Vision Zero Logo

November 10, 2023

Thank you

The Montana Department of Transportation (MDT) and Coral Construction have completed installing median high-tension cable rail along more than 40 miles of Interstate 90 (I 90), from Three Forks east to the Bear Canyon exit, east of Bozeman.

Thank you for your patience and support during this important safety improvement project for the Bozeman area!

Median high-tension cable rail has been proven to reduce the severity of crashes and prevent fatal crashes caused by vehicles crossing the median into oncoming traffic.

This project is the first phase of a four-phase project that will install 150 miles of median high-tension cable rail along sections of I 90 in the Missoula, Butte, and Bozeman areas, and Interstate 15 (I 15) in the Butte and Helena areas.

Construction of the Butte phase began on October 9. Work has paused for the season and will resume in the spring. The Butte phase is anticipated to be completed in 2024. This schedule is subject to change due to unforeseen circumstances, such as weather and project material availability.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

November 3, 2023

Coral Construction crews will complete clean-up activities next week on Interstate 90 (I 90) between Three Forks and the Bear Canyon Exit, weather and other factors permitting.

Work is scheduled for Monday, November 6, through Friday, November 10, from 6 a.m. to 6 p.m.

Single-lane, median, or shoulder closures may be required where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 27, 2023

Coral Construction crews will continue clean-up activities next week on Interstate 90 (I 90) between Three Forks and the Bear Canyon Exit. Work will occur Wednesday, November 1, through Friday, November 3, from 6 a.m. to 6 p.m., weather permitting.

Median and shoulder closures may be required where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 20, 2023

The Montana Department of Transportation (MDT) and Coral Construction have completed installing high-tension cable rail in the median of Interstate 90 (I 90) in the Bozeman area!

Crews will continue seeding and clean-up activities in the project area, between Three Forks and the Bear Canyon Exit. Work will occur today, Friday, October 20, through Wednesday, October 25, from 6 a.m. to 6 p.m., weather permitting. Brief single-lane closures may be required where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic and reduced speeds while this work is occurring.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 13, 2023

Coral Construction crews will be installing high-tension cable rail in the median of Interstate 90 (I 90) between Bozeman and the Bear Canyon Exit on Tuesday, October 17, from midnight to noon.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Once finished, high-tension median cable rail installation on I 90 in the Bozeman area will be complete!

Next week, crews will also begin seeding and cleaning up the project area between Three Forks and the Bear Canyon Exit. Work will occur Tuesday, October 17, through Saturday, October 21, from 6 a.m. to 6 p.m. Brief single-lane closures may be required where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 6, 2023

Coral Construction continues work on the Interstate 90 (I 90) High-Tension Median Cable Rail project. Crews will install and tension cable between Belgrade and Bozeman tonight, Friday, October 6, and into the early morning hours tomorrow, Saturday, October 7, from 9 p.m. to 7 a.m.

Next week, cable installation will occur at the east end of the project area.

Bozeman Area: Crews will be onsite Monday, October 9, from 9 p.m. to 7 a.m. on Tuesday, October 10.

Bozeman to the Bear Canyon Exit: Crews will be onsite Monday, October 9, through Friday, October 13, from midnight to noon.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

September 29, 2023

Coral Construction crews will begin installing and tensioning cable between Belgrade and Bozeman during the night and early morning hours next week.

Work will occur Tuesday, October 3, through Saturday, October 7, from 9 p.m. to 7 a.m.

The left lanes closest to the median on both sides of Interstate 90 (I 90) will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

road work Coral Construction crews install cable between Manhattan and Belgrade. (Coral Construction Photo/Kris Karpstein)

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

September 22, 2023

Coral Construction crews will be installing and tensioning cable at the west end of the Interstate 90 (I 90) High-Tension Median Cable Rail project between Manhattan and Belgrade tomorrow, Saturday, September 23, and next week, Monday, September 25, through Thursday, September 28, from 5 a.m. to 3 p.m.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway. To accommodate traffic, crews will finish work by noon on the westbound lanes and by 3 p.m. on the eastbound lanes.

A crew will also be installing guardrail in select locations throughout the project area during the night and early morning hours. Work will occur Monday, September 25, through Wednesday, September 27, from midnight to 10 a.m.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

September 15, 2023

Progress continues on the Interstate 90 (I 90) High-Tension Median Cable Rail project. Coral Construction crews continue installing and tensioning cable at the west end of the project area.

Three Forks to Manhattan: Crews will be onsite Tuesday, September 19, through Wednesday, September 20, from 5 a.m. to 3 p.m.

Manhattan to Belgrade: Crews will be onsite Wednesday, September 20, through Saturday, September 23, from 5 a.m. to 3 p.m.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway. To accommodate traffic, crews are scheduled to finish work by noon on the westbound lanes and by 3 p.m. on the eastbound lanes.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

September 8, 2023

Coral Construction crews will continue installing and tensioning cable at the west end of the project area, between Three Forks and Manhattan next week. Work will occur Monday, September 11 through, Thursday, September 14, between 6 a.m. and 6 p.m.

The left lanes closest to the median on both sides of Interstate 90 (I 90) will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

September 1, 2023

We hope you have a safe and happy Labor Day!

Work on the Interstate 90 (I 90) Median Cable Rail project has paused for the holiday weekend and will resume on Wednesday, September 6.

Wednesday, September 6, through Saturday, September 9, Coral Construction crews will continue installing and tensioning cable at the west end of the project area, between Three Forks and Manhattan. Work will take place between 6 a.m. and 6 p.m.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

August 25, 2023

Starting tomorrow, Coral Construction will begin the next phase of the Bozeman area Interstate 90 (I 90) Median High-Tension Cable Rail project. Crews will be working at the west end of the project area, between Three Forks and Manhattan, installing and tensioning cable.

This work will occur Saturday, August 26, and next week, August 28 through August 30, between 6 a.m. and 6 p.m.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

Labor Day Holiday work schedule: Work will pause starting Thursday, August 31, and resume Wednesday, September 6, to accommodate increased holiday traffic and give workers time to spend with their families.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

August 18, 2023

Work continues on the Interstate 90 (I 90) Median High-Tension Cable Rail project. Next week, Coral Construction crews will be installing guardrail in select areas throughout the project site. Work will occur during the night and early morning hours to accommodate summer traffic.

The anticipated schedule for next week:

Belgrade to Bozeman: Tuesday, August 22, from midnight to noon.

Bozeman to the Bear Canyon Exit: Wednesday, August 23, from midnight to 10 a.m.

Three Forks to Manhattan: Friday, August 25, from midnight to noon.

Manhattan to Belgrade: Saturday, August 26, from midnight to noon.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

August 11, 2023

Work continues on the Interstate 90 (I 90) Median High-Tension Cable Rail project tomorrow, Saturday, August 12. A clean-up crew will be onsite between Belgrade and Bozeman from midnight to 10 a.m. A crew will also be grading slopes and cleaning up between Bozeman and the Bear Canyon Exit from midnight to noon.

Next week, crews will work during the night and early morning hours to accommodate summer traffic. Crews will be on-site from 9 p.m. to 7 a.m. to continue line post layout and installation, as well as general clean-up activities.

Work will be occurring in the Bozeman area on Monday, August 14, through Wednesday, August 16, and between Belgrade and Bozeman on Wednesday, August 16, through Friday, August 18.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

August 4, 2023

Coral Construction crews working on the Interstate 90 (I 90) Median High-Tension Cable Rail project begin a short break starting today, Friday, August 4, through Monday, August 7. Line post layout, installation, and clean-up activities will resume at midnight on Tuesday, August 8.

Next week, work will continue between Bozeman and the Bear Canyon Exit during the night and early morning hours to accommodate summer traffic. Crews will be onsite Tuesday, August 8, through Friday, August 11, from midnight to noon.

On Saturday, August 12, a clean-up crew will be working between Belgrade and the Bear Canyon Exit from midnight to noon.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

July 28, 2023

The Interstate 90 (I 90) Median High-Tension Cable Rail project is on schedule, and crews are working hard during the night and early morning hours to accommodate the summer traffic.

Line post layout, installation, and cleanup activities continue between Bozeman and Bear Valley. Crews will be onsite tomorrow, Saturday, July 29, and Monday, July 31, through Thursday, August 3, from midnight to 10 a.m.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway. On Saturday, July 29, the shoulder will also be closed in the areas where work is occurring.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

Starting Friday, August 4, through Monday, August 7, the crew will take a short break and return to work at midnight on Tuesday, August 8.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

July 21, 2023

Progress continues on the Interstate 90 (I 90) Median High-Tension Cable Rail project. The following is planned for the week of July 24 and includes work during night and early morning hours.

The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Belgrade to Bozeman: Crews will be onsite Monday through Wednesday, from midnight to 10 a.m. Work continues on line post layout, installation, and cleanup in the median of I 90.

Bozeman to Bear Valley: Crews will be onsite Monday through Saturday, from midnight to noon. Work will continue on anchor and line post installation from Monday through Saturday. On Saturday, July 29, the shoulder will be closed in the areas where work is underway, in addition to the left lanes both sides of I 90.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

July 14, 2023

Crews will be on-site tomorrow, Saturday, July 15, between Belgrade and Bozeman from 2 a.m. to 10 a.m. The left lanes closest to the median on both sides of Interstate 90 (I 90) and the shoulder will be closed where work occurs.

Next week, crews will work Monday, July 17, through Wednesday, July 19 with nighttime and early morning activities. The left lanes closest to the median on both sides of I 90 will be closed where work is underway.

Belgrade to Bozeman: Monday through Wednesday, from approximately midnight to 10 a.m., line post layout, installation, and cleanup will continue in the median of I 90.

Bozeman to Bear Valley: Tuesday and Wednesday, from approximately 2 a.m. to noon, anchor installation will be underway.

Work will pause for the remainder of the week, from Thursday, July 20 through Sunday, July 23, to make way for Big Sky Country State Fair traffic.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

July 7, 2023

The Montana Department of Transportation (MDT) and its partner Coral Construction will resume work on Monday, July 10. Line post layout and installation will continue in the median of Interstate 90 (I 90) between Belgrade and Bozeman starting July 10, through Friday, July 14. Lane closures will occur from 4 a.m. to 10 a.m.

The left lanes closest to the median on both sides of I 90 will be closed where work is occurring.

On Saturday, July 15, crews will be onsite from 4 a.m. to noon. The shoulder will be closed in the areas where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

June 30, 2023

We hope you have a safe and happy Fourth of July!

Work on the Interstate 90 (I 90) Median High-Tension Cable Rail project will pause Saturday, July 1, through Sunday, July 9, to accommodate increased holiday traffic and give workers time to spend with their families. Crews will return on Monday, July 10.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

June 23, 2023

Early next week, Coral Construction will complete line post layout and installation on Interstate 90 (I 90) between Manhattan and Belgrade. Crews will be working in this area tomorrow, Saturday June 24, from 5 a.m. to noon, and the week of June 26, Monday through Thursday, 5 a.m. to 3 p.m. with lane closures.

Line post layout and installation will begin between Belgrade and Bozeman on Tuesday, June 27. Lane closures will occur 4 a.m. to 10 a.m.

Crews will be working in the median. This will require the left lanes closest to the median on both sides of Interstate 90 (I 90) to be closed where work is occurring. Crews will also be performing cleanup activities throughout the project area during the day.

There will be a brief period between 5 a.m. and 10 a.m. on Monday, June 26, and Friday, June 30, when crews will be working in two areas requiring separate construction zones with reduced speed limits. Crews will be separated by at least five miles, and each work site will require lane closures.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate minor travel delays.

Fourth of July work schedule: Work will pause starting Saturday, July 1, through Sunday, July 9, to accommodate increased holiday traffic and give workers time to spend with their families. Crews will return on Monday, July 10.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

June 16, 2023

Coral Construction crews will continue line post layout and installation on Interstate 90 (I 90) between Manhattan and Belgrade Monday through Friday, 5 a.m. to 6 p.m., and Saturdays, from 5 a.m. to noon.

One crew will be working in the median, requiring the westbound and eastbound left lanes closest to the median to be closed in the area.

Please slow down and watch for workers and equipment. Drivers should anticipate minor travel delays due to lane closures and reduced speeds.

Fourth of July holiday work schedule: Work will pause starting Saturday, July 1, through Sunday, July 9, to accommodate increased holiday traffic and give workers time to spend with their families.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

June 9, 2023

Line post layout and installation will continue on Interstate 90 (I 90) between the Manhattan and Belgrade areas next week.

One crew will be working in the median, requiring the westbound and eastbound left lanes closest to the median to be closed in the area.

Please slow down and watch for workers and equipment. Drivers should anticipate minor travel delays due to lane closures and reduced speeds.

Crews will NOT be on-site tomorrow, Saturday, June 10. Next week, crews will be on-site Monday to Friday, from 6 a.m. to 6 p.m., and Saturday, from 6 a.m. to noon.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

June 2, 2023

Next week, only one crew will be installing high-tension median cable rail along Interstate 90 (I 90), requiring only one set of lane closures throughout the project area.

Line post layout and installation will continue between the Manhattan and Belgrade areas. The westbound and eastbound left lanes closest to the median will be closed.

Crews will be on-site Monday to Friday, from 6 a.m. to 6 p.m., and Saturday, from 6 a.m. to noon. Work will also occur tomorrow, Saturday, June 3, from 6 a.m. to noon.

Drivers should anticipate minor travel delays due to lane closures and reduced speeds. Please slow down and watch for workers and equipment. Montana Highway Patrol (MHP) will be onsite monitoring traffic.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

May 26, 2023

Thank you to our Veterans, those currently serving our country and their families. We are forever in your debt. We wish everyone a safe and enjoyable Memorial Day.

Crews are not working today, Friday, May 26. They will return to continue installing high-tension median cable rail along Interstate 90 (I 90) in the Bozeman area on Wednesday, May 31.

Line post layout and installation will continue between Three Forks and Manhattan, and a second crew will be installing anchor posts in the I 90 median at Bear Canyon working west.

Each work site will require lane closures. The westbound and eastbound left lanes closest to the median will be closed in both construction areas.

Next week, crews will be on-site Wednesday to Friday from 5 a.m. to 6 p.m., and on Saturday, June 3. During this time, line post installation will be underway between Manhattan and Belgrade, requiring only one project location with westbound and eastbound lane closures.

Drivers should anticipate minor travel delays due to lane closures and reduced speeds. Please slow down and watch for workers and equipment. Montana Highway Patrol (MHP) will be onsite monitoring traffic.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

May 19, 2023

Work to install high-tension median cable rail along Interstate 90 (I 90) in the Bozeman area continues next week.

There will continue to be two separate construction zones with reduced speed limits. Crews will be separated by at least five miles, and each work site will require lane closures. The westbound and eastbound left lanes will be closed closest to the median in both construction areas.

One crew will continue to lay out and install line posts between Three Forks and Manhattan.

The second crew will work further east, installing anchor posts between Belgrade and Bozeman.

On Saturday, May 20, only the crew installing line posts between Three Forks and Manhattan will be on-site, requiring only one area of westbound and eastbound lane closures.

Next week, crews will be on-site Monday to Thursday from 6 a.m. to 6 p.m. and return on Wednesday, May 31, after the Memorial Day holiday weekend.

Drivers should anticipate minor travel delays due to lane closures and reduced speeds. Speeds are reduced through the construction zones. Please slow down and watch for workers and equipment. Montana Highway Patrol will be onsite monitoring traffic.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

May 12, 2023

Two separate crews will continue working to install the high-tension median cable rail along Interstate 90 (I 90) in the Bozeman area next week.

One crew will continue installing anchor posts between Manhattan and Belgrade. A second crew will lay out and install line posts between Three Forks and Manhattan.

Crews will be separated by at least five miles, and each work site will require lane closures. The westbound and eastbound left lanes will be closed closest to the median in both construction areas.

Speeds are reduced through the construction zones. Please slow down and watch for workers and equipment. Montana Highway Patrol will be onsite monitoring traffic. Drivers should anticipate minor travel delays due to lane closures and reduced speeds.

Next week, crews will be on-site Monday to Saturday, from 6 a.m. to 6 p.m. On Saturday, only the crew installing line posts will be on-site, requiring only one area of westbound and eastbound lane closures.

Remember the three Ss of work zone safety when traveling through the project sites: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

May 5, 2023

Coral Construction Company will have two crews working to install the high-tension median cable rail along Interstate 90 (I 90) in the Bozeman area next week, starting at Three Forks and working east to Belgrade.

One crew will continue installing anchor posts starting in the Manhattan area.

A second crew will begin laying out and installing line posts starting in the Three Forks area and working east.

Crews will be separated by at least five miles, and each work site will require lane closures. The westbound and eastbound left lanes will be closed closest to the median in both construction areas.

road work

Speeds are reduced through the construction zone. Please slow down and be mindful of workers, signage, and equipment. Drivers should anticipate minor travel delays due to lane closures and reduced speeds.

Next week, crews will be on-site Tuesday to Saturday, from 6 a.m. to 6 p.m. On Saturday, only the crew installing line posts will be on-site, requiring only one area of westbound and eastbound lane closures.

Remember the three Ss of work zone safety when traveling through the project sites: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

April 28, 2023

This week, Coral Construction Company will begin installing anchor posts for high-tension median cable rail along Interstate 90 (I 90) in the Bozeman area.

A crew will be on-site Monday to Friday, from 6 a.m. to 6 p.m. Installation work will begin at the west end of the project from Three Forks to Manhattan.

Traffic control will be on-site, speed limits will be reduced, and lane closures will begin. The westbound and eastbound left lanes will be closed closest to the median.

Drivers should anticipate minor travel delays due to lane closures and reduced speeds.

When traveling through the project sites, remember the three Ss of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

April 21, 2023

The Montana Department of Transportation (MDT) and Coral Construction Company will begin preparations for installing high-tension median cable rail along Interstate 90 (I 90) from Three Forks through the Bozeman area starting on Tuesday, April 25.

A crew will be on-site from Tuesday to Friday, from 6 a.m. to 6 p.m., doing pre-installation work in the highway median, starting at the west end of the project at Three Forks.

Minimal traffic disruption is anticipated. Travelers can expect traffic control on site, reduced speed limits, and shoulder closures during construction.

When traveling through the project site, remember the three Ss of work zone safety: speed, space, and stress. Slow down when approaching work zones and follow posted speed limits. Leave adequate braking room between your vehicle and the one ahead of you. Keep your cool, pay attention, and plan for delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.