastbound on and off ramps. This work will continue along Zoo Drive, Pierce Parkway, and Gabel Road in the coming weeks to prepare for intersection and traffic signal modifications.
- Median modifications are in progress on Zoo Drive and at the Shiloh Road roundabout. Work at the Shiloh Road roundabout is expected to be completed by the end of the week.
Travel Advisories:
- Single-lane traffic is active in areas where work is being completed. Please use caution, expect minor delays, and watch for workers near the roadway as you travel through the project area.
- The sidewalk along the north side of Zoo Drive is expected to be closed for the duration of the project.


June 6, 2025
Construction is expected to begin on Monday, June 9 beginning with the following activities:
- Underground electrical work where the I-90 eastbound on and off ramps intersect Zoo Drive.
- Roadway widening of the I-90 eastbound on and off ramps.
- Median modifications along Zoo Drive.
Travel Advisories:
- Beginning next week, the sidewalk along the north side of Zoo Drive, will be closed for the duration of the project.
- The I-90 eastbound ramps are expected to remain open to traffic while improvements are completed. Traffic may be shifted onto the shoulder to make room for construction activities while maintaining traffic flow.
- Please expect reduced speeds and watch for workers near the roadway.