Havre logo

Week of September 14, 2025

This week:

  • Gravel work is complete at the south end of the project, and Riverside Contracting, Inc. will continue laying finished gravel north of the junction of South Secondary Highway 233, heading north.
  • Milling continues at approximately mile marker 4, heading north. Two-way traffic at reduced speeds (35 mph) has resumed at the south end of the project with a pilot car and signal lights stationed at the north end.
  • The contractor will continue constructing foundations for the new roadway with heavy equipment and trucking operations. This work will occur between mile markers 4 and 7, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • Speed limit is 35 mph in unpaved areas with pilot cars guiding traffic through active work zones.
  • Travelers can expect wait times of approximately 15 minutes at the signal light and a total delay time of approximately 30 minutes. Please plan ahead and allow for extra travel time.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work 6 a.m. to 6:30 p.m. Monday through Friday and occasionally on Saturdays as needed, weather and other unforeseen factors permitting.

Week of September 7, 2025

This week:

  • Riverside Contracting, Inc. will continue laying finished gravel toward the south end of the project, milling at approximately mile marker 6, heading north. Once this work is complete, two-way traffic will resume at reduced speeds (35 mph) with no pilot car or signal lights situated at the south end of the project.
  • The contractor will continue constructing foundations for the new roadway with heavy equipment and trucking operations. This work will occur between mile markers 4 and 7, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • Speed limit is 35 mph in unpaved areas with pilot cars guiding traffic through active work zones.
  • Travelers can expect wait times of approximately 15 minutes at the signal light and a total delay time of approximately 30 minutes. Please plan ahead and allow for extra travel time.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work 6 a.m. to 6:30 p.m. Monday through Friday and occasionally on Saturdays as needed, weather and other unforeseen factors permitting.

Week of August 31, 2025

This week:

  • Riverside Contracting, Inc. will begin laying finished gravel toward the south end of the project and will continue milling at approximately mile marker 4, heading north.
  • Pilot cars and signal lights will be utilized for the first 2 miles of the project (south end) and also from mile markers 3 to 7. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Reduced speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light and a total delay time of approximately 30 minutes. Please plan ahead and allow for extra travel time.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will resume work on Tuesday, September 2, and will observe normal work hours the rest of the week (7 a.m. to 5 p.m), weather and other unforeseen factors permitting.

Week of August 24, 2025

This week:

  • Riverside Contracting, Inc. will continue milling at approximately mile marker 3, heading north.
  • Pilot cars and signal lights will be utilized for the first 2 miles of the project (south end) and also from mile markers 3 to 7. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • Crews will continue installing pipe starting at mile marker 4, heading north; watch for directional signage and detours.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light and a total delay time of approximately 30 minutes. Please plan ahead and allow for extra travel time.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • In observance of Labor Day, crews will pause construction activities at 5 p.m. on Thursday, August 28 (no work Friday through Monday), and will resume on Tuesday, September 2.

Week of August 17, 2025

This week:

  • Riverside Contracting, Inc. will begin milling at approximately mile marker 3, heading north.
  • Pilot cars and signal lights will be utilized for the first 2 miles of the project (south end) and also from mile markers 3 to 7. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • Crews will continue installing pipe between mile posts 4 and 6; watch for directional signage and detours.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light. Parents and students traveling to and from school should allow for extra travel time.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of August 10, 2025

This week:

  • Riverside Contracting, Inc. will continue laying gravel at the south end of the project moving north.
  • Crews will continue installing pipe between mile posts 4 and 6; watch for directional signage and detours.
  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of August 3, 2025

This week:

  • Riverside Contracting, Inc. will continue laying gravel at the south end of the project moving north.
  • Crews will continue installing pipe between mile posts 4 and 6; watch for directional signage and detours.
  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of July 27, 2025

This week:

  • Riverside Contracting, Inc. plans to start laying gravel at the south end of the project moving north.
  • Crews will continue installing pipe between mile posts 4 and 6; watch for directional signage and detours.
  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of July 20, 2025

This week:

  • Crews will be installing pipe intermittently between mile posts 4 and 6; watch for directional signage and detours.
  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 2 to 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of July 13, 2025

This week:

  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue stripping topsoil and constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of July 6, 2025

This week:

  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue stripping topsoil and constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • To accommodate holiday traffic, there will be no construction Thursday, July 3, through Sunday, July 6. Work will resume Monday, July 7.

Week of June 29, 2025

This week:

  • Milling will continue from mile marker 2 going south.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue stripping topsoil and constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday and Tuesday, weather and other unforeseen factors permitting.
  • To accommodate holiday traffic, there will be no construction Wednesday, July 3, through Sunday, July 6. Work will resume Monday, July 7.

Week of June 22, 2025

This week:

  • Depending on weather and roadway conditions, milling will continue near the southern end of the project, continuing north toward the intersection of Wild Horse Trail and Saint Joe Road.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. Timed signals controlling single-lane traffic may be intermittent during nighttime hours. Otherwise, travelers can expect two-lane traffic overnight.
  • The contractor will continue stripping topsoil and constructing foundations adjacent to the roadway with trucking operations. This work will occur approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect wait times of approximately 15 minutes at the signal light.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of June 15, 2025

This week:

  • Depending on weather and roadway conditions, milling will continue near the southern end of the project, continuing north toward the intersection of Wild Horse Trail and Saint Joe Road.
  • A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours. The pilot car may be intermittent during nighttime hours. Otherwise travelers can expect single-lane, two-way traffic controlled by timed traffic signals.
  • The contractor will continue stripping topsoil approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.

Traffic Control

  • Please watch for reduced speeds, trucks entering the roadway, and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect 15-minute maximum wait times at the signal light.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of June 8, 2025

This week:

  • The contractor will continue stripping topsoil approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.
  • Milling will begin near the southern end of the project and head north toward the intersection of Wild Horse Trail and Saint Joe Road. A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles during daylight hours.
  • At nighttime, travelers can expect single-lane, two-way traffic controlled by timed traffic signals between mileposts 2 and 3.

Traffic Control

  • Please watch for reduced speeds and signal lights in the construction zone.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone. Speed zones will align with roadway work and will be approximately 2 miles in length.
  • Travelers can expect 15-minute maximum wait times at the signal light.
  • No width restrictions are in place at this time, however, wide loads may be delayed and should call ahead to 406-853-5392.
  • Those traveling on motorcycles may want to consider an alternate route.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of June 1, 2025

This week:

  • The contractor will continue stripping topsoil approximately 4 miles north of the intersection at Wild Horse Trail and Saint Joe Road, moving north.
  • Milling will begin near the southern end of the project and head north toward the intersection of Wild Horse Trail and Saint Joe Road. A pilot car and signal lights will be situated approximately 2 miles south of the milled area and will continue for approximately 2 miles.
  • The speed limit will be 35 mph following the pilot car with speeds returning to 55 mph outside the work zone.
  • Speed zones will align with roadway work and will be approximately 2 miles in length.

Traffic Control

  • Please watch for reduced speeds and signal lights in the construction zone. Travelers can expect 10- to 12-minute maximum wait times at the signal light.
  • No width restrictions are in place at this time; however, wide loads may be delayed and should call ahead to 406-853-5392.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., Monday through Friday, weather and other unforeseen factors permitting.

Week of May 25, 2025

This week:

  • The contractor will continue stripping topsoil approximately 1 to 2 miles north and south of the intersection at Wild Horse Trail and Saint Joe Road.
  • Stripping work will continue in these respective directions with work zones situated at approximately 1-mile increments.
  • Speed zones will align with roadway work and will be approximately 1 mile in length.

Traffic Control

  • Please watch for reduced speeds in the construction zone.
  • No width restrictions are in place at this time.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., weather and other unforseen factors permitting.
  • To accommodate holiday traffic, crews will be off the road starting at noon on Friday, May 23. There will be no construction on Memorial Day, Monday, May 26. Work will resume Tuesday, May 27.

Week of May 18, 2025

This week:

  • The contractor will continue stripping topsoil approximately 1 to 2 miles north and south of the intersection at Wild Horse Trail and Saint Joe Road.
  • Stripping work will continue in these respective directions with work zones situated at approximately 1-mile increments.
  • Speed zones will align with roadway work and will be approximately 1 mile in length.

Traffic Control

  • Please watch for reduced speeds in the construction zone.
  • No width restrictions are in place at this time.

Construction Schedule

  • Crews will work from 7 a.m. to 6 p.m., weather and other unforseen factors permitting.
  • To accommodate holiday traffic, crews will be off the road starting at noon on Friday, May 23. There will be no construction on Memorial Day, Monday, May 26. Work will resume Tuesday, May 27.

Week of May 11, 2025

This week:

  • The contractor will begin stripping topsoil approximately 1 mile north and ½ mile south of the intersection at Wild Horse Trail and Saint Joe Road.
  • Stripping work will continue in these respective directions with work zones situated at approximately 1-mile increments.
  • Speed zones will align with roadway work and will be approximately 1 mile in length.

Traffic Control

  • Please watch for reduced speeds in the construction zone.
  • No width restrictions are in place at this time.

Construction Schedule

  • Crews will work from 7 a.m. to 5 p.m., weather and other unforeseen factors permitting.