Vision Zero Logo

Thank you Butte, Median High-Tension Cable Rail

November 22, 2024

The Montana Department of Transportation (MDT) and Coral Construction have completed median high-tension cable rail installation along more than 18 miles of Interstate 15 (I-15) and 14 miles of Interstate 90 (I-90) in the Butte area.

Thank you for your patience and support during this important safety improvement project!

Median high-tension cable rail has been proven to reduce the severity of crashes and prevent fatal crashes caused by vehicles crossing the median into oncoming traffic.

This project is the second phase of a four-phase safety improvement project that will install 150 miles of median high-tension cable rail along sections of I-90 in the Missoula, Butte, and Bozeman areas and I-15 in the Butte and Helena areas.

The Bozeman phase was completed in 2023. Construction of the Missoula phase began in September and is anticipated to be completed in 2026. A start date for construction of phase four, I-15 near Helena, has yet to be determined.

November 15, 2024

The Montana Department of Transportation (MDT) and Coral Construction will continue conducting cleanup activities throughout the project area along Interstate 90 (I-90) and Interstate 15 (I-15).

Crews will be onsite Saturday, November 16, and Monday, November 18, through Thursday, November 21, from 6 a.m. to 6 p.m.

Intermittent closures of the left lane closest to the median on Interstate 15 and Interstate 90 may be required where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Cleanup activities may also require the shoulder to be closed in select locations throughout the project area.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

November 8, 2024

The Montana Department of Transportation (MDT) and Coral Construction will continue installing and tensioning cable and conducting cleanup activities in the median of Interstate 15 (I-15) and Interstate 90 (I-90) from Tuesday, November 12, through Saturday, November 16.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

All work is subject to change due to weather and other unforeseen circumstances.

Crews will be onsite from 6 a.m. to 6 p.m.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

November 1, 2024

The Montana Department of Transportation (MDT) and Coral Construction will continue installing and tensioning cable rail and conducting clean-up activities in the median of Interstate 15 (I-15) and Interstate 90 (I-90) next week.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

All work is subject to change due to weather and other unforeseen circumstances.

Work is planned for the following areas:

I-90 from Burlington Street, east to mile marker 230, two miles east of the Continental Drive Exit: Crews will finish tensioning the cable and conduct clean-up activities in the median on Friday, November 8.

I-90 from the I-90/I-15 Interchange west to Whiskey Gulch: Crews will install and tension cable on Monday, November 4, through Wednesday, November 6.

I-15 from the I-90/I-15 Interchange north to Woodville: Crews will install and tension cable from Tuesday, November 5, through Thursday, November 7.

I-15 from the I-90/I-15 Interchange, south to Buxton: Crews will be tensioning cable on Thursday, November 7, and Friday, November 8.

Work will occur from 6 a.m. to 6 p.m.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

October 25, 2024

The Montana Department of Transportation (MDT) and Coral Construction will continue to conduct cleanup activities in the median of Interstate 15 (I-15) and Interstate 90 (I-90) throughout the project area on Monday, October 28, through Saturday, November 2.

Cable rail installation will also occur in the median of I-90 from the I-90/I-15 Interchange west to Whiskey Gulch on Saturday, November 2.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

October 18, 2024

The Montana Department of Transportation (MDT) and Coral Construction will conduct cleanup activities and seeding operations in the median of Interstate 15 (I-15) and Interstate 90 (I-90) throughout the project area tomorrow, Saturday, October 19, and Monday, October 21, through Friday, October 25.

Cable rail installation will also occur in the median of I-15 from the I-90/I-15 Interchange south to Buxton on Saturday, October 19, and Monday, October 21.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

October 11, 2024

Montana Department of Transportation (MDT) and Coral Construction continue cable rail installation in the median of Interstate 15 (I-15) from the Interstate 90 (I-90)/I-15 Interchange south to Buxton on Tuesday, October 15, through Friday, October 18.

Miscellaneous cleanup activities will also be underway in the median I-15 and I-90 throughout the project area on Tuesday, October 15, through Saturday, October 19.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

October 4, 2024

Montana Department of Transportation (MDT) and Coral Construction will continue to install cable rail in the median of Interstate 15 (I-15) from the Interstate 90 (I-90)/I-15 Interchange south to Buxton on Saturday, October 5, and Monday, October 7, through Tuesday, October 8.

Crews will also complete miscellaneous cleanup activities in the median I-15 and I-90 throughout the project area on Tuesday, October 8, through Friday, October 11.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

September 27, 2024

Montana Department of Transportation (MDT) and Coral Construction will continue to install cable rail in the median of Interstate 15 (I-15) from the Interstate 90 (I-90)/I-15 Interchange south to Buxton on Tuesday, October 1, through Saturday, October 5.

The left lanes closest to the median on both sides of I-15 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 5 a.m. to 5 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

September 20, 2024

Coral Construction will continue to install cable rail in the median of Interstate 90 (I-90) and Interstate 15 (I-15) next week.

The left lanes closest to the median on both sides of I-90 and I-15 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Work is planned for the following areas:

I-90 from mile marker 230, two miles east of the Continental Drive Exit, west to Rocker: Crews will be installing and tensioning cable and completing grading work tomorrow, Saturday, September 21, from 5 a.m. to 5 p.m.

I-15 from the I-90/I-15 Interchange north to Woodville: From Monday, September 23, through Wednesday, September 25, crews will install and tension cable from 5 a.m. to 5 p.m.

I-15 from the I-90/I-15 Interchange south to Buxton: Crews will install line posts and grade the road. Work will occur Wednesday, September 25, through Friday, September 27, from 5 a.m. to 5 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

September 13, 2024

Coral Construction will continue to install cable rail in the median of Interstate 90 (I-90) and Interstate 15 (I-15) next week.

The left lanes closest to the median on both sides of I-90 and I-15 will be closed where work is underway. Drivers should expect reduced speeds when passing through the work zone.

Work is planned for the following areas:

I-90 from Burlington Street, east to mile marker 230, two miles east of the Continental Drive Exit: Crews will be installing and tensioning cable Monday, September 16, through Saturday, September 21, from 5 a.m. to 5 p.m.

I-90 from the I-90/ I-15 Interchange, west to Rocker: Crews will be onsite Wednesday, September 18, through Saturday, September 21, during night and early morning hours, from midnight to 10 a.m.

I-90 between Rocker and the Anaconda Interchange: On Tuesday, September 17, crews will be installing and tensioning cable from 5 a.m. to 5 p.m.

I-15 from the I-90/I-15 Interchange, south to Buxton: Crews will complete terminal end anchor installation on Friday, September 20. Work will occur from 5 a.m. to 5 p.m. Terminal end anchors are where each end of a cable rail segment is bolted into the ground.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

September 6, 2024

Coral Construction will be installing and tensioning cable in the median of Interstate 90 (I-90) between Rocker and the Anaconda Interchange next week. Crews will also be installing guardrail in select areas throughout the project. Work will occur on Saturday, September 7, and Monday, September 9, through Friday, September 13.

Additionally, on Friday, September 13, crews will install end anchors on Interstate 15 (I-15) from the I-15/I-90 Interchange south to Buxton.

The left lanes closest to the median on both sides of I-90 and I-15 will be closed where work is underway.

Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 5 a.m. to 5 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

August 30, 2024

Labor Day Holiday: Work on the Butte Phase of the Median High-Tension Cable Rail project will pause starting Friday, August 30 through Tuesday, September 3, to accommodate increased holiday traffic. Crews will return on Wednesday, September 4.

When Coral Construction crews return, work will resume in the median of Interstate 90 (I-90) between Rocker and the Anaconda Interchange. Crews will be installing and tensioning cable on Wednesday, September 4, through Saturday, September 7.

Tensioning the cable will create a barrier that acts like a net, absorbing the energy created by the impact of a vehicle, and preventing it from crossing the median into oncoming traffic.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway.

Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

August 23, 2024

Coral Construction crews will be installing and tensioning cable in the median of Interstate 90 (I-90) the week of August 26. Tensioning the cable will create a barrier that acts like a net, absorbing the energy created by the impact of a vehicle and preventing it from crossing the median into oncoming traffic.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway.

Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 5 a.m. to 5 p.m.

Work will occur in the following areas:

I-90 from Burlington Street, east to mile marker 230, two miles east of the Continental Drive Exit: Crews will be installing and tensioning cable tomorrow, Saturday, August 24, Monday, August 26, and Tuesday, August 27.

I-90 from the I-90/Interstate15 (I-15) Interchange, west to Rocker: Work will occur Tuesday, August 27, through Thursday, August 29.

I-90 between Rocker and the Anaconda Interchange: Crews will be working in this segment on Wednesday, August 28, and Thursday, August 29.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

Labor Day Holiday: Work on the Butte Phase of the Median High-Tension Cable Rail project will pause from Friday, August 30 through Tuesday, September 3, to accommodate increased holiday traffic. Crews will return on Wednesday, September 4.

August 16, 2024

Coral Construction crews will be installing cable rail in the median of Interstate 90 (I-90) and Interstate 15 (I-15) the week of August 19.

The left lanes closest to the median on both sides of I-15 and I-90 will be closed where work is underway.

I-15 from the I-90/I-15 Interchange, north to Woodville: Crews will install line posts in this segment tomorrow, Saturday, August 17, Tuesday, August 20, and Wednesday, August 21.

I-90 from Burlington Street, east to mile marker 230, two miles east of the Continental Drive Exit: Crews will begin installing and tensioning cable on Thursday, August 22, through Saturday, August 24. Tensioning the cable will create a barrier that acts like a net, absorbing the energy created by the impact of a vehicle and preventing it from crossing the median into oncoming traffic.

Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 5 a.m. to 5 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

August 9, 2024

Coral Construction crews are expected to complete line post installation in the median of Interstate 90 (I-90) between Rocker and the Anaconda Interchange on Saturday, August 10.

Starting Monday, August 12 through Friday, August 16 line post installation will begin in the median of Interstate 15 (I-15) from the I-90/I-15 Interchange, north to Woodville.

The left lanes closest to the median on both sides of I-90 and I-15 will be closed where work is underway.

Drivers should expect reduced speeds when passing through the work zone.

Crews will be onsite from 5 a.m. to 5 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

Do not hesitate to reach out with any questions or concerns. Email me directly at sloaneXYZbigskypublicrelationsABCcom or call the project hotline at 406-207-4484, Monday to Friday, 9 a.m. to 5 p.m.

August 2, 2024

Coral Construction crews continue to make great progress. Next week they will continue installing line posts in the median of Interstate 90 (I-90) between Rocker and the Anaconda Interchange Tuesday, August 6 through Saturday, August 10. Crews will be onsite from 5 a.m. to 5 p.m.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway.

Drivers should expect reduced speeds when passing through the work zone.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

Do not hesitate to reach out with any questions or concerns. Email me directly at sloaneXYZbigskypublicrelationsABCcom or call the project hotline at 406-207-4484, Monday to Friday, 9 a.m. to 5 p.m.

July 26, 2024

Coral Construction crews will continue installing line posts in the median of Interstate 90 (I-90) between Rocker and the Anaconda Interchange tomorrow, Saturday, July 27, and Monday, July 29 through Thursday, August 1. Crews will be onsite from 6 a.m. to 6 p.m.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Travelers should expect reduced speeds when passing through the work zone.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

July 19, 2024

The Montana Department of Transportation (MDT) and Coral Construction crews will continue installing line posts in the median of Interstate 90 (I-90) the week of July 22.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Travelers should expect reduced speeds when passing through the work zone.

Next week, work will occur in the following areas:

I-90 from the I-90/Interstate15 (I-15) Interchange, west to Rocker: Crews will be onsite in this segment for one night and into the early morning hours on Tuesday, July 23.

I-90 between Rocker and the Anaconda Interchange: Crews will be onsite Tuesday, July 23, through Saturday, July 27, from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

July 12, 2024

The Montana Department of Transportation (MDT) and Coral Construction crews will resume line post installation in the median of Interstate 90 (I-90) the week of July 14.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Motorists should expect reduced speeds when passing through the work zone.

Next week, work will occur in the following areas:

I-90 from the I-90/Interstate15 (I-15) Interchange, west to Rocker: Crews will be onsite Sunday, July 14, through Tuesday, July 16, during night and early morning hours, from midnight to 10 a.m.

I-90 between Rocker and the Anaconda Interchange: Crews will be onsite Monday, July 15, through Thursday, July 18, from 6 a.m. to 6 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

July 5, 2024

Coral Construction will continue line post layout and installation work in the median of Interstate 90 (I-90), from the Interstate 15 (I-15)/I-90 Interchange, west to Rocker. Work will occur Monday, July 8, through Saturday, July 13 during night and early morning hours, from 10 p.m. to 1 p.m.

On Friday, July 12, crews will also install anchor ends on I-90 between Rocker and the Anaconda Interchange. Work will occur from 6 a.m. to 6 p.m.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

Please be mindful of workers and equipment throughout the project area. All work is dependent on weather and other unforeseen factors.

June 28, 2024

Coral Construction will pause construction activities on the Butte phase of the Median High-Tension Cable Rail project on Monday, July 1, and resume on Monday, July 8.

We hope you have a safe and happy Fourth of July!

June 21, 2024

Coral Construction crews continue line post layout and installation work in the median of Interstate 90 (I-90), from mile marker 230, 2 miles east of the Continental Drive Exit, west to the Interstate 15 (I-15)/I-90 Interchange (mile marker 227).

Crews will be onsite tomorrow, Saturday, June 22, and Monday, June 24, through Saturday, June 29, from 6 a.m. to 6 p.m.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Please be mindful of workers and equipment throughout the project area. All work is dependent on weather and other unforeseen factors.

Work on the Butte Phase of the Median High-Tension Cable Rail project will pause from Monday, July 1 through Monday, July 8, to accommodate increased holiday traffic. Crews will return on Tuesday, July 9.

June 14, 2024

Line post layout and installation will begin this week in the median of Interstate 90 (I-90), from 2 miles east of the Montana Highway 375 (MT 375) and Continental Drive Exit, west to the Interstate 15 (I-15)/I-90 Interchange.

Coral Construction crews will be onsite from Tuesday, June 18, through Saturday, June 22, from 6 a.m. to 6 p.m.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

All work is dependent on weather and other unforeseen factors.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

June 7, 2024

The Montana Department of Transportation (MDT) and Coral Construction will be installing terminal anchor ends in the median of Interstate 90 (I-90), from the Interstate 15 (I-15)/I-90 Interchange, west to Rocker the week of June 10.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

Crews will be onsite Monday, June 10, through Thursday, June 13. Work will occur during night and early morning hours, from midnight to 1 p.m.

All work is dependent on weather and other unforeseen factors.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

May 31, 2024

The Montana Department of Transportation (MDT) and Coral Construction crews will resume work on the Butte phase of the Median High-Tension Cable Rail project next week.

All work is subject to change due to weather and other unforeseen circumstances.

The left lanes closest to the median on both sides of Interstate 90 (I-90) and Interstate 15 (I-15) will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

Next week, work will occur in the following areas:

I-90 between Burlington Street and Continental Drive: Crews will install terminal anchor ends in the median Wednesday, June 5, through Friday, June 7, from 6 a.m. to 6 p.m.

I-15 from Woodville to the I-15/I-90 Interchange: Crews will install terminal anchor ends in the median of I-15 on Tuesday, June 4, and Wednesday, June 5, from 6 a.m. to 6 p.m.

I-15 from the I-15/I-90 Interchange to Buxton: Grading operations will in the median from Wednesday, June 5, through Friday, June 7, from 6 a.m. to 6 p.m.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

May 17, 2024

The Montana Department of Transportation (MDT) and Coral Construction have briefly paused work on the Butte phase of the Median Cable Rail project.

Crews will tentatively return in early June. Project updates will resume before work begins again.

May 10, 2024

The Montana Department of Transportation (MDT) and Coral Construction crews will begin installing terminal end anchors and continue grading operations on the Butte phase of the Median Cable Rail project next week.

All work is subject to change due to weather and other unforeseen circumstances.

The left lanes closest to the median on both sides of Interstate 90 (I-90) and Interstate 15 (I-15) will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

Next week, work will occur in the following areas:

I-90 between Burlington Street and Continental Drive: Crews will install terminal anchor ends in the median from Tuesday, May 14, through Thursday, May 16, from 6 a.m. to 6 p.m.

I-90 between the 1-15 North and 1-90 Interchange, and the I-15 South and I-90 Interchange: Terminal anchor end installation will occur in the median of I-90 on Thursday, May 16, and Friday, May 17, from 2 a.m. to 6 p.m. Crews will move the location where they are working to accommodate periods of increased traffic.

I-15 from Woodville, south to the I-15 North and 1-90 Interchange: Crews will install terminal anchor ends in the median of I-15 on Monday, May 13, and Tuesday, May 14, from 6 a.m. to 6 p.m.

I-15 from the I-15 South and I-90 Interchange, south to Buxton: Grading operations will be underway in the I-15 median from Monday, May 13, through Friday, May 17, from 6 a.m. to 6 p.m.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

May 3, 2024

The Montana Department of Transportation (MDT) and Coral Construction crews will continue grading operations in the median of Interstate 15 (I-15), from the I-15 South and Interstate 90 (I-90) Interchange, south to Buxton.

Crews will be onsite, Monday, May 6, through Friday, May 10, from 7 a.m. to 5 p.m.

All work is subject to change due to weather and other unforeseen circumstances.

The left lanes closest to the median on both sides of I-15 will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

April 29, 2024

The Montana Department of Transportation (MDT) and Coral Construction crews will continue grading and seeding operations in the median next week, Monday, April 29 through Wednesday, April 1. Work will occur along Interstate 90 (I-90) from Whiskey Gulch, east to the Interstate 15 (I-15) South and I-90 interchange.

Crews will continue seeding work Thursday, May 2, and Friday, May 3, beginning near Butte and working east to the base of Homestake Pass.

The left lanes closest to the median on both sides of I-90 will be closed where work is underway. Motorists should expect reduced speeds when passing through active work zones.

Crews will be on-site Monday through Friday, from 7 a.m. to 5 p.m. All work is subject to change due to weather and other unforeseen circumstances.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

April 19, 2024

Coral Construction continues work on the Butte area phase of the Median High-Tension Cable Rail project.

Grading operations will continue in select areas of the median along Interstate 90 (I-90) and Interstate 15 (I-15) from April 22 through May 3, in preparation for anchor and line post installation.

All work is subject to change due to weather and other unforeseen circumstances.

Crews will be on-site Monday through Friday, from 7 a.m. to 3 p.m.

Median and shoulder closures may be required where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

April 12, 2024

MDT and Coral Construction will resume work on the Butte area phase of the Median High-Tension Cable Rail project next week.

This construction season, crews plan to install cable rail along 18 miles of Interstate 15 (I-15), starting at the Buxton Interchange (mile marker 116) and extending north, ending on Butte Hill (mile marker 134). Work will occur on Interstate 90 (I-90) from the Anaconda Interchange (mile marker 219), extending east for 14 miles to the base of Homestake Pass (mile marker 230), ending two miles east of the Montana Highway 375 (MT 375) and Continental Drive Exit.

Work will begin with crews installing traffic control signs along I-90 and I-15, and grading select areas of the median along I-90 in preparation for anchor and line post installation.

Median and shoulder closures may be required where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area.

MDT anticipates minimal travel impacts. Motorists should expect minor delays, single-lane closures, and reduced speeds when passing through active work zones.

Crews will be on-site Monday through Saturday and occasionally during nighttime hours. Work is expected to be completed this year. This schedule is subject to change due to weather and other unforeseen circumstances.

October 27, 2023

The Montana Department of Transportation (MDT) and Coral Construction have paused work on the Median High-Tension Cable Rail project in the Butte area until spring.

Crews were able to complete terminal end anchor installation on Interstate 15 (I 15), north of the I 15 and Interstate 90 (I 90) Interchange this fall in preparation for the 2024 construction season.

MDT looks forward to completing this important safety improvement project next year. Updates will be provided as 2024 work approaches.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 20, 2023

Due to weather, Coral Construction will pause work on the Median High-Tension Cable Rail Project in the Butte area next week.

Crews are installing anchor posts today, Friday, October 20, from 6 a.m. to 6 p.m., on Interstate 90 (I 90), from just east of the Interstate 115 (I 115) City Center Exit, to the east end of the project two miles east of the Montana Highway 375 (MT 375) and Continental Drive Exit.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 13, 2023

The Median High-Tension Cable Rail project is underway in the Butte area. Coral Construction crews will begin installing anchor posts in the median of Interstate 15 (I 15) and Interstate 90 (I 90) next week.

Crews will be working on I 15 North, north of the I 15 North and I 90 Interchange, on Tuesday, October 17, through Thursday, October 19, from 6 a.m. to 6 p.m.

Anchor post installation on I 90 will begin just east of the Interstate 115 (I 115)/City Center Exit, to the east end of the project two miles east of the Montana Highway 375 (MT 375) and Continental Drive Exit. Crews will be onsite Friday, October 20, from 6 a.m. to 6 p.m.

The left lanes closest to the median on both sides of I 15 and I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

October 6, 2023

The Median High-Tension Cable Rail project will begin in the Butte area next week. Coral Construction crews will grade select areas in the median of Interstate 15 (I 15) and Interstate 90 (I 90).

Crews will be working on I 15 North, north of the I 15 North and I 90 Interchange, on Tuesday, October 10, and Wednesday, October 11, from 6 a.m. to 6 p.m.

Work on I 90 will occur just east of the Interstate 115 (I115)/City Center Exit, to the east end of the project two miles east of the Montana Highway 375 (MT 375) and Continental Drive Exit. Crews will be onsite Thursday, October 12, and Friday, October 13, from 6 a.m. to 6 p.m.

The left lanes closest to the median on both sides of I 15 and I 90 will be closed where work is underway.

Please slow down, follow traffic control, and watch for workers and equipment throughout the project area. Drivers should anticipate single-lane traffic, reduced speeds, and minor travel delays.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.

September 29, 2023

The Butte phase of the Median High-Tension Cable Rail project is anticipated to begin the week of October 9.

Coral Construction crews will be grading select areas in the median of Interstate 15 (I 15), north of the I 15 North and Interstate 90 (I 90) interchange, and I 90 on the east side of Butte.

More project details will be provided in next week's update.

Once construction begins, drivers should anticipate single-lane traffic and reduced speeds.

Remember, when traveling through a construction zone, slow down, follow traffic control, and watch for workers and equipment throughout the project area.

If you have questions or comments, please do not hesitate to share them with us by emailing Sloane at sloaneXYZbigskypublicrelationsABCcom or calling the project hotline at 406-207-4484 during business hours.